LABOR = 456
MATERIAL = 1006
OVERHEAD = 684
OUTPUT = 2770
MULTIFACTOR PRODUCTIVITY = OUTPUT / TOTAL INPUT = 2770 / (456 + 1006 + 684) = 1.29
Save Answer Question 17 3 points Compute the total productivity measure, in units/dollar, for an eight-hour...
Question 17 3 points Save Answer Compute the total productivity measure, in units/dollar, for an eight-hour day in which the usable output was 3,463 units, produced by three workers who used 596 pounds of materials. Workers have an hourly wage of $22, and material cost is $2 per pound. Overhead is 1.5 times labor cost. (Write your answer using TWO decimal places).
Question 17 3 points Save Answer Compute the total productivity measure, in units/dollar, for an eight-hour day in which the usable output was 3,463 units, produced by three workers who used 596 pounds of materials. Workers have an hourly wage of $22, and material cost is $2 per pound. Overhead is 1.5 times labor cost. (Write your answer using TWO decimal places). Question 18 Toyota is famous for several innovations, including its TPS. What is the production strategy they follow...
QUESTION 2 3 p Compute the multifactor productivity measure for an 8 hour day in which the usable output was 630 units, produced by 5 workers who used 905 pounds of materials. Workers have an hourly wage of 17 and material cost is 2.2 per pound. Overhead is 1.5 times labor cost The multifactor productivity (units/S)- decimal places) (round to 4
Compute the multifactor productivity measure for an 8 hour day in which the usable output was 920 units, produced by 6 workers who used 354 pounds of materials. Workers have an hourly wage of 19 and material cost is 3.2 per pound. Overhead is 1.6 times labor cost. The multifactor productivity (units/$) = Blank 1 (round to 4 decimal places)
please answer both questions % (round to 2 decimal places) QUESTION 2 Compute the multifactor productivity measure for an 8 hour day in which the usable output was 653 units, produced by 7 workers who used 534 pounds of materials. Workers have an hourly wage of 19 and material cost is 1.2 per pound. Overhead is 1.5 times labor cost 3 paints The multifactor productivity (units/S) (round to 4 decimal places) QUESTION 3 3points ve A A health club has...
Please answer the following question correctly please: Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Output (units) 32,000 37,000 28,000 38,000 Week Workers Material (lbs) 470 520 480 580 3 Week MFP (output /Total Cost)
Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost Material cost is $9 per pound. (Round your answers to 2 decimal places.) Workers Material (1lbs) t (units) 25,000 30,000 35,000 45,000 400 450 550 650 12 MFP (Output/Total Cost)
Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Week Output (units) 26,000 31,000 29,000 33,000 Workers Material (1bs) 400 450 490 510 WeekMFP (output/ Total Cost)
Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $14. Overhead is 1.5 times weekly labor cost. Material cost is $8 per pound. (Round your answers to 2 decimal places.) Week Output (units) Workers Material (lbs) 1 29,000 4 470 2 34,000 7 540 3 30,000 7 490 4 35,000 9 530
Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) ] Week Output (units) Workers Material (lbs) 1: 28,000 7 430 2: 33,000 8 480 3: 32,000 4 520 4: 42,000 9 620