Question

Measuring income from long-term contracts. On January 1, 2017 assume that Turner Construction Company agreed to...

Measuring income from long-term contracts. On January 1, 2017 assume that Turner Construction Company agreed to construct an observatory for Dartmouth College for $120 million. Dartmouth college must pay $60 million upon signing and $30 million in 2018 and 2019. Expected construction costs are $10 million for 2017, $60 million for 2018, and $30 million for 2019

REQUIRED:

a.) Indicate the amount and nature of income (revenue and expense) that Turner would recognize during 2017, 2018, and 2019 if it uses the completed-contract method. Ignore income taxes.

b.) Repeat requirement a using the percentage-of-completion method

c.) Indicate the balance in the Construction in Process account on December 31, 2017, 2018, and 2019, (just prior to completion of the contract) under the completed-contract and the percentage-of-completion methods.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Before start answering the above Question let me update about Revenue recognition method in case of Long construction contract . As per new Accounting standard relates to revenue recognition , we need to recognised revenue on POCM basis . POCM full form is Percentage of Completion Method . As per new standard , we used to follow Input and output method to recognising revenue . As per new standard , we can recognising POCM based on Effort as well as Cost .

Below we explain revenue recognition on the basis of POCM method under different stage wise.

We have derived cost incurred till date/ total estimated cost for this project = POCM on the basis of Cost

above POCM cost % we will apply on revenue to recognised the same year wise .

Percentage Completion Method
based on % of cost complete
2017
Cost incurred ($ Mio) 10
Total Cost to complete this contract( $ MIO) 100
% cover 10%
Revenue Recognised
( based on % of cost cover basis)-$ Mio 12 ( Revenue * Cost cover%)
Cost incurred -$ Mio 10
Margin-$ Mio 2
2018
Cost incurred ($ Mio) 60
Total Cost to complete this contract( $ MIO) 100
% cover 60%
Revenue Recognised
( based on % of cost cover basis)-$ Mio 72 ( Revenue * Cost cover%)
Cost incurred -$ Mio 60
Margin-$ Mio 12
2019
Cost incurred ($ Mio) 30
Total Cost to complete this contract( $ MIO) 100
% cover 30%
Revenue Recognised
( based on % of cost cover basis)-$ Mio 36 ( Revenue * Cost cover%)
Cost incurred -$ Mio 30
Margin-$ Mio 6

Complete Contract method - This method of revenue recognition still allow under USGAAP . IFRS not allowing this principle to recognised revenue .

Under Complete contact method , revenue and cost will recognised at the end of the contract .

2017 - Cost incurred - $ 10 MIo

2018 - cost incurred $ 60 Mio -- Accumulated cost incurred - $ 70

2019 - cost incurred $ 30 Mio - Total cost till end of the contract - $ 100 Mio

Contract end revenue recognised - $ 120 Mio

Margin will be at the end of the Contract - $ 120 Mio -$ 100 Mio = $ 20 Mio

Add a comment
Know the answer?
Add Answer to:
Measuring income from long-term contracts. On January 1, 2017 assume that Turner Construction Company agreed to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Measuring income from long-term contracts. On January 1, 2017 assume that Turner Construction Company agreed to construc...

    Measuring income from long-term contracts. On January 1, 2017 assume that Turner Construction Company agreed to construct an observatory for Dartmouth College for $120 million. Dartmouth college must pay $60 million upon signing and $30 million in 2018 and 2019. Expected construction costs are $10 million for 2017, $60 million for 2018, and $30 million for 2019 REQUIRED: a.) Indicate the amount and nature of income (revenue and expense) that Turner would recognize during 2017, 2018, and 2019 if it...

  • Constructing and Assessing Income Statements Using Percentage of Completion On March 15, 2017, Frankel Construction is...

    Constructing and Assessing Income Statements Using Percentage of Completion On March 15, 2017, Frankel Construction is contracted to build a shopping center at a contract price of $120 million. The schedule of expected (equals actual) cash collections and contract costs follows Year Cash Collections Cost Incurred 2017 2018 2019 $30 million 15 million 50 million40 mlion 40 million 30 million Total $120 million 85 million Calculate the amount of revenue, expense, and income for each of the three years 2017...

  • 4. Menlo, which began operations on January 1, year 1, recognizes income from long-term construction contracts...

    4. Menlo, which began operations on January 1, year 1, recognizes income from long-term construction contracts under the percentage of completion method in its financial statements and under the completed contract method for tax reporting. Income under each method is a s follows: Completed Contract Percentage of completion Year Year 1 Year 2 Year 3 500,000 700.000 400,000 600,000 450,000 The income tax rate was 30% for year 1 through year 3. There are no other temporary differences. Menlo should...

  • Tamarisk Construction Company changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction...

    Tamarisk Construction Company changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction contracts during 2018. For tax purposes, the company employs the completed-contract method and will continue this approach in the future. (Hint: Adjust all tax consequences through the Deferred Tax Liability account.) The appropriate information related to this change is as follows. Pretax Income from: Percentage-of-Completion Completed-Contract Difference 2017 $714,000 $647,000 $67,000 2018 642,000 512,000 130,000 (a) Assuming that the tax rate is 30%, what...

  • please provide full answer with following answer format evenue from its long-term contracts 2017, the company...

    please provide full answer with following answer format evenue from its long-term contracts 2017, the company signed a contract to Question 3 Free Form Builders Inc., a construction company, recognizes revenue from its long-ter using the percentage-of-completion method. On March 29, 2017, the company signed construct a building for $1 million. The company estimated that it would take four years the contract and estimated the cost to the company at $625,000, as follows: Year Cost 2017 $100,000 2018 $150,000 2019...

  • Ex. 18-123-Long-term construction contracts (essay). In accounting for long-term construction contracts (those taking longer than one...

    Ex. 18-123-Long-term construction contracts (essay). In accounting for long-term construction contracts (those taking longer than one year to complete), the two methods commonly followed are percentage-of-completion and completed- contract Instructions (a) Discuss how earnings on long-term construction contracts are recognized and computed under these two methods. (b) Under what circumstances should one method be used over the other? (c) How are job costs and interim billings reflected on the balance sheet under the percentage-of-completion method and the completed-contract method?

  • Blue Construction Company, which began operations in 2017, changed from the completed-contract to...

    Blue Construction Company, which began operations in 2017, changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction contracts during 2018. For tax purposes, the company employs the completed-contract method and will continue this approach in the future. The appropriate information related to this change is as follows. Pretax Income from Percentage-of-Completion Completed-Contract Difference 2017 $966,000 $600,000 $366,000 2018 906,000 434,000 472,000 (a) Assuming that the tax rate is 35%, what is the amount of net income...

  • Construction began on January 1, 2018. Expected completion date: December 31, 2020 Contract price $108 million....

    Construction began on January 1, 2018. Expected completion date: December 31, 2020 Contract price $108 million. The Completed Contract Method is used to recognize revenue and profit from the contracts. Years Actual costs incurred in each year Estimated remaining costs to complete the project (as of Dec 31) 2018 2019 2020 $40 million $38 million $36 million $60 million $44 million $ 0 What amount of gross profit (loss) would the company recognize in each year from the above contract?...

  • Question 3 Free Form Builders Inc., a construction company, recognizes revenue from its long-term contracts using...

    Question 3 Free Form Builders Inc., a construction company, recognizes revenue from its long-term contracts using the percentage-of-completion method. On March 29, 2017, the company signed a contract to construct a building for $1 million. The company estimated that it would take four years to complete the contract and estimated the cost to the company at $625,000, as follows: Year Cost 2017 $100,000 2018 $150,000 2019 $175,000 2020 $200,000 Total $625.000 The actual costs in 2017 and 2018 ended up...

  • On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of...

    On February 1, 2017, Marsh Contractors agreed to construct a building at a contract price of $5,720,000. Marsh estimated total construction costs would be $3,936,000 and the project would be finished in 2019. Information relating to the costs and billings for this contract is as follows: 2017 2018 2019 Total costs incurred to date $1,476,000 $2,592,000 $4,560,000 Estimated costs to complete 2,460,000 1,728,000 -0- Customer billings to date 2,120,000 3,936,000 5,520,000 Collections to date 1,920,000 3,420,000 5,420,000 Fill in the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT