Question

Problem 1 You have the following projects available: Time Period Project A -$40,000.00 $35,000.00 $15,000.00 $9,000.00 $2,000

​​​​​​

Problem 1) Take the difference between the payback period of Projects A and B, i.e., calculate: X = Payback Period of Project A - Payback Period of Project B.

Select one:

a)-3

b)-2

c)-1

d)0

e)1

f)2

g)3

h)Insufficient information

Problem 1) What is (are) the posiive IRR(s) of Project C?

Select one:

a)0%

b)100%

c)104.3% is one of the IRRs and another IRR exists

d)0% is one of the IRRs and another IRR exists

e)7.7% only

f)56.3% is one of the IRRs and another IRR exists

Project C has three IRR

No positive IRR exists for Project C

Problem 1) What is the IRR of Project B?

Select one:

a)10.00%

b)6.70%

c)20.00%

d)100.00%

e)19.78%

f)Project B has multiple IRRs

g)IRR doesn't exist

h)IRR is negative

Problem 1) What is the NPV of Project C?

Select one:

a)$0

b)$1,238

c)$1,078

d)$455

e)-$365

f)-$25,000

g)$55,000

The NPV cannot be calculated because the last cash flow is negative

Problem 1) What is the payback period of Project D?

Select one:

A)1

B)2

C)3

D)4

E)5

F)6

G)7

Project D never pays back the initial investment

Problem 1) What is the profitability index (PI) of Project A?

Select one:

a)1.36

b)1.60

c)2.36

d)10%

e)$1,000

f)-$40,000

g)$14,206

h)PI is negative

0 0
Add a comment Improve this question Transcribed image text
Answer #1

To complete the table we make the following calculations:

Project A

Year CF Discount Factor Discounted CF
0 $ -40,000.00 1/(1+0.1)^0= 1 1*-40000= -40,000.00
1 $   35,000.00 1/(1+0.1)^1= 0.909090909 0.909090909090909*35000=    31,818.18
2 $   15,000.00 1/(1+0.1)^2= 0.826446281 0.826446280991735*15000=    12,396.69
3 $     9,000.00 1/(1+0.1)^3= 0.751314801 0.751314800901578*9000=      6,761.83
4 $     2,000.00 1/(1+0.1)^4= 0.683013455 0.683013455365071*2000=      1,366.03
5 $     3,000.00 1/(1+0.1)^5= 0.620921323 0.620921323059155*3000=      1,862.76
NPV = Sum of all Discounted CF    14,205.50
PI = 1+NPV/initial investment 1+14205.50/40000 = 1.36

IRR is the rate at which NPV = 0
IRR can be calculated using either a financial calculator or excel or through hit and trial:
Using Excel we get the IRR = 32.95% rounded to two decimal places

Year CF Discount Factor Discounted CF
0 $ -40,000.00 1/(1+0.329589502635871)^0= 1 1*-40000= -40,000.00
1 $   35,000.00 1/(1+0.329589502635871)^1= 0.752111835 0.75211183453053*35000=    26,323.91
2 $   15,000.00 1/(1+0.329589502635871)^2= 0.565672212 0.56567221164088*15000=      8,485.08
3 $     9,000.00 1/(1+0.329589502635871)^3= 0.425448765 0.425448764840164*9000=      3,829.04
4 $     2,000.00 1/(1+0.329589502635871)^4= 0.319985051 0.319985051022684*2000=          639.97
5 $     3,000.00 1/(1+0.329589502635871)^5= 0.240664544 0.240664543747016*3000=          721.99
NPV = Sum of all Discounted CF               0.00

Payback period calculation:

Year Opening Balance CF Closing Balance
0 $         40,000.00
1 $            40,000.00 $ 35,000.00 $            5,000.00
2 $              5,000.00 $ 15,000.00 $        -10,000.00

As we have to measure the payback period in full years, it will be 2 years because that is when the full initial investment of 40000

Project B:

Year CF Discount Factor Discounted CF
0 $ -40,000.00 1/(1+0.1)^0= 1 1*-40000= -40,000.00
1 $     1,000.00 1/(1+0.1)^1= 0.909090909 0.909090909090909*1000=          909.09
2 $     4,000.00 1/(1+0.1)^2= 0.826446281 0.826446280991735*4000=      3,305.79
3 $   16,000.00 1/(1+0.1)^3= 0.751314801 0.751314800901578*16000=    12,021.04
4 $   29,000.00 1/(1+0.1)^4= 0.683013455 0.683013455365071*29000=    19,807.39
5 $   32,000.00 1/(1+0.1)^5= 0.620921323 0.620921323059155*32000=    19,869.48
NPV = Sum of all Discounted CF    15,912.79
PI 1+15912.79/40000 =1.40

Payback period:

Year Opening Balance Investment CF Closing Balance
0 $ 40,000.00 $         40,000.00
1 $            40,000.00 $   1,000.00 $         39,000.00
2 $            39,000.00 $   4,000.00 $         35,000.00
3 $            35,000.00 $ 16,000.00 $         19,000.00
4 $            19,000.00 $ 29,000.00 $        -10,000.00

IRR = 19.78% rounded to 2 decimal places

Year CF Discount Factor Discounted CF
0 $ -40,000.00 1/(1+0.197801657787439)^0= 1 1*-40000= -40,000.00
1 $     1,000.00 1/(1+0.197801657787439)^1= 0.834862762 0.834862761708967*1000=          834.86
2 $     4,000.00 1/(1+0.197801657787439)^2= 0.696995831 0.696995830888323*4000=      2,787.98
3 $   16,000.00 1/(1+0.197801657787439)^3= 0.581895864 0.581895864275061*16000=      9,310.33
4 $   29,000.00 1/(1+0.197801657787439)^4= 0.485803188 0.485803188275704*29000=    14,088.29
5 $   32,000.00 1/(1+0.197801657787439)^5= 0.405578991 0.405578991410875*32000=    12,978.53
NPV = Sum of all Discounted CF               0.00

Project C:

Year CF Discount Factor Discounted CF
0 $ -25,000.00 1/(1+0.15)^0= 1 1*-25000= -25,000.00
1 $   78,000.00 1/(1+0.15)^1= 0.869565217 0.869565217391304*78000=    67,826.09
2 $ -55,000.00 1/(1+0.15)^2= 0.756143667 0.756143667296787*-55000= -41,587.90
NPV = Sum of all Discounted CF      1,238.19
PI $          1.05

As CFs have multiple sign changes, there will be multiple IRRs

IRR 1 = 7.67%

Year CF Discount Factor Discounted CF
0 $ -25,000.00 1/(1+0.0766781545586726)^0= 1 1*-25000= -25,000.00
1 $   78,000.00 1/(1+0.0766781545586726)^1= 0.92878266 0.92878265967038*78000=    72,445.05
2 $ -55,000.00 1/(1+0.0766781545586726)^2= 0.862637229 0.862637228904384*-55000= -47,445.05
NPV = Sum of all Discounted CF             -0.00

IRR 2 = 104.34%

Year CF Discount Factor Discounted CF
0 $ -25,000.00 1/(1+1.0434)^0= 1 1*-25000= -25,000.00
1 $   78,000.00 1/(1+1.0434)^1= 0.489380444 0.489380444357443*78000=    38,171.67
2 $ -55,000.00 1/(1+1.0434)^2= 0.239493219 0.239493219319489*-55000= -13,172.13
NPV = Sum of all Discounted CF                   -  

Payback period:

Year Opening Balance CF Closing Balance
0 $         25,000.00
1 $            25,000.00 $   78,000.00 $        -53,000.00

Project D

Year CF Discount Factor Discounted CF
0 $   -9,000.00 1/(1+0.06)^0= 1 1*-9000=     -9,000.00
1 $     6,000.00 1/(1+0.06)^1= 0.943396226 0.943396226415094*6000=      5,660.38
2 $     1,000.00 1/(1+0.06)^2= 0.88999644 0.88999644001424*1000=          890.00
NPV = Sum of all Discounted CF     -2,449.63
PI 0.73

As the sum of undiscounted CFs is less than initial investment, this project will not have a positive IRR

Measure A B C D
NPV 14,205.50 15,912.79 1238.19 -2449.63
PI 1.36 1.40 1.05 0.73
IRR 32.95% 19.78% 7.67% NA
IRR2 NA NA 104.34% NA
Payback period 2 years 4 years 1 year Investment is not recovered

Problem 1) X = 2-4 = -2 so correct option is b)

Problem 2) c)104.3% is one of the IRRs and another IRR exists

Problem 3) IRR of Project B is e)19.78%

Problem 4) NPV of Project C is b)$1,238

Problem 5) Project D never pays back the initial investment

Problem 6) Profitability index (PI) of Project A is a)1.36

Add a comment
Know the answer?
Add Answer to:
​​​​​​ Problem 1) Take the difference between the payback period of Projects A and B, i.e.,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cas a llars) a. What is the payback period on each of the projects? b. If...

    Cas a llars) a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? e. If you use a cutoff period of 3 years, which projects will you accept? d-1. If the opportunity cost of capital is 10%, calculate the NPV for projects A. B. and C. (Negative amounts should be indicated by a minus sign. Do not round Intermediate calculations,...

  • a. What is the payback period for Project A? b.What is the payback period for Project...

    a. What is the payback period for Project A? b.What is the payback period for Project B? c. What is the discounted payback period for Project A? d. What is the discounted payback period for Project B? e. What is the NPV for Project A? f. What is the NPV for Project B? g. What is the IRR for Project A? h. What is the IRR for Project B? i. What is the profitability index for Project A? j. What...

  • KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value...

    KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value (NPV) c. Internal rate of return (IRR) d. NPV profile; crossover rate e. Mutually exclusive projects; independent projects f. Nonnormal cash flows; normal cash flows; multiple IRRS g. Modified internal rate of return (MIRR) h. Payback period; discounted payback CAPITAL BUDGETING CRITERIA You must analyze two projects, X and Y. Each project costs $10,000, and the firm's WACC is 12%. The expected cash flows...

  • Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects....

    Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects. Its WACC is 10%, and the projects' after-tax cash flows (in millions of dollars) would be as follows: Expected Cash Flows Time Project A Project B 0 ($30) ($30) 1 $5 $20 2 $10 $10 3 $15 $8 4 $20 $6 a.   Calculate the projects' NPVs, IRRs, MIRRs, regular paybacks, and discounted paybacks. WACC = 10% Use Excel's NPV function as explained in NPVA...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A negative $ 51 $ 25 $ 22 $ 21 $ 13 B negative $ 99 $ 22 $ 42 $ 50 $ 59 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.1 %​, what are the NPVs of the two​ projects?...

  • Please include formulas Problem 8-21 NPV and Payback Period [LO 1, 4] Kaleb Konstruction, Inc., has...

    Please include formulas Problem 8-21 NPV and Payback Period [LO 1, 4] Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 11 percent. Year WN Project F -$ 144,000 55,500 54,500 64,500 59,500 54,500 Project G -$ 214,000 35,500 50.500 94,500 124,500 139,500 Required: (a) Calculate the payback period for both projects. (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g.,...

  • Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$194,527...

    Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$194,527 –$15,905 1 27,700 5,627 2 52,000 8,470 3 52,000 13,908 4 413,000 8,564 Whichever project you choose, if any, you require a 6 percent return on your investment. a. What is the payback period for Project A? b. What is the payback period for Project B? c. What is the discounted payback period for Project A? d. What is the discounted payback period for...

  • ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...

    ​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$85.000 and expected free cash flows of ​$20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?

  • (Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash...

    (Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 - $50 $18 $19 $17 - $101 $21 $40 $51 $26 $59 a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT