Present worth of all costs = 80b + 1b / 0.06 + 20b *(A/F,6%,10) / 0.06
= 80b + 1b / 0.06 + 20b *0.0759 / 0.06
= 121.97b
Present worth of all benefits = 9b / 0.06 = 150b
B/C ratio = Present worth of all benefits / Present worth of all costs
= 150b / 121.97b
= 1.23
As B/C is greater than 0, project is justified
6. The state of California is considering a Bullet Train (high speed rail) between LA and...
Exercise 6 - Time Value of Money Please complete the following: 1) read the case study on pp. 242-243 of the Weikart textbook and then answer the four questions near the bottom of p. 243, 2) assignment 11.1 on p. 244, and 3) assignment 12.1 on pp. 263-264 In the case study, you should end up with four different cost-benefit analyses along with a summary recommendation. For assignments 11.1 and 12.1, complete the calculation in Excel and then summarize your...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...
I need Summary of this Paper i dont need long summary i need What methodology they used , what is the purpose of this paper and some conclusions and contributes of this paper. I need this for my Finishing Project so i need this ASAP please ( IN 1-2-3 HOURS PLEASE !!!) Budgetary Policy and Economic Growth Errol D'Souza The share of capital expenditures in government expenditures has been slipping and the tax reforms have not yet improved the income...