Draw and label a bar graph schedule showing Activities 1, 2, and 3. Activity 1 has...
From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.
Level the resource and schedule the activities based on the optimum resource usage. Then draw the S-curve knowing that the total cost of activities A, B, C, D, E, F and G is 2000$,3000$, 5000$, 6300$, 2500$, 4200$ and 1500$ respectively. Hint: you can use Excel to draw the histogram or S-curve. • Level the resource and schedule the activities based on the optimum resource usage. Then draw the S-curve knowing that the total cost of activities A, B....
Concerning the activities the following standards were set: ACTIVITY DESCRIPTION PRECEDING ACTIVITY ACTIVITY DURATION(DAYS) A Feasibility Study None 7 B Internal Specs A 5 C External Specs A 13 D Internal Analysis B 5 E Functional Specs C,D 10 F Hardware Specs E 15 G Hardware Acquisition F 5 H System Installation G 3 I Design material A 45 J System Testing H,I 10 a) Draw a network diagram (Activity-on-None) of the project presented in the case study with all...
1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...
question was answered QUESTION 5 Wh en planning a project there are several key points that must be considered. A bar chart based on the work breakdown structure (WBS) of a plant is a very clear means of presenting a programme of work. Draw a bar chart and a resource chart derived from the bar chart showing all salient values. [14] QUESTION 6 Table 1 shows the activities for a certain project. Due to the complexity of activities the project...
1. MICHAELIS-MENTON-(REQUIRED) a. Draw a simple graph, showing the classic Michaelis-Menton plot of enzyme activity as a function of substrate concentration; label both axes. Write the associated Michaelis-Menton equation and show the location of Km and Vmax on your graph. b. Draw a second graph showing the classic Lineweaver-Burk plot; label both axes. Show the location of Km and Vmax on your graph. Discuss which plot is the most useful to determine Vmax. Draw a second line on each graph...
2. In the following network, Draw the AON, calculate the early start and late start schedule, total and free floats, Allocate the resources, and level the resources for the following cases With a maximum of (8) laborer's per day. а. b. Level the resources to follow a normal distribution (start low, increase the resources gradually until it peaks in the middle, and then gradually decrease at the end of the project Duration Activity Predecessors laborers (days) A 2 В 2...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?
1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...
1. Given the major activities and their duration for a building project as follows: Activity DurationSuccessors B,C D,E,F HI,J K,L L,M K,L 10 4 (a) Draw the precedence network. (b) Calculate the EST, EFT, LST and LFT of each activity using the forward pass and backward pass methods entire project about a delay of the activity D by 3 days? (Remark: please redraw the diagram to verify (c) Highlight/identify the critical path in the precedence network and find the duration...