ANS. HUDSON BY DIVISION MANUFACTURES TWO TYPES OF PANEL
LOW DENSITY AND HIGH DENSITY
TOTAL VARIABLE COST FOR THE TWO PANEL GIVEN BELOW
LDP HDP
UNSKILLED LABOR
.8 HOUR @10 $8 $8
SKILLED LABOR
LDP .25@20 5
HDP 1.00@20 20
RAW MATERIAL 6 9
PURCHASED COMPONENT 7 13
VARIABLE OVERHEAD 8 16
34 66
SELL PRICE 42 126
CONTRIBUTION PER UNIT $8 $60
FIXED OVERHEAD $140000
SKILLED LABOR .25 1.00
RATIO OF FIXED OVERHEAD 28000 112000
HUDSON CAN SELL UP TO7000 UNITS OF HDP REQUIRES 7000 HRS OF SKILLED LABOR
IT CAN MEED THE DEMAND OF TCH-320 AS IT HAVE SPARED CAPACITY OF SKILLED LABOR WHICH REQUIRES 12000 HRS FOR 12000 UNITS
TOTAL SKILLED LABOR NEEDED 12000+7000=19000 HRS OF SKILLED LABOR
BALANCE 44000-19000=25000 WHICH WOULD ABLE TO PRODUCE 100000 UNIT OF LDP
PRESENT VARIABLE COST OF TCH-320
UNSKILED LABOR .8 @ 12 9.6
SKILLED LABOR 3 HRS @18 54.0
RAW MATERIAL 12.4
PURCHASED COMONENT 170.0
VARIABLE OVERHEAD 140
260.0
AFTER ACQUIRING COMONENT FROM HUDSON NEW VARIABLE COST IS
UNSKILLED LABOR 9.6
SKILLED LABOR 3 HRS @18 54.0
ADDITIONL SKILLED LABOR 54.0
RAW MATERIAL 12.4
VARIABLE OVERHEAD 14.0
COST OF TRANSPORTING 5.0
PURCHASED COMPONENT 66.0
215.0
WHICH IS LOWER THAN PREVIOUS COST OF 260 BY45PER UNIT
HENCE IT IS ADVISABLE TO PURCHASE THE COMPONENT
MINIMUM
General Instrumentation Corporation manufactures dashboard instruments for heavy construction equipment. The firm is based in Baltimore,...