1.Make a Gantt Chart diagram that illustrates a possible issue with limited resource scheduling if the...

1.Make a Gantt Chart diagram that illustrates a possible issue with limited resource scheduling if the resources are not available? Make up an example “what if”- some of the project team get the flu at the same time, for instance? Your diagram should illustrate how much of the resource is needed over a short period of time, that there is not enough of the resource, and possible options to keep the project as close to schedule or budget as possible.

2. With a short paragraph discussing possible resource issues in your project?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Consider the Gantt chart shown below. First of all, every task needs to be passed through two machines (M1 and M2) in a series and there is only one worker to handle each of the machines. This is a typical example of resource constraint. Next during the period of 21-24 we see that the worker at M1 has a flu. This means that the Load 5 is delayed by 4 days due to unavailability of the worker. This sets back the schedule of the entire system by 4 days.

A1 B C DEFGHIK LMNO P QR STUVWX Y Z AA AB AC AD AE AFAGAH AI AJ AK AL AMANAO AP AQ AR AS AT AU AVAWAX AY AZ BA BB BC BD BE BF BG BH BI BJ BK E 1 2 3 45 6 789 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 M1 Load 1 M2 Mi M2 Load 6 M1 Load 5 10 M2 M1 12 13 Load 4 M2 14 15 17 M1 Load 2 M2 Mi Load 3 M2 20 23 25 26 27 28 , | Sheet521 | Sheet522 | Sheet524 Sheet523 | Sheet525 | Sheet526 | Sensitivity Report 36 | Sk. ④ READY 囲ロ凹 + 100%

2. While planning a project there can be various types of resource issues. While availability of workforce is a common example, the resources are not necessarily restricted to human beings. Consider the above example and we can notice that instead of flu if the machine M1 had a breakdown that would cause similar delay in the project. In addition to such resources, we must also consider the skill to tool matching within the project. For example worker 1 can only work on machine 1 and worker 2 on machine 2. This kind of situation adds to the[DS1] complexity of resource management in projects.

[DS1]

Add a comment
Know the answer?
Add Answer to:
1.Make a Gantt Chart diagram that illustrates a possible issue with limited resource scheduling if the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Compare the three popular scheduling tools (1) milestone chart, (2) Gantt chart, and (3) PERT/CPM...

    1. Compare the three popular scheduling tools (1) milestone chart, (2) Gantt chart, and (3) PERT/CPM network diagram regarding their strengths, weaknesses, and limitations. 2. How does modern information technology affect managerial power and leadership style? 3. How do you overcome team member resistance to accept or use a new project management tool, such as following a new design review process or using a new method for reporting progress or changes?

  • List one area of improvement that the group can make on analysis and synthesis. Make sure...

    List one area of improvement that the group can make on analysis and synthesis. Make sure all major applicable issues are identified. Have clear connections between ideas. List one area of improvement that the group can make on logic, clarity, and justification. Comment on whether or not the group has organized and developed ideas well with high degree of logical support and structure. List one area of improvement that the group can make on persuasiveness and overall effectiveness. Comment on...

  • In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software applicatio...

    In this assignment, you will be creating a Work Breakout Structure (WBS) for your project using the software application that you have selected. Prepare the WBS, and submit the file to your instructor. This assignment is due Sunday at 11:59 p.m. All assignments should be uploaded in the Assignment area. Project Software Options There are many project management software applications that are designed to help develop project plans and schedules as well as keeping track of these plans and creating...

  • Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expresse...

    Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...

  • Please read through the article below and answer the question at the end of the article....

    Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...

  • Assignment 8: Crisis Essay Goal Write a 500-word essay that critically analyzes the macroeconomic impact of...

    Assignment 8: Crisis Essay Goal Write a 500-word essay that critically analyzes the macroeconomic impact of the Great Recession in a country of your choice. In a previous module, you analyzed the United States. Even though the great recession originated in the US, it had world-wide repercussions for years to come, for this reason often also called the Global Financial Crisis (GFC). Like that previous module, you should discuss the antecedents in the country/case of your choice and the policies...

  • Assignment 8: Crisis Essay Goal Write a 500-word essay that critically analyzes the macroeconomic impact of...

    Assignment 8: Crisis Essay Goal Write a 500-word essay that critically analyzes the macroeconomic impact of the Great Recession in a country of your choice. In a previous module, you analyzed the United States. Even though the great recession originated in the US, it had world-wide repercussions for years to come, for this reason often also called the Global Financial Crisis (GFC). Like that previous module, you should discuss the antecedents in the country/case of your choice and the policies...

  • RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program...

    RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program they attended on the benefits of using agile and Scrum on some of their projects. Radico provided products and services to both public and private sector clients, almost all of it through competitive bidding. IT was not required for any of the products and services Radico provided. Agile and Scrum had proven to be successful on internal IT projects, but there were some concerns...

  • Only need help with question 5 2 CASE The Human Resource Function of Harrison Brothers Corporation...

    Only need help with question 5 2 CASE The Human Resource Function of Harrison Brothers Corporation COMPANY HISTORY Harrison Brothers Corporation n was founded in upstate New York on September 15, 1898, by Aubrey and William Harrison. Harrison Brothers is a multi-line traditional department store tha t cares mainly men's, wome expanded to include household furnishings and other items for the home. The long-term goal of the company is to become the leading chain of department stores in the Northeast,...

  • Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager,...

    Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager, which option would you select? What risks are involved with your choice and with ACL’s request? Shell Case Fabricators BACKGROUND Shell Case Fabricators (SCF) designs and builds shell casings that enclose electronic products such as calculators, cell phones, modems. Typically the cases are plastic or plastic compounds. SCF has six different production lines that cover different types of product. For example, the largest high...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT