please answer the question asap.
L4L
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Gross requirements | 200 | 165 | 170 | 140 | 250 | 350 | 450 |
Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Inv on hand | 150 | 0 | 0 | 0 | 0 | 0 | 0 |
Net requirements | 50 | 165 | 170 | 140 | 250 | 350 | 450 |
Planned order receipts | 50 | 165 | 170 | 140 | 250 | 350 | 450 |
Planned order releases | 165 | 170 | 140 | 250 | 350 | 450 | 0 |
Inventory holding cost = Avg inventory x cost of holding one unit per period
= 150/2 x2 = 150
Ordering cost = 6x400 =2400
Total cost = 2400+150 =2550
2. EOQ = [ 2 x demand x ordering cost / holding cost for entire duration ]1/2
= [ 2 x 1725 x400/2x7]1/2 = 314
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Gross requirements | 200 | 165 | 170 | 140 | 250 | 350 | 450 |
Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Inv on hand Beginning | 150 | 0 | 149 | 293 | 153 | 217 | 181 |
Inv on hand ending | 0 | 149 | 293 | 153 | 217 | 181 | 45 |
Net requirements | 50 | 165 | 21 | 0 | 97 | 133 | 269 |
Planned order receipts | 50 | 314 | 314 | 0 | 314 | 314 | 314 |
Planned order releases | 314 | 314 | 0 | 314 | 314 | 314 | 0 |
Inventory cost = 2181/2 x2 = 2181
Order cost = 400x5 =2000
Total cost = 2181+2000 =4181
please answer the question asap. 24. Given 150 units of on hand inverntory, a lead time of one period, an ordering cost of $400, and a holding cost of S$2 per unit per period, determine the lowest...
sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...
The following is a partial MRP table. Based on the information provided, an inventory holding cost of $0.39 per unit per week and a setup cost of $139 per order, what would be the planned order release for week 2 using a part period balancing lot sizing approach? Week Gross Requirements Scheduled Receipts On-Hand Inventory Net Requirements Time Phased Net Requirements Planned Order Releases 0 1 2 3 4 5 10 30 20 15 20 40 L | 10 40...
Using gross requirements schedule below, prepare an alternative ordering system that always orders 100 units the week prior to a shortage (a fixed order quantity of 100) as a Lot Sizing technique. What is the cost of this ordering system? Period Gross requirements 25 20 50 0 10 40 30 0 30 65 1 2 3 45 6 7 8 9 10 Holding cost $1/unitweek; setup cost $200; lead time 1 week beginning inventory 25 units. Prepare a net requirements...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
The Bloomington Bike Company produces two models: the Basic and the Supra. Herb Hoosier, the owner, plans to assemble 10 Basics and 15 Supras in each week during periods 4 to 8. Product structure trees for each bike are shown below: Develop a materials requirement plan (MRP) for component parts X and F over the next eight weeks. Data on all lead times, current inventory and ordering rules are given below: Scheduled receipts are: Period 1: 20 B’s, 18 W’s;...
Chapter 6 problemi (please use the MRP table for your answer -tae le r r Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8-week planning period. Use the lot-for-lot lot-sizing rule (net requirement). L (4) M (2) Item Lead Time Quantity on Hand Scheduled receipts 0...
Please help me correct this question. Thanks Problem 9-12 One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of...
American Electronics produces Tough-Robot for lawn mowing purposes. The production manager of American Electronics would like to create an MRP for their Tough-Robot with a minimum cost possible for the plan. The following table show gross requirements of Tough-Robot for ten weeks. You are asked to develop a solution using an ordering system that always orders 100 units the week prior to a shortage (a fixed order quantity of 100) as a Lot Sizing technique. What is the cost of...