Question

13. Cost-Cutting Proposals Starset Machine Shop is clsidering a 4-year project to improve its production efficiency. Buying a

Q 13/14 are related witount excal
0 0
Add a comment Improve this question Transcribed image text
Answer #1

13

Time line 0 1 2 3 4
Cost of new machine -670000
Initial working capital -20000
=Initial Investment outlay -690000
5 years MACR rate 20.00% 32.00% 19.20% 11.52% 17.28%
Savings 245000 245000 245000 245000
-Depreciation =Cost of machine*MACR% -134000 -214400 -128640 -77184 115776 =Salvage Value
-working capital to be maintained -2500 -2500 -2500 -2500
=Pretax cash flows 108500 28100 113860 165316
-taxes =(Pretax cash flows)*(1-tax) 83545 21637 87672.2 127293.32
+Depreciation 134000 214400 128640 77184
=after tax operating cash flow 217545 236037 216312.2 204477.32
reversal of working capital 30000
+Proceeds from sale of equipment after tax =selling price* ( 1 -tax rate) 42350
+Tax shield on salvage book value =Salvage value * tax rate 26628.48
=Terminal year after tax cash flows 98978.48
Total Cash flow for the period -690000 217545 236037 216312.2 303455.8
Discount factor= (1+discount rate)^corresponding period 1 1.08 1.1664 1.259712 1.360489
Discounted CF= Cashflow/discount factor -690000 201430.5556 202363.6831 171715.5985 223049.07
NPV= Sum of discounted CF= 108558.91

14

Time line 0 1 2 3 4
Cost of new machine -670000
Initial working capital -20000
=Initial Investment outlay -690000
100.00%
Savings 245000 245000 245000 245000
-Depreciation -670000 0 0 0 0 =Salvage Value
-working capital to be maintained -2500 -2500 -2500 -2500
=Pretax cash flows -427500 242500 242500 242500
-taxes =(Pretax cash flows)*(1-tax) -329175 186725 186725 186725
+Depreciation 670000 0 0 0
=after tax operating cash flow 340825 186725 186725 186725
reversal of working capital 30000
+Proceeds from sale of equipment after tax =selling price* ( 1 -tax rate) 42350
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 72350
Total Cash flow for the period -690000 340825 186725 186725 259075
Discount factor= (1+discount rate)^corresponding period 1 1.08 1.1664 1.259712 1.360489
Discounted CF= Cashflow/discount factor -690000 315578.7037 160086.5912 148228.3252 190427.86
NPV= Sum of discounted CF= 124321.48
Add a comment
Know the answer?
Add Answer to:
Q 13/14 are related witount excal 13. Cost-Cutting Proposals Starset Machine Shop is clsidering a 4-year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ch. 8 - Problems Problem 8-11 Cost-Cutting Proposals 10 points Blue Line Machine Shop is considering...

    Ch. 8 - Problems Problem 8-11 Cost-Cutting Proposals 10 points Blue Line Machine Shop is considering a four year project to improve its production efficiency Buying a new machine press for $490,000 is estimated to result in $200,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $82,000. The press also requires an initial investment in spare parts inventory of $22,000, along...

  • 8. ​​​​​​ Below is MACRS Schedule Problem 10-21 Cost-Cutting Proposals (LO2] Masters Machine Shop is considering...

    8. ​​​​​​ Below is MACRS Schedule Problem 10-21 Cost-Cutting Proposals (LO2] Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $480,000 is estimated to result in $202,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $73,000. The press also requires an initial investment in spare parts inventory of $39,000, along with...

  • Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new...

    Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new machine press for $480,000 is estimated to result in $202,000 in annual pretax cost savings. The press falls in the 5-year MACRS class, and it will have a salvage value at the end of the project of $73,000. The press also requires an initial investment in spare parts inventory of $39,000, along with an additional $4,050 in inventory for each succeeding year of the...

  • Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...

    Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600...

  • Buying a new machine press for $415,000 is estimated to result in $163,000 in annual pretax cost savings

    Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new machine press for $415,000 is estimated to result in $163,000 in annual pretax cost savings. The press falls in the 5-year MACRS class, and it will have a salvage value at the end of the project of $63,000. The press also requires an initial investment in spare parts inventory of $26,000, along with an additional $3,400 in inventory for each succeeding year of the...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $796800 is estimated to result in $265600 in annual pretax cost savings. The press falls in the MACRS (MACRS Table) five-year class and it will have a salvage value at the end of the project of $116200. The press also requires an initial investment in spare parts inventory of $33200, along with an additional $4980 in inventory for each succeeding year...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $445,000 is estimated to result in $181,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $73,000. The press also requires an initial investment in spare parts inventory of $32,000, along with an additional $3,700 in inventory for each succeeding year of the...

  • CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $395,000 is estimated to result in $144,000 in annual pretax cost savings. The press qualifies for 100 percent bonus depreciation, and it will have a salvage value at the end of the project of $45,000. The press also requires an initial investment in spare parts inventory of $15,000, along with an additional $2,000 in inventory for each succeeding year of the...

  • 10 Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a...

    10 Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $390,000 is estimated to result in $148,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $48,000. The press also requires an initial investment in spare parts inventory of $21,000, along with an additional $3,150 in inventory for each succeeding year of...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $470,000 is estimated to result in $196,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $72,000. The press also requires an initial investment in spare parts inventory of $37,000, along with an additional $3,950 in inventory for each succeeding year of the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT