1) Classification
Insurance on delivery equipment | Period cost |
Oak and Cherry wood used in desks and chairs | Direct material |
Lubricants, rosin and polishing compounds used in manufacturing | Manufacturing overhead |
Advertising in trade magazines | Period cost |
Rent on leased factory machine | Manufacturing overhead |
Wages of assembly line workers | Direct labor |
Sales person's commission | period cost |
Insurance on factory machine | manufacturing overhead |
Depreciation on factory machine | Manufacturing overhead |
Wages of factory janitor | Manufacturing overhead |
Note : Please post each question individually as HOMEWORKLIB guidelines
Instructions Classify the following manufacturing costs and expenses by using the following code letters: A Direct...
Example 5: Hanover Manufacturing begins operations on April 1. Information from job cost sheets shows the following: Manufacturing Costs Assigned (non-cumulative) Job April May June 15 $10,200 16 5,100 $6,400 3,600 5,900 $4,000 7,300 7,400 20 3,100 18 19 Job 15 was completed in April. Job 16 was completed in May. Job 18 was completed in June. Each job was sold in the month following completion Page 4 of 8 Instructions: Determine the following amounts: Work in process inventory, April...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April May June Completed 10 $6,900 $6,100 May 11 5.900 4.600 $2.800 June 1.900 April 6,600 5.700 June 6,000 3,900 Not complete 12 What is the balance in Work in Process Inventory at the end of each month Work in Process Inventory April 30 May 31 June 30 LINK TO TEXT LINK TO TEX What is the balance in...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number Month Completed April May June $5,500 6,100 1,600 $5,400 4,100 $3,500 May June April June Not complete 6,400 6,300 4,600 4,200 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is the balance in...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $7,100 $6,400 May 11 5,900 5,900 $3,300 June 12 1,500 April 13 6,500 6,100 June 14 6,800 4,000 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April MayJune Completed 10 $6,800 $5,000 11 6,000 5,300 $ 2.600 June 12 13 14 May 2,300 April 5,300 5,600 June 6,600 4,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....
Laubitz Company begins operations on Apr.1. Information from job cost sheets shows the following: Manufacturing Costs Assigned Job Number April May June Month Completed 10 $7,500 $4,400 May 11 $4,100 $6,900 $3,000 June 12 $3,200 April 13 $4,700 $9,400 June 14 $4,400 $3,600 Not complete Each job was sold for 25% above its cost in the month following completion. (a) Work in Process Inventory at April 30: $Answer May 31: $Answer (b) Finished Goods Inventory at April 30: $Answer May...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following Job Number June 10 April $5,700 5,600 1,700 Manufacturing Costs Assigned Month May Completed $4,600 May 4,100 $2,200 June April 4,900 5,200 June 4,300 Not complete 12 14 6,400 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is...
Laubitz Company begins operations on April 1. Information from job cost sheets shows the following: Manufacturing Costs Assigned Job Number May June April $6,600 Month Completed May 10 $4,400 11 4,300 3,900 $3,000 June 12 1,200 April 13 3,400 June 4,700 5,600 14 3,800 Not complete Each job was sold for 25% above its cost in the month following completion. Calculate the balance in Work in Process Inventory at the end of each month. Work in Process Inventory April 30...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Completed 10 $5,200 $4,400 May 11 4,100 3,900 $2,000 June 12 1,200 April 13 4,700 4,500 June 14 5,900 3,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. Instructions...
Tiemney Company begins operations on April 1. Information from job cost sheets shows the following Job Number April $5,700 5,600 1,700 Manufacturing Costs Assigned Month May June Completed $4,600 May 4,100 $2,200 June April 4,900 5,200 June 6,400 4,300 Not complete Job 12 was completed in April Job 10 was completed in May, Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion What is the balance in...