Question

Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $ 5,700 $ 4,600 May 11 5,600 4,100 $ 2,200 June 12 1,700 April 13 4,900 5,200 June 14 6,400 4,300 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Manufacturing Costs Assigned

Job Number April May June Month Completed
10 $5,700 $4,600 May
11 $5,600 $4,100 $2,200 June
12 $1,700 April
13 $4,900 $5,200 June
14 $6,400 $4,300 Not complete

Work in process inventory at the end of each month:-

Working Work in process inventory
Apr-30 $5,700+$5,600 11,300
May-31 $5,600+$4,100+$4,900+$6,400 21,000
June-30 $6,400+$4,300 10,700

Finished Goods Inventory at the end of each month:-

Working Finished Goods Inventory
Apr-30 1,700
May-31 5,700+4,600 10,300
June-30 5,600+4,100+2,200+4,900+5,200 22,000

Gross Profit :-

Working Gross Profit
May 1,700*0.25 425
June 10,300*0.25 2,575
July 22,000*0.25 5,500

Previous month finished goods inventory *25%

Add a comment
Know the answer?
Add Answer to:
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following Job...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following Job Number June 10 April $5,700 5,600 1,700 Manufacturing Costs Assigned Month May Completed $4,600 May 4,100 $2,200 June April 4,900 5,200 June 4,300 Not complete 12 14 6,400 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is...

  • Tiemney Company begins operations on April 1. Information from job cost sheets shows the following Job...

    Tiemney Company begins operations on April 1. Information from job cost sheets shows the following Job Number April $5,700 5,600 1,700 Manufacturing Costs Assigned Month May June Completed $4,600 May 4,100 $2,200 June April 4,900 5,200 June 6,400 4,300 Not complete Job 12 was completed in April Job 10 was completed in May, Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion What is the balance in...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job Number 10 Manufacturing Costs Assigned Month April May June Completed $7,100 $4,900 May 4,300 5,100 $2,200 June 2,200 April 6,600 5,700 June 6,200 4,700 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. (a) - Your answer...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $6,300 $6,400 May 11 6,100 5,600 $3,200 June 12 1,900 April 13 6,500 6,100 June 14 6,800 4,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Completed 10 $5,200 $4,400 May 11 4,100 3,900 $2,000 June 12 1,200 April 13 4,700 4,500 June 14 5,900 3,600 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. Instructions...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Job Number 10 April $5,700 5,800 1,500 Manufacturing Costs Assigned Month May June Completed $5,900 May 5,400 $3,000 June April 4,900 5,300 June 7,000 3.700 Not complete 11 12 13 14 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number Month Completed April May June $5,500 6,100 1,600 $5,400 4,100 $3,500 May June April June Not complete 6,400 6,300 4,600 4,200 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is the balance in...

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April Complet May June $5,300 $4,800 May 10 6,100 4,900 $2,200 June 11 2,300 12 April 13 5,100 5,000 June 6,800 4,600 Not comp 14 Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....

  • Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...

    Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $7,100 $6,400 May 11 5,900 5,900 $3,300 June 12 1,500 April 13 6,500 6,100 June 14 6,800 4,000 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....

  • Exercise 15-10 Tierney Company begins operations on April 1. Information from job cost sheets shows the...

    Exercise 15-10 Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April May June Completed $7,200 $5,700 May 5,700 4,300 $3,600 June 1,600 April 6,000 5,500 June 6,100 3,800 Not complete Job 12 was completed in April, Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT