please provide full answer with following answer format
Free Form Builders Inc.
Percentage of completion method ( Contract amount : $ 1,000,000 )
Year | Calculations | Revenue | Expense | Profit/(loss) | ||
2017 | cost incurred in current year | $ 100,000 | ||||
cost incurred to date | $ 100,000 | $ 160,000 | $ 100,000 | $ 60,000 | ||
total estimated cost | $ 625,000 | |||||
Percentage Complete | cost incurred to date/ Total estimated cost | 16.0000% | ||||
Revenue Recognized | (contract price* percentage complete)-revenue previously recognized | $ 160,000 | ||||
Year | Calculations | Revenue | Expense | Profit/(loss) | ||
2018 | cost incurred in current year | $ 150,000 | ||||
cost incurred to date | $ 250,000 | $ 240,000 | $ 150,000 | $ 90,000 | ||
total estimated cost | $ 625,000 | |||||
Percentage Complete | cost incurred to date/ Total estimated cost | 40.0000% | ||||
Revenue Recognized | (contract price* percentage complete)-revenue previously recognized | $ 240,000 | ||||
Year | Calculations | Revenue | Expense | Profit/(loss) | ||
2019 | cost incurred in current year | $ 300,000 | ||||
cost incurred to date | $ 550,000 | $ 333,333 | $ 300,000 | $ 33,333 | ||
total estimated cost | $ 750,000 | |||||
Percentage Complete | cost incurred to date/ Total estimated cost | 73.3333% | ||||
Revenue Recognized | (contract price* percentage complete)-revenue previously recognized | $ 333,333 | ||||
Year | Calculations | Revenue | Expense | Profit/(loss) | ||
2020 | cost incurred in current year | $ 350,000 | ||||
cost incurred to date | $ 900,000 | $ 266,667 | $ 350,000 | $ (83,333) | ||
total cost | $ 900,000 | |||||
Percentage Complete | cost incurred to date/ Total cost | 100% | ||||
Revenue Recognized | (contract price* percentage complete)-revenue previously recognized | $ 266,667 | ||||
TOTALS | $ 1,000,000 | $ 900,000 | $ 100,000 |
please provide full answer with following answer format evenue from its long-term contracts 2017, the company...
Question 3 Free Form Builders Inc., a construction company, recognizes revenue from its long-term contracts using the percentage-of-completion method. On March 29, 2017, the company signed a contract to construct a building for $1 million. The company estimated that it would take four years to complete the contract and estimated the cost to the company at $625,000, as follows: Year Cost 2017 $100,000 2018 $150,000 2019 $175,000 2020 $200,000 Total $625.000 The actual costs in 2017 and 2018 ended up...
Measuring income from long-term contracts. On January 1, 2017 assume that Turner Construction Company agreed to construct an observatory for Dartmouth College for $120 million. Dartmouth college must pay $60 million upon signing and $30 million in 2018 and 2019. Expected construction costs are $10 million for 2017, $60 million for 2018, and $30 million for 2019 REQUIRED: a.) Indicate the amount and nature of income (revenue and expense) that Turner would recognize during 2017, 2018, and 2019 if it...
Measuring income from long-term contracts. On January 1, 2017 assume that Turner Construction Company agreed to construct an observatory for Dartmouth College for $120 million. Dartmouth college must pay $60 million upon signing and $30 million in 2018 and 2019. Expected construction costs are $10 million for 2017, $60 million for 2018, and $30 million for 2019 REQUIRED: a.) Indicate the amount and nature of income (revenue and expense) that Turner would recognize during 2017, 2018, and 2019 if it...
Hollywood Construction Company recognizes revenue over time according to percentage of completion for its long term construction contracts. During 2018 Hollywood began work on a $3,000,000 foed-fee construction contract which was completed in 2021. The accounting records disclosed the following data at year-end: Estimated costs to complete at end of year $1,800,000 1,100,000 400,000 Cumulative contract costs incurred S 200,000 1,100,000 2,000,000 2018 2019 2020 For the 2020 year, Hollywood should have recognized gross profit on this contract of
Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.С., for $270 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 $ 50 $100 60...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 60 $ 120 $ 70 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...
7 On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 0.5 points 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 120...
a 200 points 2/6/2020 Assignment Print View 8. Award: 2.00 points Exercise 5-18 Long-term contract revenue recognition over time vs. upon project completion (LOS-91 On June 15, 2018 Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, DC, for 1430 million. The expected completion date is April 1, 2020. just in time for the 2020 baseball season costs incurred and estimated costs to complete a year-end for the the contract are as follows (s...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2020. lust in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2018 2019 2020 $ 60 $130 $70...