Question

Q3. The Rogers Construction Company is trying to decide whether to make a bid on a...

Q3. The Rogers Construction Company is trying to decide whether to make a bid on a project against 4 competitors. The lowest bid will win the contract and be paid the amount they bid. It believes it will cost the company £10,000 to complete the project (if it wins the contract) and £350 to prepare the bid. Based on historical data, Rogers believes each competitor’s bid has a normal distribution with mean £15,000 and standard deviation £1,500. a) Set up a simulation model to help the company make the decision of how much to bid. (10 marks) b) Discuss on the obtained results and make suggestions. For example, what if the competitor’s bid has different distributions? (10 marks)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

b) Discuss on the obtained results and make suggestions. For example, what if the competitor’s bid has different distributions?

Recommended bid amount = $ 13,407

This decision will result in estimated profit of $ 3,057

If the competitor's bid has different distributions,

the simulation model will be modified to incorporate distribution of each competitor's bid.​​​​​​

As per HOMEWORKLIB RULES i can answer only b part.

Thank you

Please give thumb ?

Add a comment
Know the answer?
Add Answer to:
Q3. The Rogers Construction Company is trying to decide whether to make a bid on a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A building contractor is preparing a bid on a new construction project. Two other contractors will...

    A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for this project. In this case, the lowest bid wins the contract. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions (PLEASE SHOW IN EXCEL WITH FORMULAS FOR FULL RATING) A. Suppose the building contractor submits a bid of $650,000, what is the probability that the contractor submits the lowest bid and...

  • Decision Tree A company is trying to decide whether to bid for a certain contract or...

    Decision Tree A company is trying to decide whether to bid for a certain contract or not. They estimate that merely preparing the bid will cost $10,000. If their company bids, then they estimate that there is a 50% chance that their bid will be put on the “short-list”, otherwise their bid will be rejected. Once “short-listed”, the company will have to supply further detailed information (entailing costs estimated at $5,000). After this stage, their bid will either be accepted...

  • The controller of a construction company used a spreadsheet to develop a bid on a multi-million...

    The controller of a construction company used a spreadsheet to develop a bid on a multi-million dollar office complex. At the last minute he made a change and included $254,000 for overhead expenses he had forgotten about earlier. He inserted this number at the top of a column of numbers. Unfortunately the $254,000 was not included in the final total and the contract was underbid by that amount. The construction company was awarded the contract and was forced to make...

  • The management of Borealis Manufacturing Company is trying to decide whether to continue manufacturing a part...

    The management of Borealis Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, caled WISCO, component of the company's finished product The following information was collected from the accounting records and production data for the year ending December 31, 2020 1. The machining department produced 8,000 units of WISCO during the year 2. Variable manufacturing costs applicable to the production of each WISCO unit were direct materials...

  • Problem 7.35A - The management of Borealis Manufacturing Company is trying to decide whether to continue...

    Problem 7.35A - The management of Borealis Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it man outside supplies. The part, called WISCO, isa component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020: 1. The machining department produced 7,800 units of WISCO during the year 2. Variable manufacturing costs applicable to the production of each WISCO were...

  • Assess whether from a utilitarian, rights, justice and caring perspective, Unocal did the right thing in...

    Assess whether from a utilitarian, rights, justice and caring perspective, Unocal did the right thing in deciding to invest in the pipeline and then in conducting the project as it did. In your view, and using your utilitarian, rights, justice and caring assessments, did Unocal do the right thing? CASE: Unocal in Burma Union Oil Company of California, or Unocal, was founded in 1890 to develop oil fields around Los Angeles and other parts of California. By 1990, Unocal had...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT