Production in first 8 hours will be = 90 x 8 = 720 units
cost for producing 720 units will be $ 4248 x 8 = 33984.
Now balance production required will be = 967 - 720 = 247 units.
Production rate per hour after overtime will be = 90 x 92% = 82.80 units. (Productivity drops by 8% because of overtime)
Hourly cost of manpower will increase by 50% i.e. 4248 x 150% = 6372.
So additional cost for producing 247 units will be = (247 / 82.80) x 6372 = 19008.26
Hence total cost = 33984 + 19008.26 = $ 52992.26
Answer: $52992.26
An assembly line can produce 90 units per hour. The line's hourly cost (total salaries of...
2-8 A An assembly line can produce 80 units per hour. The line's hourly cost is $4250 on straight time (the first 8 hours). Workers are guaranteed a minimum of 5 hours. There is a 35% premium for overtime, however, productivity for overtime drops by 10%. What are the average and marginal costs per unit for the following daily quantities? (a) 350 (b) 500 (c) 640 (d) 850
1- An assembly line can produce 90 units per hour. The line’s hourly cost is $4,500 on straight time (the first 8 hours). Workers are guaranteed a minimum of 6 hours. There is a 50% premium for overtime, however, productivity for overtime drops by 5%. What are the average and marginal costs per unit for the following daily quantities? 450 600 720 900 2- Owning, operating and maintaining an automobile carries with it private internal costs to the driver, as...
cost estimation PROB #2: LearningCurve An activity to produce 100 units was planned for 40 working days of 8 hours each, for one 5 person crew at KD 10 per hour per person. Because of owner required acceleration, the contractor worked with 2 crews of 5 people each for 10 hour per day. The contractor had to pay KD 15 per hour per person for the overtime hours above 8 hr day. For this work, LP 85% ( for learning...
Question 17 3 points Save Answer Compute the total productivity measure, in units/dollar, for an eight-hour day in which the usable output was 3,463 units, produced by three workers who used 596 pounds of materials. Workers have an hourly wage of $22, and material cost is $2 per pound. Overhead is 1.5 times labor cost. (Write your answer using TWO decimal places). Question 18 Toyota is famous for several innovations, including its TPS. What is the production strategy they follow...
Save Answer Question 17 3 points Compute the total productivity measure, in units/dollar, for an eight-hour day in which the usable output was 2,770 units, produced by three workers who used 503 pounds of materials. Workers have an hourly wage of $19; and material cost is $2 per pound, Overhead is 1.5 times labor cost. (Write your answer using TWO decimal places).
Question 17 3 points Save Answer Compute the total productivity measure, in units/dollar, for an eight-hour day in which the usable output was 3,463 units, produced by three workers who used 596 pounds of materials. Workers have an hourly wage of $22, and material cost is $2 per pound. Overhead is 1.5 times labor cost. (Write your answer using TWO decimal places).
9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate 50 wklyr, 5 shifts/wk, 8 hr/shift. Expected line efficiency is 96%. There will be one worker per station. Determine (a) average hourly production rate, (b) cycle time, and (c) ideal minimum number of workstations.(6 pts) 9. A new product is to be assembled on...
suppose that a second shift is added to the assembly department. what is the new capacity of the assembly department Below is the XYZ operation. Molded Parts Mold Parts Finished Componen Final Assembly Purchased Pary Vnventory Purchase Parts from Vendors Assumptions 1) One worker is needed to operate each machine in the molding dept. 2) The molding dept. has 10 machines. 3) Currently 6 workers in the molding dept., earning $15 per hour. 4) Each molding machine produces 25 parts...
USE LEVEL AGGREGATE PLAN: Cost data Regular time labor cost per hour $10 Overtime time labor cost per hour $15 Subcontracting cost per unit $80 Back order cost per unit per period $20 Inventory holding cost per unit per period $10 Hiring cost per employee $400 Firing cost per employee $500 Capacity data Beginning workforce 40 employees Beginning inventory 0 units Beginning backorders 0 units Production standard per unit (hours) 2 hours of labor per unit Regular time available per...
Activity Activity Rate Casting $ 29 X per machine hour Assembly $ 15 → per direct labor hour Inspecting $ 12 ✓ per inspection Setup $ 146 ✓ per setup Materials handling $ 50 per load b. Use the activity rates in (a) to determine the total and per-unit activity costs associated with each product. Round the per unit amounts to the nearest cent. Product Total Activity Cost Activity Cost Per Unit Entry Lighting Fixtures Dining Room Lighting Fixtures $...