Question

Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

Tierney Company begins operations on April 1. Information from job cost sheets shows the following.
Manufacturing Costs Assigned
Job Number April May June Completed
10 $5,200 $4,400 May
11 4,100 3,900 $2,000 June
12 1,200 April
13 4,700 4,500 June
14 5,900 3,600 Not complete


Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion.

Instructions
a. What is the balance in Work in Process Inventory at the end of each month?
b. What is the balance in Finished Goods Inventory at the end of each month?
c. What is the gross profit for May, June, and July?

3 2
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

  1. Ending work in process inventory    

Work in process are those items that are still being processed under factory and not complete.

Job 10 and 11 are pending in April

Job 11, 13 and 14 are pending in May

Job 14 is incomplete at June end

April (5200 +4100)

9,300

May (4100 + 3900 + 4700 + 5900)

18,600

June ( 5900 +3600)

9,500

Ending work in process inventory

37,400

  1. Finished goods

Finished goods are 100% complete in respect of materials and labor and can be sold. Since they are sold in following month, current month inventory would not end up in next month inventory.

Job 12 is complete in April

Job 10 is complete in May

Job 11 and 13 are complete in June

April

1200

May (5200 + 4400)

9600

June (4100 + 3900 +2000 + 4700 +4500)

19,200

Finished goods

30,000

  1. Gross profit

Gross profits are computed on finished goods sold as:

April (1200 X 0.25)

300

May (9600 * 0.25)

2400

June (19200 X 0.25)

4800

Finished goods

7500

Add a comment
Know the answer?
Add Answer to:
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $7,100 $6,400 May 11 5,900 5,900 $3,300 June 12 1,500 April 13 6,500 6,100 June 14 6,800 4,000 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $ 5,700 $ 4,600 May 11 5,600 4,100 $ 2,200 June 12 1,700 April 13 4,900 5,200 June 14 6,400 4,300 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job Number 10 April $5,700 5,800 1,500 Manufacturing Costs Assigned Month May June Completed $5,900 May 5,400 $3,000 June April 4,900 5,300 June 7,000 3.700 Not complete 11 12 13 14 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following Job...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following Job Number June 10 April $5,700 5,600 1,700 Manufacturing Costs Assigned Month May Completed $4,600 May 4,100 $2,200 June April 4,900 5,200 June 4,300 Not complete 12 14 6,400 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job Number 10 Manufacturing Costs Assigned Month April May June Completed $7,100 $4,900 May 4,300 5,100 $2,200 June 2,200 April 6,600 5,700 June 6,200 4,700 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. (a) - Your answer...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number Month Completed April May June $5,500 6,100 1,600 $5,400 4,100 $3,500 May June April June Not complete 6,400 6,300 4,600 4,200 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is the balance in...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $6,300 $6,400 May 11 6,100 5,600 $3,200 June 12 1,900 April 13 6,500 6,100 June 14 6,800 4,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....

  • Laubitz Company begins operations on April 1. Information from Job cost sheets shows the following: Manufacturing...

    Laubitz Company begins operations on April 1. Information from Job cost sheets shows the following: Manufacturing Costs Assigned Job Number April May June Month Completed 10 $6,500 $4,400 May 11 $4,100 $3,900 $3,000 June 12 $1,200 April 13 $4,700 $3,400 June 14 $5,400 $3,600 Not Complete Each Job was sold for 30% above its cost in the month following completion. Hint: Determine the month sold for each job and then complete the question. Remember to add the total costs of...

  • Exercise 15-10 Tierney Company begins operations on April 1. Information from job cost sheets shows the...

    Exercise 15-10 Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April May June Completed $7,200 $5,700 May 5,700 4,300 $3,600 June 1,600 April 6,000 5,500 June 6,100 3,800 Not complete Job 12 was completed in April, Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is the...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April MayJune Completed 10 $6,800 $5,000 11 6,000 5,300 $ 2.600 June 12 13 14 May 2,300 April 5,300 5,600 June 6,600 4,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT