As per rules I am answering the first 4 subparts of the question
Sub Part | |||
1 | IRR | 14.36% | Reject since IRR is less than cost of capital |
2 | Discounted Payback | Never | Reject since Discounted Payback is never |
3 | Payback | 2.90 | reject since Payback period is more than that required |
4 | NPV | -12062.90 | reject since NPV is negative |
Workings
Year | Cash flows | Cumulative CF | DCF | Cumulative DCF |
0 | -150000 | -150000 | -150000.00 | -150000.00 |
1 | 60000 | -90000 | 50847.46 | -99152.54 |
2 | 0 | -90000 | 0.00 | -99152.54 |
3 | 100000 | 10000 | 60863.09 | -38289.46 |
4 | 0 | 10000 | 0.00 | -38289.46 |
5 | 60000 | 70000 | 26226.55 | -12062.90 |
Provide your solutions in sequential order below the line. Round final answer to the nearest hundredth....
You are analyzing a project which has a $20,000 sunk cost. The project’s cost is $150,000 and the expected cash flows are: (Use this info for questions #1-4) Year 1: $60,000 Year 2: $0 Year 3: $100,000 Year 4: $0 Year 5: $60,000 The discount rate is 18% (the required return is also 18%). The required payback is 2.3 years. 1. Calculate the internal rate of return (must have correct set-up and your answer should be between two consecutive whole...
Yr 5. A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000. The project will have the following projected cash flows: Cash Flow $30,000 $50,000 $0 $50,000 The discount rate is 14% Calculate the modified internal rate of return. Do you accept or reject? (Must have correct set-up and your answer should be between two consecutive whole percentages.)
A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000. The project will have the following projected cash flows: Yr Cash Flow 1 $30,000 2 $50,000 3 $0 4 $50,000 The discount rate is 14%. Calculate the modified internal rate of return. Do you accept or reject? (Must have correct set-up and your answer should be between two consecutive whole percentages.)
please show all the steps and formula
1. DUULIUL LUI . ILUOPUITUJOUL. 5. A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000. The project will have the following projected cash flows: Cash Flow $30,000 $50,000 $0 $50,000 The discount rate is 14%. Calculate the modified internal rate of return. Do you accept or reject? (Must have correct set-up and your answer should be between two consecutive whole percentages.)
make sure you show all the steps
1. DUULIUL LUI . ILUOPUITUJOUL. 5. A project will cost $95,000 today and there will be an additional cost in year 3 of $15,000. The project will have the following projected cash flows: Cash Flow $30,000 $50,000 $0 $50,000 The discount rate is 14%. Calculate the modified internal rate of return. Do you accept or reject? (Must have correct set-up and your answer should be between two consecutive whole percentages.)
Your first assignment in your new position as assistant financial analyst at Caledonia Products is to evaluate two new capital-budgeting proposals. Because this is your first assignment, you have been asked not only to provide a recommendation but also to respond to a number of questions aimed at assessing your understanding of the capital-budgeting process. This is a standard procedure for all new financial analysts at Caledonia, and it will serve to determine whether you are moved directly into the...
Use the following for Questions 1 - 5: You are considering two mutually exclusive projects, A and B. Project A costs $60,000 and generates cash flows of $9,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for seven years and then cash flows of $27,000 for three years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% Question 1 (3 points) Calculate what discount rate would make you indifferent between choosing...
Project A is currently being considered by your company. It has the following projected cash flows: Year Project A 0 -$300,000 1 90,000 2 90,000 3 110,000 4 110,000 The required rate of return for this project is 10 percent. Payback Period: Hurdle rate: 3.25 years Document the number of years (and partial years you calculate for it to payback for full or partial credit. Accept or Reject?
1. The most popular capital budgeting techniques used in practice to evaluate and select projects are payback period, Net Present Value (NPV), and Internal Rate of Return (IRR). 2. Payback period is the number of years required for a company to recover the initial investment cost. 3. Net Present Value (NPV) technique: NPV is found by subtracting a project’s initial cost of investment from the present value of its cash flows discounted using the firm’s weighted average cost of capital....
how
would u answer this on a calculator ?
- 4 8 x 8 30 2. Project LMK requires an initial outlay of $375,000 and it is expected to generate annual cash flows of 4 N $60,000 each year for the next 5 years (years 1 through 5) and $50,000 each year over the following 5 W years (years 6 through 10). The required return for this project is 18%. Calculate the following for Project MLK: The payback period The...