Question

Three options are under review for controlling neighborhood flooding during heavy rainstorms. All options are expected...

Three options are under review for controlling neighborhood flooding during heavy rainstorms. All options are expected to be in place for 50 years. The options differ both in cost and damage averted when a heavy rain event occurs. A promise has been made to build one option so ‘doing nothing’ is not a political acceptable alternative. When considering weather driven damage the usual method is to list the level of damage in currency terms and to state the likelihood that the damage will occur in terms of frequency that the weather event will occur. For example, a damage estimate of 500,000 for a twenty year event is interpreted that the event will occur on average once every 20 years or has a probability of 0.05 occurring this year so the expected damage this year is 0.05 times 500,000 which equals 25,000. If an intervention prevented all damage from such an event the benefit would be shown as 25,000 every year. Apply incremental benefit cost analysis to this situation using an interest rate of 7.0% and answer the questions that follow.

Option A B C
Investment 2.4 Million 1.6 Million 4.1 Million
Annual Operating Cost 85,000 92,000 35,000
Annual Benefit 160,000 140,000 290,000
Annual Disbenefit 12,000 1,000 21,000

a. What is the B/C for option A?

b. What is the B/C for option B?

c. What is the B/C for the difference between option B and A?

d. Complete the analysis for all options and based on the analysis, which option is the best public investment?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Please see the table below. Please be guided by the second column titled “Linkage” to understand the mathematics. Y The last row highlighted in yellow is your answer. Figures in parenthesis, if any, mean negative values. All financials are in $.

Option Linkage A B C B - A
Investment A       2,400,000     1,600,000         4,100,000            (800,000)
Annual Operating Cost B 85,000 92,000 35,000                  7,000
Annual Benefit C 160,000 140,000 290,000              (20,000)
Annual Disbenefit D 12,000 1,000 21,000              (11,000)
Net Benefit E = C - D 148,000 139,000 269,000                 (9,000)
Period F 50 50 50 50
Interest rate G 7% 7% 7% 7%
PV of net benefits H = E/G x (1 - (1 + G)^(-F))       2,042,510     1,918,304         3,712,401            (124,207)
PV of costs I = B/G x (1 - (1 + G)^(-F))+ A       3,573,063     2,869,669         4,583,026            (703,395)
B/C J = H / I        0.571641      0.668476         0.810033            0.176582

You can see the answer of Part (a), (b ) & (c) in the yellow colored row above.

Part (d) Analysis for all the options are shown above. Based on B/C ratio, Option C has the highest B/C ratio, even though it's not > 1. Hence, among all the options  available, Option C is the best one.

Add a comment
Know the answer?
Add Answer to:
Three options are under review for controlling neighborhood flooding during heavy rainstorms. All options are expected...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (15 pts) A project to control flooding from rare, but sometimes heavy rainfalls in the arid...

    (15 pts) A project to control flooding from rare, but sometimes heavy rainfalls in the arid southwest will have the cash flows shown below. Determine which project should be selected on the basis of a B/C analysis at 1-8% per year and a 20 year study period. (Keep in mind do nothing is not an option) 3. Sanitary SewersOpen Channels 48 million 1st Cost, S (SW City Cost) M&O Cost, Sper year (SW City Cost) Homeowner clean up $ costs,...

  • Three sites (A, B & C) are being considered for flood control dams. The three construction...

    Three sites (A, B & C) are being considered for flood control dams. The three construction costs are $10 million, $12 million and $20 million; and the annual maintenance costs are expected to be $15,000, $20,000 and $23,000 respectively for sites A, B and C. In addition, a $75,000 refurbishing expenditure will be required every 10 years at each site. Every year without the dams, $2 million in flood damage occurs. It is projected that dam A, by itself, would...

  • An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss....

    An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss. It has been proposed that the river channel be improved by straightening and deepening it at a cost of$2,400,000​, to reduce the annual probability of flooding to 0.364  during a period of 18 years before it would have to be deepened again. This procedure would...

  • Real options problems 2. You just finished a week of heli-skiing and had such a good...

    Real options problems 2. You just finished a week of heli-skiing and had such a good time that you want to go again next year. Plus, the heli-ski outfit is offering the following deal: If you pay for your vacation now, you can get a week of heli-skiing for $2,500. However, if you cannot ski because the helicopters cannot fly due to bad weather, there is no snow or you get sick, you do not get a refund. There is...

  • 6. Hedging with forwards, options and money market. Princess Cruise Company (PCC) purchased a ship from Mitsubishi Heavy...

    6. Hedging with forwards, options and money market. Princess Cruise Company (PCC) purchased a ship from Mitsubishi Heavy Industry for 500 million yen payable in one year. The current spot rate is ¥124/$ and the one year forward rate is ¥110/$. The annual interest rate is 5 percent in Japan and 8 percent in the U.S. PCC can also buy a oneyear call option on yen at the strike price of $0.0081 per yen for a premium of 0.014 cents...

  • Please Answer all parts NEedUS Pharmaceuticals is exploring options for shipping a $9.5 million dollar machine...

    Please Answer all parts NEedUS Pharmaceuticals is exploring options for shipping a $9.5 million dollar machine to its main plant. Holding cost is high for this type of machinery because of opportunity costs. The machine is not available for production while in transit resulting in lost revenue from a highly profitable drug. The annual holding cost is 40%. Options are: A, 40 day transit costing 95,000, B. 25 day transit costing 160,000, and C, 15 day transit costing 280,000. a....

  • A metal plating company is considering three different methods for recovering by-product heavy metals from a...

    A metal plating company is considering three different methods for recovering by-product heavy metals from a manufacturing site’s liquid waste. The investment costs and incomes associated with each method have been estimated. All methods have a 10-year life. The MARR is 12% per year. Using internal rate of return method, determine which method should be selected A metal plating company is considering three different methods for recovering by-product heavy metals from a manufacturing site's liquid waste. The investment costs and...

  • Please Show all work and formulas! Problem 4 You have just won a lottery of $1...

    Please Show all work and formulas! Problem 4 You have just won a lottery of $1 million and you can choose among the following three payout options.  The effective annual interest rate (EAR) is 5%. Option A: $200,000 right now and $100,000 every two years, starting 2 years from now and ending 16 years from now. Option B: $100,000 a year at the end of the next 10 years, with the first payment one year from today. Option C: Twenty annual...

  • A company that manufactures magnetic membrane switches is investigating three production options that have the estimated...

    A company that manufactures magnetic membrane switches is investigating three production options that have the estimated cash flows below. Given that the interest rate is 13.9761942% per year compounded continuously, (a) Determine which option is preferable (b) If the options are independent, determine which are economically acceptable (All dollar values are in millions). A B C First Cost -30 -2 0 Annual Cost -5 -0.2 -2 Annual Income 14 1.5 2.5 Salvage Value 7 - - Life,years 10 Infinity 5...

  • Consider a $5,000 payment that is to be received exactly three (3) years from now. If...

    Consider a $5,000 payment that is to be received exactly three (3) years from now. If the discount rate is 5%, what is the “present value” of the future $5,000 payment? Group of answer choices a. $4,319.19 b. $4,750.00 c. $4,761.90 d. $5,788.13 A pharmaceutical firm has recently developed a new medication, and is now considering whether or not to market the new medication over the next two years. The firm has decided to use “cost-benefit analysis” to make its...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT