Question

Construction began on January 1, 2018. Expected completion date: December 31, 2020 Contract price $108 million. The Completed Contract Method is used to recognize revenue and profit from the contracts. Years Actual costs incurred in each year Estimated remaining costs to complete the project (as of Dec 31) 2018 2019 2020 $40 million $38 million $36 million $60 million $44 million $ 0 What amount of gross profit (loss) would the company recognize in each year from the above contract? Show your work. This is a fairly simple question. Please organize your computation/work neatly. If I cannot read it, I cannot grade it. Clearly indicate the profit (loss) amount for each year in bold blue.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Percentage of Completion Method (Amount in Millions)       

(A) Costs incurred to date

$48

$38

$36

Estimated future costs

$60

$44

$0

B) Estimated total costs

$108

$82

$36

(C) Est. total gross profit($108 - B)

0

$26

$72

(D) Percent Complete (A/B)

44%

46%

100%

Total GP Recognized to Date (C*D)

0

$11.96

$72

Current Yr. Gross Profit Recognized

0

0

$72

Gross Profit to be recognized in each year

2018 = 0 Million

2019 = 0 Million

2020 = $72 Million

Add a comment
Know the answer?
Add Answer to:
Construction began on January 1, 2018. Expected completion date: December 31, 2020 Contract price $108 million....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred...

    Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...

  • 1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...

    1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...

  • Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred...

    Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred...

    Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred costs of $295,500, billed its customer for $200,500, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $155,645. Prepare Vaughn’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 60 $ 120 $ 70 Estimated costs to complete as of...

  • Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $30 million. Construction...

    Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $30 million. Construction costs incurred in the first year were $16 million and estimated remaining costs to complete at the end of the year were $17 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method? How much gross profit or loss will Franklin recognize in the first year applying the...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2020. lust in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2018 2019 2020 $ 60 $130 $70...

  • Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred...

    Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred costs of $299,000, billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $151,030. Prepare Indigo’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $46 million. Construction...

    Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $46 million. Construction costs incurred in the first year were $36 million and estimated remaining costs to complete at the end of the year were $23 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method? (Enter your answer in millions.) Gross loss million How much gross profit or loss will...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT