Question

A certain company utilizes the Economic Order Quantity Run Size for its MRP Schedule. The company has determined the EOQ is 180 units, the holding costs is 2.1% per unit per week, the cost to produce a unit is $1, and the the setup cost is $33.96. Consider the the following MRP schedule: Find the letter A in the table and calculate its value:

Net Week Requirements 1 84 76 3 93 4 80 5 61 Production Quantity А B Ending Inventory F G Н. Holding Cost K Setup Cost Р Q R

0 0
Add a comment Improve this question Transcribed image text
Answer #1

EOQ = 180 units,

holding costs = 2.1% per unit per week,

cost to produce a unit = $1,

setup cost = $33.96

Letter A represents the production quantity in week 1

Net requirement in week 1 is 84

We are using EOQ lot sizing.

Therefore, production quantity in week 1 = EOQ = 180 units

Value of A = 180 ANSWER

Add a comment
Know the answer?
Add Answer to:
A certain company utilizes the Economic Order Quantity Run Size for its MRP Schedule. The company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A certain company uses the Lot-for Lot run size for its production. The company has a...

    A certain company uses the Lot-for Lot run size for its production. The company has a holding cost of 3% per week on unsold inventory. Setup costs for a production run are $24.36. Consider the following MRP table: Find letter l in the table and calculate the value that should be there Holding Net Production Period Requirements Quantity Total Cost Cost Setup Cost p 1 81 Ending Inventory f g h a k u - V 115 78 b с...

  • Sandy’s Cabinet Company uses MRP to schedule its production. Due to the current recession and the...

    Sandy’s Cabinet Company uses MRP to schedule its production. Due to the current recession and the need to cut costs, Sandy has targeted the inventory investment area for cost reduction. However, the company does not want to reduce its customer service level in the process. Demand and inventory data for a standard two-drawer file cabinet are given in the following table. Complete an MRP matrix for the cabinet using (a) no lot sizing, (b) minimum of 200, and (c) multiples...

  • 4. Sandy's Cabinet Company uses MRP to schedule its production. Due to the current recession and...

    4. Sandy's Cabinet Company uses MRP to schedule its production. Due to the current recession and the need to cut costs, Sandy has targeted the inventory investment area for cost reduction. However, the company does not want to reduce its customer service level in the process. Demand and inventory data for a standard two-drawer file cabinet are given in the following table. Complete an MRP matrix for the cabinet using (a) no lot sizing, (b) minimum of 200, and (c)...

  • Economic Order Quantity Ottis, Inc., uses 656,100 plastic housing units each year in its production of...

    Economic Order Quantity Ottis, Inc., uses 656,100 plastic housing units each year in its production of paper shredders. The cost of placing an order is $24. The cost of holding one unit of inventory for one year is $12. Currently, Ottis places 162 orders of 4,050 plastic housing units per year. Required: 1. Compute the economic order quantity. X units 2. Compute the ordering, carrying, and total costs for the EOQ. Ordering cost $ X Carrying cost Total cost 3....

  • - Data Table for Problems 14.17 through 14.19* Period 1 2 3 4 5 6 7 8 9 10 11 12 requirements 30 ...

    please answer 14.17 - Data Table for Problems 14.17 through 14.19* Period 1 2 3 4 5 6 7 8 9 10 11 12 requirements 30 40 30 70 20 10 80 50 8 "Holding cost $2.50/unit/week; setup cost $150; lead time 1 week; beginning n Gross inventory 40 m14.17 Develop a lot-for-lot solution and calculate total rel- s evant costs for the data in the table for Problems 14.17 through d 14.19. Px 14.18 Develop an EOQ solution and...

  • sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior...

    sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...

  • 3. Calculate the Economic Ordering Quantity (EOQ) model Aa Aa Inventory costs can be categorized as...

    3. Calculate the Economic Ordering Quantity (EOQ) model Aa Aa Inventory costs can be categorized as the costs associated with holding the inventory, ordering and receiving the inventory, or running out of the inventory. For example, costs are the direct and indirect costs of keeping inventory on hand. carrying ordering The number of units in the optimal size order is called the economic ordering quantity (EOQ). Jones Company purchases custom-made durable packing boxes to ship its equipment. Each year, Jones...

  • 4.a) Find the savings between the total cost of the current production run size and the...

    4.a) Find the savings between the total cost of the current production run size and the optimal run size. b) Find the additional savings in production costs and ordering and holding costs with the proposed project. Calculate the payback period for the investment in the project. The anticipated annual demand for a chemical product distributed by the Seanna Chemical Group is 25,000 tons per year for the coming year. The company is currently producing the product with a capacity of...

  • CHAP 15 - Q13 DROPDOWN OPTIONS ARE BELOW THIS 13. Calculate economic ordering quantity (EOQ) Inventory...

    CHAP 15 - Q13 DROPDOWN OPTIONS ARE BELOW THIS 13. Calculate economic ordering quantity (EOQ) Inventory costs can be categorized as the costs incurred for holding the inventory, the costs of ordering and receiving the inventory, and the cost of running out of inventory. costs are the direct and indirect costs of keeping inventory on hand. The number of units in the optimal size order is called the economic ordering quantity (E0Q). Murphy Company purchases custom-made durable packing boxes to...

  • A company wishes to determine the optimal order quantity for its products. The product is sold...

    A company wishes to determine the optimal order quantity for its products. The product is sold at a rate of 800 per week. Each order costs $500. On average, the cost of each product is $8 and the holding cost is based on an annual percentage rate of 10% per product. The lead time for order arrival is 1.5 weeks. Respond to parts (a) Suppose that annual percentage rate may vary up to 14% per product. How much will the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT