Question

Which of the following statements is true of activity-based costing?


Multiple Choice

  • ABC ignores the allocation of marketing costs.

  • ABC classifies some indirect costs as direct costs. products.

  • ABC is more likely to result in big differences from a traditional costing system if the business makes only one product rather than multiple products.

  • Activities are the cost objects of the second stage of ABC.



Aces, Inc., a manufacturer of tennis rackets, began operations this year. The company produced 6,000 rackets and sold 4,900.

Production costs per tennis racket total $ 38, which consists of $ 25 in variable production costs and $ 13 in fixed production costs (based on the 6,000 units produced). Ten percent of total selling and administrative expenses are variable. Compute net income under variable costing.



2 0
Add a comment Improve this question Transcribed image text
Answer #1
1] Which of the following statements is true of ABC?
*ABC classifies some indirect costs as direct costs.
2] Sales $      4,41,000
Variable expenses:
Production cost [4900*25] $      1,22,500
Selling and administration [75000*10%] $           7,500
Total variable expenses $      1,30,000
Contribution margin $      3,11,000
Fixed expenses:
Production [6000-13] $          78,000
Selling and administration [75000*90%] $          67,500
Total fixed expenses $       1,45,500
Net Income under variable costing $     1,65,500
Add a comment
Know the answer?
Add Answer to:
Which of the following statements is true of activity-based costing?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 9. Which of the following statements is true? a. Activity-based costing uses a number of activity...

    9. Which of the following statements is true? a. Activity-based costing uses a number of activity cost pools, each of which is allocated to products on the basis of direct labor-hours. b. Activity rates in activity-based costing are computed by dividing costs from the first stage allocations by the activity measure for each activity cost pool. C. An activity-based costing system is generally easier to implement and maintain than traditional costing system. d. One of the goals of activity-based costing...

  • Which of the following statements about activity-based costing is false? Activity-based costing is most appropriate for...

    Which of the following statements about activity-based costing is false? Activity-based costing is most appropriate for a firm that produces similar products that use similar resources. Activity-based costing requires a two-stage allocation of costs. Activity-based costing categorizes costs as unit-level, batch-level, product-level, or organization-sustaining. Activity-based costing can be used for manufacturing, administrative, or selling costs.

  • Question 33 2 pts The first step for implementing activity-based costing is Calculate activity rates Assign...

    Question 33 2 pts The first step for implementing activity-based costing is Calculate activity rates Assign overhead costs to activity cost pools Define activities, activity cost pools, and activity measures Assign overhead costs to cost objects Question 34 2 pts The differences between ABC and Traditional Product Costs include the following except: Traditional cost systems create a more favorable net operating income (loss) Traditional cost systems allocate manufacturing overhead costs using a volume-related allocation base Traditional cost systems allocate all...

  • please answer the following questions. 5. Answer True or False for the following: Activity Based Costing...

    please answer the following questions. 5. Answer True or False for the following: Activity Based Costing is NOT a more accurate allocation of manufacturing overhead than Traditional Costing. Cost drivers are activities that drive the cost to be accumulated. Traditional systems use a plant wide manufacturing allocation rate. The third step to ABC costing is to identify each activity and estimate its total indirect cost. Value Engineering includes the financial team only of a company. When calculating cost based pricing...

  • Uhlt 4 Activity Based Costing Question 22 (1 point) Which of the following statements about activity-based...

    Uhlt 4 Activity Based Costing Question 22 (1 point) Which of the following statements about activity-based costing is TRUE? It does not affect cost control. It provides less information than traditional cost systems. It provides similar results to traditional costing when different products use resources from different activities in different proportions. Indirect cost allocation bases are unlikely to be cost drivers. It provides similar results to traditional costing when one activity creates a substantial amount of total cost. Question 23...

  • Mastery Problem: Activity-Based Costing (Advanced) Activity-Based Costing Traditionally, Overhead cost: Sometimes referred to as "factory overhead,"...

    Mastery Problem: Activity-Based Costing (Advanced) Activity-Based Costing Traditionally, Overhead cost: Sometimes referred to as "factory overhead," this is an indirect cost that is not directly tied to the production of units, yet nonetheless must be built into product cost in order to appropriately price it. Examples are managerial salaries, rent expense, setup costs, and property taxes.overhead costs are assigned based arbitrarily on the rate of either Direct labor: This is a labor cost directly associated with the production of goods...

  • A Melbourne-based company Acacia is considering the adoption of an activity-based costing (ABC) system because they...

    A Melbourne-based company Acacia is considering the adoption of an activity-based costing (ABC) system because they suspect that their traditional costing system distorts the product costs. Acacia produces and sells two products A and B. Their traditional costing system uses direct labor hours as the allocation base for manufacturing overhead cost. Additional information: Product A Product B Direct materials (DM) $38 per unit $28 per unit Direct labor (DL) $24 per unit $12 per unit Units produced 50,000 units 200,000...

  • Help Which of the following statements is correct? Multiple Choice Activity based management seeks to eliminate...

    Help Which of the following statements is correct? Multiple Choice Activity based management seeks to eliminate waste by allocating costs to products that waste resources Activity based costing involves a two-stage allocation process in which overhead costs are first assigned to departments and then to jobs on the basis of direct labor hours In activity-based costing a separate activity rate se predetermined overhead rate) is computed for each activity cost pool by dividing the estimated overhead cost in the activity...

  • TRUE or FALSE? In the second-stage allocation in activity-based costing, costs that were allocated in the...

    TRUE or FALSE? In the second-stage allocation in activity-based costing, costs that were allocated in the first stage are assigned to products. O True O False

  • Which of the following statements is true regarding variable costing? Multiple Choice It is a traditional...

    Which of the following statements is true regarding variable costing? Multiple Choice It is a traditional costing approach. It makes it easier to manipulate earnings with changes in production levels. Only manufacturing costs that change in total with changes in production level are included in product costs. It treats overhead in the same manner as absorption costing. It is not permitted to be used for managerial reporting.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT