Question

Exercise 11-6 Managing a Constrained Resource (LO11-6] Portsmouth Company makes upholstered furniture. Its only variable costRequired 1 Required 2 Required 3 A small nearby upholstering company has offered to upholster furniture for Portsmouth at a fComplete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Should Portsmouth hire th

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1.

Particulars Sofa ($)
Selling price per unit 2,000
Variable cost per unit 1,300
Contribution margin per unit (a) 700
Upholstery shop time required to produce one unit (b) 14 hours
Maximum overtime premium per hour (a) / (b) [700/12] 50

Answer 2.

Particulars Love Seat ($)
Selling price per unit 1,650
Variable cost per unit 1,200
Contribution margin per unit (a) 450
Upholstery shop time required to produce one unit (b) 5 hours
Contribution margin per unit of the constrained resource (a) / (b) [ 450/5] 90
price charged to upholster by another firm 47
Additional contribution margin [90-47 ] 43

Answer 3.

Yes it should be hired as there is additional margin

Add a comment
Know the answer?
Add Answer to:
Exercise 11-6 Managing a Constrained Resource (LO11-6] Portsmouth Company makes upholstered furniture. Its only variable cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 12-6 Managing a Constrained Resource (L012-6] Portsmouth Company makes upholstered furniture. Its only variable cost...

    Exercise 12-6 Managing a Constrained Resource (L012-6] Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: Selling price per unit Variable cost per unit Upholstery labor-hours per unit $ $ Recliner 1,284 $ 900 $ 6 hours Sofa Love Seat 1,700 $ 1,520 1,200 $ 1,100...

  • Exercise 11-6 Managing a Constrained Resource (LO11-6] Portsmouth Company makes upholstered furniture. Its only variable cost...

    Exercise 11-6 Managing a Constrained Resource (LO11-6] Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: Selling price per unit Variable cost per unit Upholstery labor-hours per unit Recliner Sofa Love Seat $ 1,190 $ 1,880 $ 1,550 $ 700 $ 1,250 $ 1,100 7 hours...

  • Exercise 11-6 Managing a Constrained Resource (LO11-6) Portsmouth Company makes upholstered furniture. Its only variable cost...

    Exercise 11-6 Managing a Constrained Resource (LO11-6) Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: Selling price per unit Variable cost per unit Upholstery labor-hours per unit Recliner Sofa Love Seat $ 1,298 $ 1,855 $ 1,280 850 $ 1,250 $ 1.000 7 hours 11...

  • Exercise 12-6 Managing a Constrained Resource (LO12-6] Portsmouth Company makes upholstered furniture. Its only variable cost...

    Exercise 12-6 Managing a Constrained Resource (LO12-6] Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: Selling price per unit Variable cost per unit Upholstery labor-hours per unit $ $ Recliner 1,330 700 9 hours $ $ Sofa Love Seat 2,819 $ 1.558 1,350 $ 1,158...

  • Portsmouth Company makes upholstered furniture Its only variable cost is direct materials. The demand for the...

    Portsmouth Company makes upholstered furniture Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below Selling price per unit Variable cost per unit Upholstery labor hours per unit $ $ Recliner 1,480 $ 800 $ 8 hours Sofa Love Seat 1,800 $ 1,500 1,200 $ 1,000 10 hours 5 hours Required: 1....

  • Portsmouth Company... Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand...

    Portsmouth Company... Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: points Selling price per unit Variable cost per unit Upholstery labor-hours per unit Recliner Sofa Love Seat $ 1,156 $ 1,850 $ 1,300 $ 750 $ 1,250 $ 1,000 7 hours 12 hours 4 hours...

  • Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the...

    Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: Selling price per unit Variable cost per unit Upholstery labor-hours per unit Recliner Sofa $ 1,000 $ 1,900 $ 700 $ 1,250 6 hours 13 hours Love Seat $ 1,500 $ 1,200 4 hours Required: 1. Portsmouth...

  • Should Portsmouth hire the nearby upholstering company? Portsmouth Company makes upholstered furniture. Its only variable cost...

    Should Portsmouth hire the nearby upholstering company? Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: Selling price per unit Variable cost per unit Upholstery labor-hours per unit Recliner Sofa Love Seat $ 1,214 $ 2,065 $ 1,440 $ 750 $ 1,350 $ 1,100 8 hours...

  • Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the...

    Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: Recliner $ 1,228 Sofa 1,800 Love Seat $ 1,370 $ Selling price per unit Variable cost per unit 8 hours 10 hours 4 hours 1. Portsmouth is considering paying its upholstery laborers hourly compensation, in addition to...

  • Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the...

    Portsmouth Company makes upholstered furniture. Its only variable cost is direct materials. The demand for the company's products far exceeds its manufacturing capacity. The bottleneck (or constraint) in the production process is upholstery labor-hours. Information concerning three of Portsmouth's upholstered chairs appears below: Selling price per unit Variable cost per unit Upholstery labor-hours per unit Love Recliner Sofa Seat $ 1,276 $ 1,700 $ 1,275 $ 800 $ 1,250 $ 850 10 7 hours 5 hours hours on Required: 1....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT