Question

Crane Products manufactures two component parts: AJ40 and AJ60. AJ40 components are being introduced currently, and AJ60 partCalculate the difference in overhead allocated to each product. (Round answers to 0 decimal places, e.g. 5,275. Show an under

0 0
Add a comment Improve this question Transcribed image text
Answer #1
AJ40 AJ60
Units planned 1100 1100
No. of change orders 4 2
Total number of change orders 275 550 825
Machine hours per unit 1 1.5
Total machine hours required 1100 1650 2750
Total cost of change order $247,500
Traditional system
Total allocated cost for AJ40 $99,000 (247,500*1100/2750)
Total allocated cost for AJ60 $148,500 (247,500*1650/2750)
$247,500
ABC system
Total allocated cost for AJ40 82500 (247500/825*275)
Total allocated cost for AJ60 165000 (247500/825*550)
$247,500
Overcharged(undercharged) for AJ40 $16,500
Overcharged(undercharged) for AJ60 -$16,500
Add a comment
Know the answer?
Add Answer to:
Crane Products manufactures two component parts: AJ40 and AJ60. AJ40 components are being introduced currently, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 7.25 Bonita Products manufactures two component parts: AJ40 and AJ60. AJ40 components are being introduced...

    Exercise 7.25 Bonita Products manufactures two component parts: AJ40 and AJ60. AJ40 components are being introduced currently, and AJ60 parts have been in production for several years. For the upcoming period, 2,600 units of each product are planned for manufacturing. Assume that the only relevant overhead cost is for engineering change orders (any requested changes in product design or the manufacturing process). AJ40 components are expected to require 4 change orders and AJ60 only 2. Each AJ40 requires 1 machine...

  • Coronado Company produces two products: MB-R and MB-X. Currently, Coronado allocates overhead based on direct labour...

    Coronado Company produces two products: MB-R and MB-X. Currently, Coronado allocates overhead based on direct labour hours. Overhead is estimated at $436,800. The cost accountant realizes that there are some differences in how resources are being used in producing these two components and is considering the use of ABC to allocate overhead. She determines that overhead is caused by testing and inspections, $112,000; machine setup, $84,000; machine stamping, $200,000; and plant maintenance, $40,800. Coronado estimates the following activities related to...

  • Problem 7-21 Crane is an electronics components manufacturer. Information about the company's two products follows: Units...

    Problem 7-21 Crane is an electronics components manufacturer. Information about the company's two products follows: Units produced Direct labor hours required for production Units per batch Shipping weight per unit AM-2 FM-9 18,000 3,600 24,000 19,000 4,000 90 0.50 lbs. 4 lbs. The company incurs $1,412,655 in overhead per year and has traditionally applied overhead on the basis of direct labor hours. (i) How much overhead will be allocated to each product using the traditional direct labor hours allocation base?...

  • The controller of Crane Industries has collected the following monthly expense data for use in analyzing...

    The controller of Crane Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Total Maintenance Costs Month January February March April May June $2,748 3,123 3,748 4,234 3,331 4,620 Total Machine Hours 3,645 4,164 6,246 8,224 5,205 8,325 Determine the variable-cost components using the high-low method. (Round answer to 2 decimal places e.g. 2.25.) Variable cost per machine hours LINK TO TEXT LINK TO TEXT VIDEO: SIMILAR EXERCISE Determine the fixed...

  • Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products:...

    Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds $ Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead 40 20 (2 hr. at $15) 96 (2 hr. at $48) 166 Ends 5,000 units $ 60 15 (3 hr. at $15) 144 (3 hr. at $48) $...

  • Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead...

    Question 3 International Steel Company has budgeted manufacturing overhead costs of $1,995,000. It has allocated overhead on a plant-wide basis to its two products (soft steel and hard steel) using machine hours, which are estimated to be 100,000 for the current year. The company has decided to experiment with activity-based costing and has created five activity cost pools and related activity cost drivers as follows: Activity Centre Cost Driver Estimated Activity Material handling Purchase orders Product testing Machine set-up Machining...

  • Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products:...

    Required information [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds $ Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead 40 20 (2 hr. at $15) 96 (2 hr. at $48) 166 Ends 5,000 units $ 60 15 (3 hr. at $15) 144 (3 hr. at $48) $...

  • Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate...

    Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Production quantity Direct material Direct labor (not including setup time) Manufacturing overhead Total cost per unit Odds 1,000 units $ 40 30 (2 hr. at $15) 96 (2 hr. at $48) $ 166 Ends 5,000 units $ 60 45 (3 hr. at $15) 144 (3 hr. at $48) $ 249 Manufacturing overhead budget:...

  • [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and...

    [The following information applies to the questions displayed below.] Knickknack, Inc. manufactures two products: Odds and Ends. The firm uses a single, plantwide overhead rate based on direct-labor hours. Production and product-costing data are as follows: Odds Ends Production quantity 1,000 units 5,000 units Direct material $ 40 $ 60 Direct labor (not including setup time) 30 (2 hr. at $15) 45 (3 hr. at $15) Manufacturing overhead 96 (2 hr. at $48) 144 (3 hr. at $48) Total cost...

  • EcoFabrics has budgeted overhead costs of $1,115,100. It has allocated overhead on a plantwide basis to...

    EcoFabrics has budgeted overhead costs of $1,115,100. It has allocated overhead on a plantwide basis to its two products (wool and cotton) using direct labor hours which are estimated to be 531,000 for the current year. The company has decided to experiment with activity-based costing and has created two activity cost pools and related activity cost drivers. These two cost pools are cutting (cost driver is machine hours) and design (cost driver is number of setups). Overhead allocated to the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT