Question

cost sheet for Largo Corp, showed the following material cost related to one unit of produet: 4pieces at $4 per piece $16 per unit During February 19X1,10,000 units were produced.The costs recorded showed the following Purchase of material 8000 pieces at $3.80 Issue of material 43,000 pieces Determine the material Give the significance and possible explanation of each materials variance What are some causes of unfavorable materials purchase price variances? The purchasing department of a large corporation using the responsibility accounting system purchase price variance and material quantity (usage) variance. delays placing an assembly department order for 10,000 parts at $2.00 each. By the time the additional charges incurred? Why? The standard cost sheet lor York Corp. shows the following cost for a unit of product price has risen to S220 Which department should be assigned the Direct labor: 2% hours at $7 an hour During February 19X1, 10,000 units were completed. The actual cost incurred was 28,000 hours at $8 per hour-$224,000 Determine the labor rate variance and labor efficiency variance . Give the significance and possible explanation of each labor variance Direct labor and variable overhead standards per finished unit for Century-Fox Metals Company are as follow: variable overhead, 10 hours at $2.00 per hour. During October,5,000 units were produced. Direct labor hours used were 52,000 bours Actual variable overbead costs were $109,200. Deterinine the spending variance and efficiency variance for variable overhead. Give the significance and possible explanation of each variable overbead variance E. T. Toys Inc. produces toys for national distibution. The management has recently established a standard cost system to control costs The standards on a particular toy are Materials Labor: 12 pieces per toy at $0.56 per piece 2 hours per toy at $3.75 per hour During the month of Fiebruary 19A, the company produced 1,000 toys Production data for the month are as follows Materials: 17500 pieces were purchased for use in production, at a toral cost of $8,925 of which 3,500 pieces were still in inventory at the end of the month - Labor: 2,500 hours were worked, at a cost of $10.500. (a) Calculate the materials purchase price variance b) Calculate the materials quantity (usage) variance (c) Calculate the labor rate variance (d) Cakulate the labor efficiency variance
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Material Purchase Price variance = (Standard Price – Actual Price)*Actual Quantity Purchased

= (4-3.80)*48,000

= 9,600 F

Material Usage Variance = (Standard Quantity – Actual Quantity)*Standard Price

= (10,000*4 – 43,000)*4

= 12,000 U

Material Purchase Price Variance is favorable which indicates that the actual price paid for material was less than the standard price set which is good for the company.

Possible Reasons are :

1.Change in Market Rate

2.Purchase of Lower Quality Material

Unfavorable Material Usage Variance indicates that the material used in the process is more than the standard quantity of material which should have been used.

Possible Reasons are:

1.Lower quality of material

2.Inefficient Labour

Labor rate Variance = (Standard Rate – Actual Rate)*Actual Hours

= (7-8)*28,000

= 28,000 U

Labor Efficiency Variance = (Standard Hours – Actual Hours)*Standard rate

= (2.75*10,000 – 28,000)*7

= 3,500 U

Both variances are unfavourable which indicates that the labor is paid at more than the standard rate and labor is inefficient as well i.e. it makes more than the standard time set for production.

a)Material Price Variance = (Standard Price – Actual Price)*Actual Quantity

= (0.56 – Actual Price)*17,500

= 9,800 – 8,925

= 875 F

Material Usage Variance = (Standard Quantity – Actual Quantity)*Standard Price

= (12*1,000 – 14,000)*0.56

= 1,120 U

Labor rate Variance = (Standard rate – Actual rate)*Actual Hours

= (3.75 – actual rate)*2,500

= 9,375 – 10,500

= 1,125 U

Labor Efficiency Variance = (Standard Hours – Actual Hours)*Standard Rate

= (2*1,000 – 2,500)*3.75

= 1,875 U

Add a comment
Know the answer?
Add Answer to:
cost sheet for Largo Corp, showed the following material cost related to one unit of produet:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Schock Manufacturing Company uses a standard cost system. The standards are set January 1 each...

    The Schock Manufacturing Company uses a standard cost system. The standards are set January 1 each year and remain unchanged until December 31 The standard costs set for the next year are: Diret materials S10.00 per unit Direct labor Overhead 7.50 per unit 600 per unit The labor standard above includes a methods change from 2 hours to 1% bours per unit, effective February 28, and a change in labor rates from $4.00 to $5,00 per hour effective February 28....

  • Cardinal Company has determined the following standard cost data necessary to manufacture one unit of its...

    Cardinal Company has determined the following standard cost data necessary to manufacture one unit of its primary product Direct Materials.... (6 pounds Direct labor. hours 520) 515) payroll costs for direct labor During 20X1. Cardinal produced only 1 unit of product. This unit required 7 pounds of direct material a total of pounds were purchased at a cost of $18 per pound. In addition to during 201 were 5130/10 hours $13 per hour) Required: Answer the following questions, indicating BOTH...

  • EXHIBIT 14.5 Standard Cost Sheet, Product XV-1 Subtotal Total SCHMIDT MACHINERY COMPANY Standard Cost Sheet Product:...

    EXHIBIT 14.5 Standard Cost Sheet, Product XV-1 Subtotal Total SCHMIDT MACHINERY COMPANY Standard Cost Sheet Product: XV-1 Descriptions Quantity Cost Rate Direct materials: Aluminum 4 pounds $25/pound PVC 1 pound 40/pound Direct labor 5 hours 40/hour Variable factory overhead 5 hours 12/hour Total variable manufacturing cost Fixed factory overhead* 5 hours 24/hour Standard manufacturing cost per unit Standard variable selling and administrative cost per unit $100 40 200 60 120 $400 120 $520 $ 50 *Budgeted fixed factory overhead cost...

  • ABC Company has set the following standards in order to produce one unit of its single...

    ABC Company has set the following standards in order to produce one unit of its single product: standard quantity standard price direct materials 2.7 yards ?? per yard direct labor 2 hours $14 per hour variable overhead 2 hours ?? per hour During August, ABC Company spent $133,770 to purchase direct materials and had direct labor totaling $189,440. During August, ABC Company used 16,000 yards of direct materials in the production of units. ABC had 2,500 yards of materials in...

  • ABC Company has set the following standards in order to produce one unit of its single...

    ABC Company has set the following standards in order to produce one unit of its single product: standard quantity standard price direct materials 2.7 yards ?? per yard direct labor 2 hours $14 per hour variable overhead 2 hours ?? per hour During August, ABC Company spent $133,770 to purchase direct materials and had direct labor totaling $189,440. During August, ABC Company used 16,000 yards of direct materials in the production of units. ABC had 2,500 yards of materials in...

  • Topper Toys has developed a new toy called the Brainbuster. The company has a standard cost...

    Topper Toys has developed a new toy called the Brainbuster. The company has a standard cost system to help control costs and has established the following standards for the Brainbuster toy: Direct materials: 6 diodes per toy at $0.34 per diode Direct labor: 1.1 hours per toy at $7.40 per hour During August, the company produced 5,200 Brainbuster toys. Production data on the toy for August follow. Direct materials: 76,000 diodes were purchased at a cost of $0.33 per diode....

  • Topper Toys has developed a new toy called the Brainbuster. The company has a standard cost...

    Topper Toys has developed a new toy called the Brainbuster. The company has a standard cost system to help control costs and has established the following standards for the Brainbuster toy: Direct materials: 7 diodes per toy at $0.33 per diode Direct labor. 1.2 hours per toy at $6.50 per hour During August, the company produced 5,200 Brainbuster toys. Production data on the toy for August follow:. Direct materials: 74,000 diodes were purchased at a cost of $0.30 per diode....

  • Standard Cost Sheet, Product XV-1 EXHIBIT 14.5 SCHMIDT MACHINERY COMPANY Standard Cost Sheet Product: XV-1 Descriptions...

    Standard Cost Sheet, Product XV-1 EXHIBIT 14.5 SCHMIDT MACHINERY COMPANY Standard Cost Sheet Product: XV-1 Descriptions Quantity Cost Rate Subtotal Total Direct materials: Aluminum $100 4 pounds $25/pound 1 pound PVC 40/pound 40 Direct labor 5 hours 40/hour 200 Variable factory overhead 5 hours 12/hour 60 Total variable manufacturing cost $400 Fixed factory overhead 24/hour 5 hours 120 120 Standard manufacturing cost per unit $520 50 Standard variable selling and administrative cost per unit *Budgeted fixed factory overhead cost $120,000....

  • ABC Company has set the following standards in order to produce one unit of its single product: sta...

    ABC Company has set the following standards in order to produce one unit of its single product: standard quantity standard price direct materials 2.7 yards ?? per yard direct labor 2 hours $14 per hour variable overhead 2 hours ?? per hour During August, ABC Company spent $133,770 to purchase direct materials and had direct labor totaling $189,440. During August, ABC Company used 16,000 yards of direct materials in the production of units. ABC had 2,500 yards of materials in...

  • Hemandez Corporation uses a standard cost system and has established the following standards for one unit...

    Hemandez Corporation uses a standard cost system and has established the following standards for one unit of product: Standard Quantity 10 pounds 25 hour Standard Cost $26.00 Price Direct materials Direct labor $2.60 per pound $10.00 per hour2.50 $28.50 During October, the company purchased 240,000 pounds of material at a total cost of $588,000. The total factory wages for October were $49,400. During October, 21,000 units ofproduct were manufactured using 211,000 pounds of material and 5,200 direct labor hours. Material...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT