Question

In project management, a work breakdown structure is Group of answer choices a a listing of...

In project management, a work breakdown structure is

Group of answer choices

a a listing of the work assignments given to the project team members.

b a detailed time schedule for each project activity.

c a top-down listing of all the tasks needed to complete a project.

d none of the above.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct answer is option C, i.e. a work breakdown structure is a top-down listing of all the tasks needed to complete a project. In project management, the project work is divided into distinct manageable sections with subcategory tasks. This helps in visualizing the entire project work and executing the project efficiently to achieve the required goals.

Add a comment
Know the answer?
Add Answer to:
In project management, a work breakdown structure is Group of answer choices a a listing of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Application Work Breakdown Structure In a single-person endeavor, it is relatively easy to understand the duties...

    Application Work Breakdown Structure In a single-person endeavor, it is relatively easy to understand the duties and responsibilities of the person. However, when you work in groups, the work should be distributed as appropriately as possible among the team members. As a PM, you can create a diagram called the work breakdown structure (WBS), which specifies the activities that need to be carried out and the responsibilities of the individuals. Complete the following tasks: 1. Write a set of tasks...

  • Project Management - Creating a Work-Breakdown Structure (WBS) Produce a WBS of at least 3 levels...

    Project Management - Creating a Work-Breakdown Structure (WBS) Produce a WBS of at least 3 levels (1.1.1) for a "Fun Walk-or-Run" event, intended to raise money for the local community. A minimum of 6 tasks of at least 3 levels (1.1.1) need to be identified.    Thank you.

  • Create a work breakdown structure

    Create a work breakdown for the project, the WBS should include up to the third level and must demonstrate dividing work up to multiple work items. A graphic chart must be used. Information :You have decided to enter a South African innovative App competition. The competition requires you (and your team) to think of an innovative idea that could lead to the development of an App aimed at assisting and benefiting south African citizens in the following category: (Government services)Some fundamental...

  • Create a Work Breakdown Structure ( WBS) for a design & build project of your choosing...

    Create a Work Breakdown Structure ( WBS) for a design & build project of your choosing (phone app) 10 – 15 tasks Establish precedents Determine critical path Determine finish date (or time)

  • Work Breakdown Structure Expectations The top level category has to be “Completion of Project Management Course,”...

    Work Breakdown Structure Expectations The top level category has to be “Completion of Project Management Course,” It must have the following multiple second-level categories: Initiation, Planning, Execution, and Close-out. My question is, for initiation, what type of information is that asking for? For example: initiation: read the syllabus, buy the text book. What else can be listed for under initiation.

  • QUESTION 22 Is the conversion of a project work breakdown structure (WBS) into an operating timetable....

    QUESTION 22 Is the conversion of a project work breakdown structure (WBS) into an operating timetable. O Project budget O Project schedule O Project scope O Project resources QUESTION 23 People are the most valuable resource in your project O True False QUESTION 24 A common mistake in project management is to appoint as project manager an individual with excellent skills but weak skills. O Technical; Managerial O Managerial: Technical O Technical: Social O Social: Managerial

  • QUESTION 6 All of the following are true about a work breakdown structure (WBS)EXCEPT which one?...

    QUESTION 6 All of the following are true about a work breakdown structure (WBS)EXCEPT which one? A The team and the project manager should be involved in creating it B. The accumulation of the work in the WBS should be equal to the work of the project, C. The activity sequencing of the WBS can be done only in parallel D. If the work is not listed in the WBS, it is not in the project.

  • Draw a work breakdown structure (WBS) with its key elements and their associated risks in project...

    Draw a work breakdown structure (WBS) with its key elements and their associated risks in project development of COVID-19 emergency response plan for a community of 5600 members and a limited project budget of $250,000 with following conditions: a. procurement, modification to, and set up of the vehicles carrying patients (ambulances) and supplying water, PPE and disinfection services. b. recruitment and hiring of drivers, buyers, logistics specialists, etc. c. training – all types d. supply chain establishment and original stock...

  • An overriding, key TRADE OFF to consider in inventory management is Group of answer choices how...

    An overriding, key TRADE OFF to consider in inventory management is Group of answer choices how many items to hold in inventory vs. location of the facility. how often to purchase items vs. how quickly you receive them. inventory holding costs vs. set up or order costs. carrying cost vs. warehouse expenses. None of the above. Considering inventory, the following statements are true EXCEPT ______. Group of answer choices Inventory ties up working capital. Inventory is an expensive asset. Inventory...

  • With the information given, write a project management plan and work break down structure (WBS), Mary...

    With the information given, write a project management plan and work break down structure (WBS), Mary and her fiancé, Bobby Doe, have decided to get married on August 15, 2021. The start date of this project is August 15, 2021. The project managers will be a wedding consulting firm. This project will define, plan, execute, and implement the wedding. The project aims to prepare a wonderful wedding experience for both families and also for wedding guests. The budget will be...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT