Question

1. ABC Company needs to plan workforces and production levels for the six-month period of January to June to produce the famous ABCzappers. The following table shows forecasted demand for zappers. At the end of December there are 200 workers employed. Ending inventory in December is expected to be 500 zappers, and management would like to have 750 zappers on hand at the end of June. The cost of hiring one worker is expected to be $500, the cost of firing one worker is expected to be $1,000, and the cost of holding one zapper in inventory for one month is estimated to be S10. In the past, in a 46 working-day period of time, 174 workers produced 8,000 zappers Feb 2,750 Mar 2,400 Ma 3,750 June 3,500 an Demand forecast Number of working days 3,500 4,600 24 25 26 20 a) If ABC plans production using a chase strategy (zero inventory plan), what workforce and production plan should we use? b) What are the total hiring/firing and inventory holding costs for this plan? c) If ABC plans production using a constant workforce plan (equal workforce levels for January through June), what workforce and production plan should we use? d) What are the total hiring/firing and inventory holding costs for this plan? e) Develop a mathematical programming model of the problem

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Worker productivity = 8000 zappers produced / (46 working days * 174 workers) = 8000/(46*174) = 8000/8004 ~ 1 zapper per worker per day

a) Chase Strategy - In this strategy workers are hired and fired to match the exact demand as much as possible.

J12 Q fx-SUMPRODUCT(16:19,J6:J9) B C Month Jan Feb Mar Apr May Jun Total Unit cost 2 Demand 3,500 2,7002,4004,6003,750 3,500

Formula:

C6 =B6+C5-C2 copy to C6:H6

C10 =B10+C8-C9 copy to C10:H10

J12 =SUMPRODUCT(I6:I9,J6:J9)

b) Total hiring/firing and inventory holding cost for this plan = $ 178,940

c) Constant workforce plan - In this plan, workers are hired or fired at the beginning of the planning period and thereafter, workforce is held constant throughout the planning period.

Total demand over 6 months period = (3500+2700+2400+4600+3750+3500) = 20450

Net requirement = Total demand - Initial inventory + Inventory required at the end of planning period = 20450-500+750 = 20700

Total working days in the planning period = 22+24+25+26+22+20 = 139

Therefore, level workforce required = 20700/139 = 149

Hence, number of workers to be fired in Jan = 200-149 = 51

Resulting plan is as follows:

BC 1 Month 2 Demand Jan Feb Mar Apr May Jun Total Unit cost 3,5002,7002,4004,6003,750 3,50020,450 139 24 25 26 20 4 Productio

d) Total cost of level workforce plan = $ 128,060

e) Mathematical model

Let Hi, Fi, Wi be the number of workers hired, fired and working in month i

Pi and Vi be the production and inventory in month i

Min ?Vi*10 + ?Hi*500 + ?Fi*1000

s.t.

Pi + Vi-1 - Vi = Di , where Di is the demand in month i

V0 = 500

V6 >= 750

Vi >= 0

Wi = Wi-1 + Hi - Fi

Pi = ni*Wi, where ni is the number of working days in month i

All variables >= 0

Add a comment
Know the answer?
Add Answer to:
1. ABC Company needs to plan workforces and production levels for the six-month period of January...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The washing machine plant is interested in determining work force and production levels for the next...

    The washing machine plant is interested in determining work force and production levels for the next 8  months. Forecasted demands for Jan‐Aug. are: 420, 280, 460, 190, 310, 145, 110, 125. Starting inventory  at the end of December is 200. The firm would like to have 100 units on hand at the end of August.  Suppose we are told that over a period of 40 days, the plant had 38 workers who produced 520 units.  Assume we are given the following number of working...

  • Solve in excell by using: 1) Chase strategy (zero inventory) 2) Level strategy (constant work force)...

    Solve in excell by using: 1) Chase strategy (zero inventory) 2) Level strategy (constant work force) ********** PLEASE PROVIDE ALL FORMULAS USED IN EXCELL ****************** Densepack is to plan workforce and production levels for the six-month period January to June. The firm produces a line of disk drives for mainframe computers that are plug compatible with several computers produced by major manufacturers. Forecast demands over the next six months for a particular line of drives produced in the Milpitas, California,...

  • Check The current aggregate demand requirements for a firm are shown below for the next six...

    Check The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct 230 Demand 210 210 210 240 260 Click here for the Excel Data File The firm always plans to meet all demand. The firm currently has 230 workers capable of producing 230 units in a month (1 unit/worker). The workforce can be increased (at a cost of $500 per worker) or decreased (at a cost of...

  • Check my wa will have 400 mowers in inventory at the beginning of the month and...

    Check my wa will have 400 mowers in inventory at the beginning of the month and desires to maintain at least that number at the end of each month. Assume hiring and layoff/firing, if necessary, occur at the beginning of the quarter. Below is other critical data: Production cost per unit = $230 Inventory carrying cost per month per unit = $50 (based on ending month inventory) Hiring cost per worker = $420 Firing cost per worker = $540 Beginning...

  • Sales and Operations Planning ABC Manufacturing is developing their 2020 SOP. The sales plan is already...

    Sales and Operations Planning ABC Manufacturing is developing their 2020 SOP. The sales plan is already developed, using the forecast obtained from Demand Management and is as follows: (the numbers are in 1000’s) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 420 375 425 600 200 100 150 250 420 390 420 450 Other problem parameters are: Initial worker level = 500, Initial inventory = 100,000, Required ending inventory = 220,000, Cost per unit = $50,...

  • How would you modify the workforce to reduce cost? What would be the cost of the...

    How would you modify the workforce to reduce cost? What would be the cost of the 46-worker production plan? Assume the following costs: • Holding Cost (per unit per month): $8.50 • Hiring Cost per worker: $800 • Firing Cost per worker: $1,250 • Payroll Cost: $75/worker/day Shortage Cost: $50 unit short/month • Assume that the work force at end of Dec was 40. • How many did you have to hire? Starting inver Ending invent 200 100 K= 0.342105263...

  • Given the following production plan: Briefly explain the differences between a Chase Production Strategy and a...

    Given the following production plan: Briefly explain the differences between a Chase Production Strategy and a Level Production Strategy, then use: (a) chase production strategy and (b) level production strategy to compute the monthly production, ending inventory or backlog, and workforce levels. A worker is capable of producing 50 units per month. Assume the beginning inventory as of January is 500 units, and the firm desires to have 200 units inventory at the end of June. Demand production EI workforce...

  • A firm must plan production for the next six months. Each unit costs $480 to produce...

    A firm must plan production for the next six months. Each unit costs $480 to produce and it has an inventory holding cost of $20 per unit per month based on ending inventory levels. The cost to hire a worker is $330, and the cost to fire a worker is $660 per worker. Each worker produces 10 units per month. There are 25 persons on the payroll at the beginning of the first month. The company currently has 200 units...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • A firm must plan production for the next six months. Each unit costs $370 to produce...

    A firm must plan production for the next six months. Each unit costs $370 to produce and it has an inventory holding cost of $23 per unit per month based on ending inventory levels. The cost to hire a worker is $220, and the cost to fire a worker is $440 per worker. Each worker produces 10 units per month There are 20 persons on the payroll at the beginning of the first month. The company currently has 150 units...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT