Question

Sensitivity Analysis Question: A chemicals company produces two main products, C and B. The market price...

Sensitivity Analysis Question:

A chemicals company produces two main products, C and B.

The market price of C is £205 and that of B is £155 per 100 kg. The resource requirements for producing 100 kg of each of the two products are:

      Cost of                Process 1         Process 2              

                                      Materials              Labour             Labour

                                      £                        Hours              Hours

C                                    75                       4                   5

B                                    60                       5                   2.5

Labour in Process 1 costs £9 per hour. Labour in Process 2 costs £12 per hour. During the coming period the company will have the following resources available:

                                     

                                      Process 1    3,000 hours

                                      Process 2    2,500 hours

C is a long established product where demand has been reducing over the years. The company expects the demand on this product to be limited to 15,000 kg this year.

Required

  1. Formulate the linear programme for the optimum production plan using the existing resources available. (4 marks)

A solution to the linear programme is given below:

S1,S2 and S3 are slack variables for Process 1 and Process 2 and the maximum demand for Product C, respectively.

Final Tableau

C B        S1       S2        S3      Solution

                    B        0 1    0.2    0 -0.8    480

                    S2       0 0 -0.5 1 -3    550

                    C        1 0        0 0 1 150

Z 0 0       4 0 18 14,700

  1. Interpret the information given in the tableau above and show that it would be worthwhile paying the labour in Process 1 for overtime working at £11.00 per hour

(6 marks)

  1. Calculate how many extra hours in Process 1 could be worked on overtime before another binding constraint is created and calculate the extra contribution this would make.

(2 marks)

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a. Formulate the linear programme for the optimum production plan using
the resources available
Ans.
Let the company produce x kg of Product C and y kg of product B
Market price Cost of materials $ Process 1 labour hrs Labour cost per hour $ Process 1 labour cost Process 2 labour hrs Labour cost per hour $ Process 2 labour cost Profit per 100 kg
C 205 75 4 9 36 5 12 60 34
B 155 60 5 9 45 2.5 12 30 20
The linear programming problem for the question can be formulated as follows
Suppose we want to maximize the profit of producing product C and product B
Maximize Z = 34x + 20y
Subject to
4x + 5y <= 3000 Process 1 labour hours
5x + 2.5y <= 2500 Process 2 labour hours
x <= 15000 Product C demand limitation
Add a comment
Know the answer?
Add Answer to:
Sensitivity Analysis Question: A chemicals company produces two main products, C and B. The market price...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sensitivity Analysis Question: A chemicals company produces two main products, C and B. The market price...

    Sensitivity Analysis Question: A chemicals company produces two main products, C and B. The market price of C is £205 and that of B is £155 per 100 kg. The resource requirements for producing 100 kg of each of the two products are:       Cost of                Process 1         Process 2                                                     Materials              Labour             Labour                                       £                        Hours              Hours C                                    75                       4                   5 B                                    60                       5                   2.5 Labour in Process 1 costs £9 per hour. Labour in Process...

  • Question 3: Variance Analysis (20 marks in total) A Chill Menu Company produces cases of frozen...

    Question 3: Variance Analysis (20 marks in total) A Chill Menu Company produces cases of frozen food. During April, the company produced 1,450 cases of food and incurred the following actual costs: Variable overhead 11000 Fixed overhead 26000 Actual direct labour cost (8,000 direct labour hours) 151200 Actual material cost (30,000 kilograms purchased and used 66000 Standard cost and annual budget information is as follows: Standard cost per case Direct labour (5 hours @ $18) 90 Direct material (20 kilograms...

  • I need the answer to include solver and excel. Thank you. A Company produces two products....

    I need the answer to include solver and excel. Thank you. A Company produces two products. Relevant information for each product is shown in the Table below. The company has a goal of $48 in profits and incurs $1 penalty for each dollar it falls short of this goal. A total of 32 hours of labor are available. A $2 penalty is incurred for each hour of overtime (labor over 32 hours) used, and $1 penalty is incurred for each...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 21,000 units 28,000 units 35,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 22 $ 36 direct labor cost per unit ....... $18 $ 50 $ 62 variable overhead cost per unit...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A demand for next year ............. 21,000 units selling price per unit ........... $80 direct material cost per unit .... $24 direct labor cost per unit ........ $18 variable overhead cost per unit .. $22 Product B 28,000 units $120 $ 22 $ 50 $ 25 Product C 35,000 units $160...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 21,000 units 28,000 units 35,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 22 $ 36 direct labor cost per unit ....... $18 $ 50 $ 62 variable overhead cost per unit...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 21,000 units 28,000 units 35,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 22 $ 36 direct labor cost per unit ....... $18 $ 50 $ 62 variable overhead cost per unit...

  • XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...

    XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 21,000 units 28,000 units 35,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 22 $ 36 direct labor cost per unit ....... $18 $ 50 $ 62 variable overhead cost per unit...

  • Harrington Corporation produces three products, A, B, and C. Pertinent information on these products is as...

    Harrington Corporation produces three products, A, B, and C. Pertinent information on these products is as follows: Product Selling Price per Unit Variable Cost per Unit Fixed Cost per Unit DL Hours per Unit A (Anchor bolts) $ 8.00 $ 2.00 $ 3.00 1 B (Bearings) $ 3.60 $ 2.60 $ 4.00 2 C (Castings) $ 8.00 $ 4.00 $ 1.00 4 There are 160 direct labor hours available. Machine-hour capacity allows 100 anchor bolts, only; 40 bearings, only; 60...

  • 6 6 RS Question 2 (Marks:20) The accountant of Royal Products provided the following information for...

    6 6 RS Question 2 (Marks:20) The accountant of Royal Products provided the following information for purposes of determining the optimal product mix Product King (K) Product Queen (Q) Marginal income per unit R30 R36 Machine hours required per unit Marginal income per machine hour R6 Ranking in terms of machine hours 2nd Labour hours required per unit 6 Marginal income per labour hour R6 Ranking in terms of labour hours Annual demand for product in units 12 000 15...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT