Question

A project will cost $95,000 today and there will be an additional cost in year 3...

A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000.  The project will have the following projected cash flows:

            Yr                                Cash Flow

            1                                  $30,000

            2                                  $50,000

            3                                  $0

            4                                  $50,000

The discount rate is 14%.  Calculate the modified internal rate of return.  Do you accept or reject?  (Must have correct set-up and your answer should be between two consecutive whole percentages.)

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Please refer to below spreadsheet for calculation and answer. Cell reference also provided.

A В C D 1 2 Cash Flow Year -$95,000.00 3 0 $30,000.00 4 1 $50,000.00 5 2 -$15,000.00 6 $50,000.00 7 4 9 Discount rate 14% 10

Cell reference -

А В C 1 2 Cash Flow Year -95000 0 1 4 30000 2 50000 -15000 6 50000 4 7 0.14 9 Discount rate 10 Modified internal rate of retu

Please note: Project has been rejected because it's modified IRR is less than its required return (discount rate).

Hope this will help, please do comment if you need any further explanation. Your feedback would be highly appreciated.

Add a comment
Know the answer?
Add Answer to:
A project will cost $95,000 today and there will be an additional cost in year 3...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Yr 5. A project will cost $95,000 today and there will be an additional cost in...

    Yr 5. A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000. The project will have the following projected cash flows: Cash Flow $30,000 $50,000 $0 $50,000 The discount rate is 14% Calculate the modified internal rate of return. Do you accept or reject? (Must have correct set-up and your answer should be between two consecutive whole percentages.)

  • please show all the steps and formula 1. DUULIUL LUI . ILUOPUITUJOUL. 5. A project will...

    please show all the steps and formula 1. DUULIUL LUI . ILUOPUITUJOUL. 5. A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000. The project will have the following projected cash flows: Cash Flow $30,000 $50,000 $0 $50,000 The discount rate is 14%. Calculate the modified internal rate of return. Do you accept or reject? (Must have correct set-up and your answer should be between two consecutive whole percentages.)

  • make sure you show all the steps 1. DUULIUL LUI . ILUOPUITUJOUL. 5. A project will...

    make sure you show all the steps 1. DUULIUL LUI . ILUOPUITUJOUL. 5. A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000. The project will have the following projected cash flows: Cash Flow $30,000 $50,000 $0 $50,000 The discount rate is 14%. Calculate the modified internal rate of return. Do you accept or reject? (Must have correct set-up and your answer should be between two consecutive whole percentages.)

  • Provide your solutions in sequential order below the line. Round final answer to the nearest hundredth....

    Provide your solutions in sequential order below the line. Round final answer to the nearest hundredth. Show all work and circle your final answer. You are analyzing a project which has a $20,000 sunk cost. The project's cost is $150,000 and the expected cash flows are: (Use this info for questions #1-4) Year 1: $60,000 Year 2: $0 Year 3: $100,000 Year 4: $0 Year 5: $60,000 The discount rate is 18% (the required return is also 18%). The required...

  • You are analyzing a project which has a $20,000 sunk cost. The project’s cost is $150,000...

    You are analyzing a project which has a $20,000 sunk cost. The project’s cost is $150,000 and the expected cash flows are: (Use this info for questions #1-4)             Year 1: $60,000             Year 2: $0             Year 3: $100,000             Year 4: $0             Year 5: $60,000 The discount rate is 18% (the required return is also 18%). The required payback is 2.3 years. 1. Calculate the internal rate of return (must have correct set-up and your answer should be between two consecutive whole...

  • Net present value. Lepton Industries has a project with the following projected cash flows: 3: a....

    Net present value. Lepton Industries has a project with the following projected cash flows: 3: a. Using a discount rate of 12% for this project and the NPV model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 17%? c. Should the company accept or reject it using a discount rate of 22%? a. Using a discount rate of 12%, this project should be . (Select...

  • 4. Lepton Industries has a project with the following projected cash flows: Initial Cost, Year 0:...

    4. Lepton Industries has a project with the following projected cash flows: Initial Cost, Year 0: $468,000 Cash flow year one: $135,000 Cash flow year two: $240,000 Cash flow year three: $185,000 Cash flow year four: $135,000 Plot the NPV profile of this project in Excel. Start with discount rate equal to zero and increase the discount rate by 2% increments until discount rate equal to 30%. For what discount rates would Lepton accept this project? For what discount rates...

  • Net present value. Lepton Industries has a project with the following projected cash flows: a. Using...

    Net present value. Lepton Industries has a project with the following projected cash flows: a. Using a discount rate of 10% for this project and the NPV model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 17%? c. Should the company accept or reject it using a discount rate of 20%? a. Using a discount rate of 10%, this project should be V. (Select from...

  • P9-8 (similar to) EQuestion Help Net present value. Lepton Industries has a project with the following...

    P9-8 (similar to) EQuestion Help Net present value. Lepton Industries has a project with the following projected cash flows: a. Using a discount rate of 9% for this project and the NPV model, determine whether the company should accept or reject this project b. Should the company accept or reject it using a discount rate of 17% ? c. Should the company accept or reject it using a discount rate of 20 %? . (Select from the drop-down menu.) a....

  • 1. A firm is starting a new project that will cost $200,000. It is projected to...

    1. A firm is starting a new project that will cost $200,000. It is projected to last 5 years and to generate cash flows of $50,000, $70,000, $90,000, $50,000 and $30,000 from Years 1 through 5 respectively. If the discount rate is 10%, what is the payback period of this project? Round to the second decimal place. Type only numbers without any unit ($, %, etc.) 2. A firm is starting a new project that will cost $200,000. It is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT