NPV at 23% | 74.74 |
NPV at 41% | -5915.60 |
value factor = 1 /(1+r)^n
r is interest rate => 23% , 41% in the given case =>0.23, 0.41.
n =0,1,2,3.
the following table show the calculation of NPV:
year | cash flow | PV factor @23% | cash flow *PV factor | PV factor @41% | cash flow *PV factor |
0 | -30,000 | 1/(1.23)^0=>1 | -30,000*1=>-30,000 | 1/(1.41)^0=>1 | -30,000*1=>-30,000 |
1 | 19,000 | 1/(1.23)=>0.8130 | (19,000*0.8130)=>15,447 | 1/(1.41)=>0.7092 | 19,000*0.7092=>13,474.80 |
2 | 14,000 | 1/(1.23)^2=>0.6610 | (14,000*0.6610)=>9,254 | 1/(1.41)^2=>0.5030 | 14,000*0.5030=>7,042 |
3 | 10,000 | 1/(1.23)^3=>0.5374 | (10,000*0.5374)=>5,374 | 1/(1.23)^3=>0.3567 | 10,000*0.5374=>3,567 |
NPV | 75...(close to 74.74) | -5,916.20 ..(close to -5915.60) |
note: minor variations will arise due to rounding off of the PV factor to 4 decimals.
A firm evaluates all of its projects by using the NPV decision rule. Year WNO Cash...
A firm evaluates all of its projects by using the NPV decision rule. Year 0 WNO Cash Flow -$29,000 22,000 16,000 10,000 a. At a required return of 18 percent, what is the NPV for this project? $ 7,221" 7,582 $ 6,932 $ 7,366 $ 7,077 b. At a required return of 39 percent, what is the NPV for this project? CA $-1,226.38 $-1,121.26 $-1,191.34 $-1,144.62 $-1,167.98
A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow 0 –$30,000 1 21,000 2 15,000 3 10,000 a. At a required return of 23 percent, what is the NPV for this project? b. At a required return of 39 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule. At a required return on f 14 percent, what is the NPV for this project? At a required return of 37 percent, what is the NPV for this project? A firm evaluates all of its projects by using the NPV decision rule. Year WNO Cash Flow $31,000 20.000 14.000 11,000 a. At a required return of 14 percent, what is the NPV for this project? b. At...
A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow 0 –$25,000 1 20,000 2 17,000 3 8,000 Required: (a) At a required return of 24 percent, what is the NPV for this project? (Click to select)6,125.886,253.56,381.126,508.746,700.18 (b) At a required return of 40 percent, what is the NPV for this project? (Click to select)918.37874.64839.65892.13857.14
A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow 0 –$27,000 1 19,000 2 17,000 3 8,000 a. At a required return of 12 percent, what is the NPV for this project? b. At a required return of 39 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow 0 –$25,000 1 19,000 2 13,000 3 8,000 a. At a required return of 30 percent, what is the NPV for this project? b. At a required return of 39 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow 0 –$27,000 1 21,000 2 16,000 3 6,000 Required: (a) At a required return of 12 percent, what is the NPV for this project? (Click to select) 8,775.78 9,214.57 8,424.75 8,951.3 8,600.27 (b) At a required return of 40 percent, what is the NPV for this project? (Click to select) -1,617.14 -1,683.15 -1,650.15 -1,732.65 -1,584.14
A firm evaluates all of its projects by using the NPV decision rule. Year WNLO Cash Flow -$30,000 21,000 15,000 6,000 a. At a required return of 10 percent, what is the NPV for this project? b. At a required return of 36 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow 0 –$26,000 1 24,000 2 13,000 3 9,000 a. At a required return of 22 percent, what is the NPV for this project? b. At a required return of 35 percent, what is the NPV for this project?
A firm evaluates all of its projects by using the NPV decision rule. Year Cash Flow 0 –$29,000 1 21,000 2 15,000 3 4,000 a. At a required return of 17 percent, what is the NPV for this project? b. At a required return of 33 percent, what is the NPV for this project?