Question

Sandy’s Cabinet Company uses MRP to schedule its production. Due to the current recession and the...

Sandy’s Cabinet Company uses MRP to schedule its production. Due to the current recession and the need to cut costs, Sandy has targeted the inventory investment area for cost reduction. However, the company does not want to reduce its customer service level in the process. Demand and inventory data for a standard two-drawer file cabinet are given in the following table. Complete an MRP matrix for the cabinet using (a) no lot sizing, (b) minimum of 200, and (c) multiples of 175 lot sizing. Which lot-sizing rule do you recommend?

Ordering cost =$100 per order

Holding cost = $1 per cabinet per week (Notice the unit change)

Lead time = 1 period

Beginning inventory = 150

Demand: Period 1/145 Period 2/165 Period 3/155 Period 4/135 Period 5/170

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a. No Lot Sizing
Period 1 2 3 4 5 Total
Item Demand 145 165 155 135 170
OH= 150 Scheduled Receipts 0 0 0 0 0
LT = 1 Projected On Hand | 150 5 0 0 0 0 5
Q = L4L Net Requirements 0 160 155 135 170
Planned Order Receipt 0 160 155 135 170
Planned Order Release 160 155 135 170 0
Cost:
Number of orders (order release) = 4
Total On-hand at end of period = 5
Ordering cost = $100
Holding cost per unit per period = $1.00
Total Ordering cost (number of orders * Ordering cost per order) = $400
Total holding cost (total On-hand* holding cost per unit per period) = $5
Total Cost = $405
b. Minimum order quantity 200
Period 1 2 3 4 5 Total
Item Demand 145 165 155 135 170
OH= 150 Scheduled Receipts 0 0 0 0 0
LT = 1 Projected On Hand | 150 5 40 85 150 180 460
Q = Minimum order quantity 200 Net Requirements 0 160 115 50 20
Planned Order Receipt 0 200 200 200 200
Planned Order Release 200 200 200 200 0
Cost:
Number of orders (order release) = 4
Total On-hand at end of period = 460
Ordering cost = $100
Holding cost per unit per period = $1.00
Total Ordering cost (number of orders * Ordering cost per order) = $400
Total holding cost (total On-hand* holding cost per unit per period) = $460
Total Cost = $860
c. Multiple of 175
Period 1 2 3 4 5 Total
Item Demand 145 165 155 135 170
OH= 150 Scheduled Receipts 0 0 0 0 0
LT = 1 Projected On Hand | 150 5 15 35 75 80 210
Q = Multiple of 175 Net Requirements 0 160 140 100 95
Planned Order Receipt 0 175 175 175 175
Planned Order Release 175 175 175 175 0
Cost:
Number of orders (order release) = 4
Total On-hand at end of period = 210
Ordering cost = $100
Holding cost per unit per period = $1.00
Total Ordering cost (number of orders * Ordering cost per order) = $400
Total holding cost (total On-hand* holding cost per unit per period) = $210
Total Cost = $610

We should go for no-lot sizing or Lot for Lot (L4L) as the total cost is less under this strategy. Under this rule the lot size ordered covers the demand for a single period (week) and minimizes inventory levels.

Add a comment
Know the answer?
Add Answer to:
Sandy’s Cabinet Company uses MRP to schedule its production. Due to the current recession and the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. Sandy's Cabinet Company uses MRP to schedule its production. Due to the current recession and...

    4. Sandy's Cabinet Company uses MRP to schedule its production. Due to the current recession and the need to cut costs, Sandy has targeted the inventory investment area for cost reduction. However, the company does not want to reduce its customer service level in the process. Demand and inventory data for a standard two-drawer file cabinet are given in the following table. Complete an MRP matrix for the cabinet using (a) no lot sizing, (b) minimum of 200, and (c)...

  • sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior...

    sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...

  • please answer the question asap. 24. Given 150 units of on hand inverntory, a lead time of one period, an ordering cost of $400, and a holding cost of S$2 per unit per period, determine the lowest...

    please answer the question asap. 24. Given 150 units of on hand inverntory, a lead time of one period, an ordering cost of $400, and a holding cost of S$2 per unit per period, determine the lowest cost lot sizing technique among Lot for Lot, and EOQ Use the gross requirements as given in the tables. Calculate here: Lot for Lot Period # 250 350 200 406 450 Gross 170 165 Requirement On Hand Inventory Requirements order receipts order release...

  • A certain company uses the Lot-for Lot run size for its production. The company has a...

    A certain company uses the Lot-for Lot run size for its production. The company has a holding cost of 3% per week on unsold inventory. Setup costs for a production run are $24.36. Consider the following MRP table: Find letter l in the table and calculate the value that should be there Holding Net Production Period Requirements Quantity Total Cost Cost Setup Cost p 1 81 Ending Inventory f g h a k u - V 115 78 b с...

  • Need help with b,c and d. A30 fx III. A B с 78 79 TOTAL LIABILITIES...

    Need help with b,c and d. A30 fx III. A B с 78 79 TOTAL LIABILITIES 80 81 b) In the next 3 months the following accounting events happened to the company (the VAT is 25% in each 82 event wherever it is possible). Record the accounting events in the books! (24p) 83 84 85 86 1. The owners opened a bank account and paid 300.000 K HUF in as a startup capital to launch the business. 87 88 2....

  • Apologies for the long question! L M N O P Q R S at 10 at...

    Apologies for the long question! L M N O P Q R S at 10 at A1 ✓ fx Part 2 C D E F G H I J K 7 The budget director for Bird House Unlimited, Inc., has gathered the following data for use in developing the budgeted income statement for January 2020. Estimated sales for January Bird House 34,000 units $42 per unit Bird Feeder 25,000 units $70 per unit Direct materials Estimated inventories at January 1(beginning)...

  • CASE 1-5 Financial Statement Ratio Computation Refer to Campbell Soup Company's financial Campbell Soup statements in...

    CASE 1-5 Financial Statement Ratio Computation Refer to Campbell Soup Company's financial Campbell Soup statements in Appendix A. Required: Compute the following ratios for Year 11. Liquidity ratios: Asset utilization ratios:* a. Current ratio n. Cash turnover b. Acid-test ratio 0. Accounts receivable turnover c. Days to sell inventory p. Inventory turnover d. Collection period 4. Working capital turnover Capital structure and solvency ratios: 1. Fixed assets turnover e. Total debt to total equity s. Total assets turnover f. Long-term...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT