Question

8 of 10 Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed on March 31, year 2.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The period starts from July 1 Year 1 to March 31 Year 2. It means there are two accounting periods for interest computation as:

Year 1 = July 1 to Dec 31 = 6 months

Year 2 = Jan 1 to March 31 = 3 months

Computation of weighted average interest rate

Principal

Interest

10% notes

3,000,000

300,000

5% bonds

7,000,000

350,000

$       10,000,000

$ 650,000

Weighted average interest rate = 650,000/10,000,0000 = 6.5%

Computation of average accumulated expenditures for Year 1

Details

Amount

July 1

500,000 * 6/6

500,000

Sep 30

600,000 * 3/6

300,000

Nov 30

400,000 *1/6

66667

Total

1500,000

866667

Interest to be capitalized in Year 1 = 866667 X 6.5% X 6 /12 = $ 28167

Computation of average accumulated expenditures for Year 1

Details

Amount

Jan 1, Year 2

(1500,000+28167) X 3/3

1528,167

January 30

550,000 * 2/3

366667

1894,834

Interest to be capitalized in Year 2 = 1894,834 X 6.5% X 3/12 = $ 30791

Add a comment
Know the answer?
Add Answer to:
8 of 10 Keiron Industries began construction of a warehouse on July 1, year 1. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed...

    Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed on March 31, year 2. No new loans were required to fund construction. Keiron does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 10% note $7,000,000, 5% bonds Construction expenditures incurred were as follows: July 1, year 1 September 30, year 1 November 30, year 1 January 30, year 2 $500,000 600,000 400,000 550,000 The company's fiscal year-end...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 6% note $5,000,000, 2% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 540,000 September 30, 2018 750,000 November 30, 2018 750,000 January 30, 2019 690,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 12% note $7,000,000, 7% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 700,000 September 30, 2021 990,000 November 30, 2021 990,000 January 30, 2022 930,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 8% note $8,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 January 30, 2022 $ 400,000 600,000 600,000 540,000 The company's fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 9% note $6,000,000, 6% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 430,000 September 30, 2021 630,000 November 30, 2021 630,000 January 30, 2022 570,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 10% note $6,000,000, 5* bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 $ 640,000 960,000 960,000 900,000 January 30, 2022 The company's fiscal year-end is December 31. Required: Calculate...

  • Exercise 10-25 Interest capitalization; multiple periods [LO10-7] Thornton Industries began construction of a...

    Exercise 10-25 Interest capitalization; multiple periods [LO10-7] Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest- bearing liabilities that were outstanding throughout the construction period: $4,000,000, 9% note $6,000,000, 68 bonds Construction expenditures incurred were as follows: $ 430,000 630,000 630,000 570,000 July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT