Answer
Actual Cost |
Standard Cost |
|||||||||
AQ |
x |
AP |
AQ |
x |
SP |
SQ |
x |
SP |
||
20,000 |
x |
$ 12.90 [258000/20000] |
20,000 |
x |
$ 12.80 |
22,800 [3800 x 6] |
x |
$ 12.80 |
||
$ 258,000.00 [20000 x 12.90] |
$ 256,000.00 |
$ 291,840.00 [22800 x 12.80] |
||||||||
Price Variance - Material |
$ 2,000.00 [258000 – 256000] |
Quantity Variance - Material |
$ 35,840.00 [291840 – 256000] |
Direct material Price Variance |
$ 2,000.00 |
Unfavourable |
Direct material Quantity Variance |
$ 35,840.00 |
Favourable |
Total Direct material Variance |
$ 33,840.00 |
Favourable |
0 Required information Use the following information for the Exercises below. [The following information applies to...
Required information Use the following information for the Exercises below. [The following information applies to the questions displayed below.] Hart Company made 4,600 bookshelves using 31,000 board feet of wood costing $359,600. The company's direct materials standards for one bookshelf are 7 board feet of wood at $11.50 per board foot. Exercise 21-13 Computation and interpretation of materials variances LO P2 (1) Compute the direct materials price and quantity variances incurred in manufacturing these bookshelves. AQ = Actual Quantity SQ...
Required information Use the following information for the Exercises below. [The following information applies to the questions displayed below.] Hart Company made 4,700 bookshelves using 36,000 board feet of wood costing $378,000. The company's direct materials standards for one bookshelf are 8 board feet of wood at $10.40 per board foot. Exercise 21-13 Computation and interpretation of materials variances LO P2 (1) Compute the direct materials price and quantity variances incurred in manufacturing these bookshelves. AQ = Actual Quantity SQ...
Required information [The following information applies to the questions displayed below.] Hart Company made 3,800 bookshelves using 20,000 board feet of wood costing $258,000. The company's direct materials standards for one bookshelf are 6 board feet of wood at $12.80 per board foot. (1) Compute the direct materials price and quantity variances incurred in manufacturing these bookshelves, AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP - Standard Price Actual Cost Standard Cost
Required information Use the following information for the Exercises below. [The following information applies to the questions displayed below.] Hart Company made 4,500 bookshelves using 21,000 board feet of wood costing $241,500. The company's direct materials standards for one bookshelf are 5 board feet of wood at $11.40 per board foot. Exercise 8.13 C。mputation and interpretation of materials variances LO P2 1) Compute the direct materials price and quantity variances incurred in manufacturing these bookshelves. AQ- Actual Quantity SQ Standard...
Use the following information for the Exercises below. [The following information applies to the questions displayed below.] Hart Company made 4,900 bookshelves using 22,000 board feet of wood costing $261,800. The company's direct materials standards for one bookshelf are 5 board feet of wood at $11.80 per board foot. Exercise 23-13 Computation and interpretation of materials variances LO P2 AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price (1) Compute the direct materials...
! Required information 2 (The following information applies to the questions displayed below.] Hart Company made 4,100 bookshelves using 23,000 board feet of wood costing $255,30o0. The company's direct materials standards for one bookshelf are 6 board feet of wood at $11.00 per board foot (1) Compute the direct materials price and quantity variances incurred in manufacturing these bookshelves. AQ Actual Quantity SQ Standard Quantity AP Actual Price SP Standard Price Actual Cost Standard Cost $ 0 0 EAEA !...
Help Save & Exit Submit Required information [The following information applies to the questions displayed below.] Hart Company made 4,400 bookshelves using 34,000 board feet of wood costing $387600. The company's direct materials standards for one bookshelf are 8 board feet of wood at $11.30 per board foot (1) Compute the direct materials price and quantity variances incurred in manufacturing these bookshelves. AQ Actual Quantity SQ Standard Quantity AP Actual Price SP Standard Price 5tandard Cost Actual Cost AQ SP...
Required information (The following information applies to the questions displayed below.) Hart Company made 3,160 bookshelves using 22,160 board feet of wood costing $285,864. The company's direct materials standards for one bookshelf are 8 board feet of wood at $12.80 per board foot. AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price (1) Compute the direct materials price and quantity variances and classify each as favorable or unfavorable. (2) Hart applies management by...
Check my work Hart Company made 5,000 bookshelves using 32,000 board feet of wood costing $384,000. The company's direct materials standards for one bookshelf are 7 board feet of wood at $11.90 per board foot. Part 1 of 2 Exercise 23-13 Computation and interpretation of materials variances LO P2 points AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price Skipped (1) Compute the direct materials price and quantity variances incurred in manufacturing these...
Required Information (The following information applies to the questions displayed below.) Hart Company made 3.220 bookshelves using 22,220 board feet of wood costing $293,304. The company's direct materials standards for one bookshelf are 8 board feet of wood at $13.10 per board foot. AQ = Actual Quantity SQ = Standard Quan AP = Actual Price SP - Standard Price (1) Compute the direct materials price and quantity variances and classify each as favorable or unfavorable. (2) Hart applies management by...