Question

3. Given the following inventory, calculate the Economic Order Quantity and Reorder Point. Annual Requirements (R)...

3.

Given the following inventory, calculate the Economic Order Quantity and Reorder Point.

Annual Requirements (R) 7200 units
Setup Cost (S) 100 per order
Holding rate (k) 20% per year
Unit Cost (C) 20 per unit
Order lead time (LT) 6 days
Number of days per year 360

Please show work including formulas for EXCEL.  

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
3. Given the following inventory, calculate the Economic Order Quantity and Reorder Point. Annual Requirements (R)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Excel Online Structured Activity: EOQ Calculation The Las Vegas Corporation purchases a critical component from one...

    Excel Online Structured Activity: EOQ Calculation The Las Vegas Corporation purchases a critical component from one of its key suppliers. The operations manager wants to determine the economic order quantity, along with when to reorder, to ensure the annual inventory cost is minimized. The information obtained from historical data has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. Do not round intermediate calculations. Round your answers...

  • The Las Vegas Corporation purchases a critical component from one of its key suppliers. The operations...

    The Las Vegas Corporation purchases a critical component from one of its key suppliers. The operations manager wants to determine the economic order quantity, along with when to reorder, to ensure the annual inventory cost is minimized. The information obtained from historical data has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. Do not round intermediate calculations. Round your answers according to the input instructions for...

  • A manufacturer keeps a continuous inventory review system on the key component, part X. The annual...

    A manufacturer keeps a continuous inventory review system on the key component, part X. The annual demand on part X is 12,000 units and the demand rate is constant. The supplier charges $50 for each unit of part X. Each order costs $150 to process and annual holding cost per unit is 20% of the purchase price. (a) What is the economic order quantity? How many orders will be placed each year (365 days)? If the lead time is 3...

  • An automobile manufacturer stocks a certain inventory item. The daily demand for the inventory item is...

    An automobile manufacturer stocks a certain inventory item. The daily demand for the inventory item is 20 units. The company estimates its annual holding cost for this item to be $10 per unit. The cost to place and process an order from the supplier is $200. The company operates 300 days per year, and the lead time to receive an order from the supplier is 3 working days on average. (a)    Find the economic order quantity. (b)    Find...

  • a) What is the economic order​ quantity? _______ units ​(round your response to the nearest whole​...

    a) What is the economic order​ quantity? _______ units ​(round your response to the nearest whole​ number). ​b) What are the annual holding​ costs? $_________​(round your response to the nearest whole​ number). ​c) What are the annual ordering​ costs? $__________ ​(round your response to the nearest whole​ number). ​d) What is the reorder​ point? _______ units ​(round your response to the nearest whole​ number). Score: 1.5 of 2 pts 10 of 24 (23 complete) w score: 77.62% , 33.38 .....

  • Compute the safety stock (S.S.) and reorder point (ROP) for the following situation: Annual Demand =...

    Compute the safety stock (S.S.) and reorder point (ROP) for the following situation: Annual Demand = 6570 units Unit Price = $11 and no quantity discounts Ordering Cost = $25/order Holding Cost = $1.50/unit Lead Time = 5 days Desired Customer Service Level = 97.5% Assume 365 days/year and that demand and lead time are constant. Safety Stock = 10; ROP = 90 Safety Stock = 0; ROP = 90 Safety Stock = 5; ROP = 150 Safety Stock =...

  • The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time dema...

    The reorder point r = dm is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with...

  • SS LIMITED Inventory Cost Management Annual Holding Cost / unit Total Holding Cost / Buffer Stock...

    SS LIMITED Inventory Cost Management Annual Holding Cost / unit Total Holding Cost / Buffer Stock Total Holding Cost / Orders Fixed Cost / order Total Ordering Cost / Orders Total Cost Saving by Economic Order Quantity Annual Consumption, units     1,800,000 £1.50 £37.50 Quantity per Order, units           50,000 £42,000.00 £37,500.00 £1,350.00 £80,850.00 Economic Order Quantity, units             9,487 £42,000.00 £7,115.25 £7,115.00 £56,230.25 £24,619.75 Buffer Stock, units           28,000 Weekly Demand, units           36,000 Lead Time, weeks                     2...

  • The reorder point is defined as the lead-time demand for an item. In cases of long...

    The reorder point is defined as the lead-time demand for an item. In cases of long lead times, the lead-time demand and thus the reorder point may exceed the economic order quantity Q*. In such cases, the inventory position will not equal the inventory on hand when an order is placed, and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with D = 9,000,...

  • A certain company utilizes the Economic Order Quantity Run Size for its MRP Schedule. The company...

    A certain company utilizes the Economic Order Quantity Run Size for its MRP Schedule. The company has determined the EOQ is 180 units, the holding costs is 2.1% per unit per week, the cost to produce a unit is $1, and the the setup cost is $33.96. Consider the the following MRP schedule: Find the letter A in the table and calculate its value: Net Week Requirements 1 84 76 3 93 4 80 5 61 Production Quantity А B...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT