Answer a-b: Fig. 3
Explanation: figure 1 has a wrong precedence relationship, A precedes B and F (not B and E). Fig. B and C have the same precedence relationships but different workstation assignments.
Workstation cycle time= production time/production requirement= 400 mins/62= 6.45 mins per unit. Hence the sum of the tasks in a workstation cannot be more than 6.45 mins.
In Fig. 2, workstation has G and H together which cannot be possible as the sum of task times of G and H is 8 mins. Therefore, Fig. 3 is correct.
Answer c: Effficiency= 83.72%
Explanation:
if the no. of workstation= 5
cycle time= 6.45 mins
Total task time ==1+3+1+4+2+3+2+6+2+3= 27 mins
Efficiency= total task time / no. of workstation* cycle time = 27/(5*6.45)= 0.8372 or 83.72%
Answer d: idle time= no. of workstation*cycle time – total task time= 5*6.45 - 27= 5.25 ~ 5 mins
Do ask, if you have any doubts through the comment section. Please rate the answer
Tailwind, Inc, produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for...
Tailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide more stability and better protection against knee, foot, and back injuries. Manufacturing the shoes requires 10 separate tasks. There are 400400 minutes available for manufacturing the shoes in the plant each day. Daily demand is 6464. The information for the tasks is as follows: Task Performance Time (mins) Predecessors A 11 minus− B 33...
Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...