Question

Charps-in-the-Bag Inc is considering two projects Project A will cost $1,098,000 and yield annual project cash flows of $491,

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The NPV of the project is computed as shown below:

= Initial investment + Present value of future cash flows

Present value of future cash flows is computed as follows:

= Future value / (1 + r)n

NPV of project A is computed as follows:

= - $ 1,098,000 + $ 491,000 / 1.15 + $ 491,000 / 1.152 + $ 491,000 / 1.153

= $ 23,063.53 Approximately

NPV of project B is computed as follows:

= - $ 359,000 + $ 128,000 / 1.15 + $ 128,000 / 1.152 + $ 128,000 / 1.153 + $ 128,000 / 1.154 + $ 43,000 / 1.155

= $ 27,815.83 Approximately

Hence the correct answer is option of Accept project B, its NPV is $ 27,815.83.

Feel free to ask in case of any query relating to this question

Add a comment
Answer #2

ygygygygkyugkuku

Add a comment
Answer #3

phasmatos incidia

Add a comment
Know the answer?
Add Answer to:
Charps-in-the-Bag Inc is considering two projects Project A will cost $1,098,000 and yield annual project cash...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Considering the following two projects, if the WACC =10%, then I should: Project Year 0 1...

    Considering the following two projects, if the WACC =10%, then I should: Project Year 0 1 2 3 4 A Cash flows -$100 $50 $60 $70 $80 B Cash flows -$100 $50 $50 $50 $50 Accept project A since its NPV = $102.27 is higher than project B’s NPV = $58.49 Accept project B since its NPV = $102.27 is higher than project A’s NPV = $58.49 Project A’s NPV = - $102.27. Thus, I shall reject project A and...

  • 28. You are considering two independent projects. Project A has an initial cost of $125,000 and...

    28. You are considering two independent projects. Project A has an initial cost of $125,000 and cash inflows of $46,000, $79,000, and $51,000. Project B costs $135,000 with expected cash flows of $50,000, $30,000, and $100,000. The required rate of return for both projects is 15%. Based on IRR, you should: (SHOW WORK) A) accept both projects B) accept Project A and reject Project B C) accept Project B and reject Project A D) reject both projects E) accept either...

  • The following are the cash flows of two projects: Year Project $(370) 200 Proiect B $...

    The following are the cash flows of two projects: Year Project $(370) 200 Proiect B $ (370) 270 209 270 280 270 200 a:Calculate the NPV for both projects if the opportunity cost of capital is 15% (Do not round intermediate calculations. Round your answers to 2 decimal places.) NPV Project A B b. Suppose that you can choose only one of these projects. Which would you choose? Project A Neither Project B

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. 0 Time: 43,000 Project A 33,000 23,000 Flow Project B 43,000 23,000 33,000 63,000 Cash Flow Use the discounted payback decision rule to evaluate these projects; which one(s) should...

  • Suppose Hungry Whale Electronics is evaluating a proposed capital budgeting project (project Beta) that will require...

    Suppose Hungry Whale Electronics is evaluating a proposed capital budgeting project (project Beta) that will require an initial Investment of $2,500,000. The project is expected to generate the following net cash flows: Year Year 1 Year 2 Year 3 Year 4 Cash Flow $325,000 $450,000 $500,000 $400,000 Hungry Whale Electronics's weighted average cost of capital is 9%, and project Beta has the same risk as the firm's average project. Based on the cash flows, what is project Beta's NPV? O...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0123 Project -35,000 25,000 45,000 16,000 A Cash Flow Project -45,000 25,000 35,000 B Cash Flow Use the NPV decision rule to evaluate these projects; which one(s) should...

  • Suppose Blue Hamster Manufacturing Inc. is evaluating a proposed capital budgeting project (project Beta) that will...

    Suppose Blue Hamster Manufacturing Inc. is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $2,500,000. The project is expected to generate the following net cash flows: Cash Flow Year Year 1 $325,000 $500,000 Year 2 $475,000 Year 3 $500,000 4 Blue Hamster Manufacturing Inc.'s weighted average cost of capital is 10%, and project Beta has the same risk as the firm's average project. Based on the cash flows, what is project Beta's NPV?...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 1 2 3 14,000 34,000 Project A Cash Flow 24,000 5,000 24,000 Project B Cash Flow -34,000 14,000 54,000 Use the NPV decision rule to evaluate these projects;...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0 1 2 3 Project A Cash Flow -30,000 20,000 40,000 11,000 Project B Cash Flow -40,000 20,000 30,000 60,000 Use the NPV decision rule to evaluate these...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -37,000 27,000 47,000 18,000   Project B Cash Flow -47,000 27,000 37,000 67,000 Use the NPV decision rule to evaluate these...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT