Level the resource and schedule the activities based on the
optimum resource usage. Then draw the S-curve knowing that the
total cost of activities A, B, C, D, E, F and G is 2000$,3000$,
5000$, 6300$, 2500$, 4200$ and 1500$ respectively. Hint: you can
use Excel to draw the histogram or S-curve.
Level the resource and schedule the activities based on the optimum resource usage. Then draw...
3. For the following schedule, draw the node network, perform the CPM calcula tions, mark the critical path, and complete the table TF FE LS LF ES IPA Duration Activity 2 A - A 4 A 6 C A 5 F B, C D, E, F 7 F 3 G
Question #2. (20 marks) The following table shows activities related to a small project and their weekly usage of labors. Smooth (level) the resource usage so that a preferred resource usage is obtained. Activity IPA Duration week) Labor/week start start start Selo F G H Question #3. (15marks) For the project information of question2 above, and referring to the field report below, perform a revised schedule, then comment on it. At the end of week 5 the following field information...
3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days. Activity Duration IPA ES EF LS LF TF FF A 2 - B 4 A C 6 A D 9 A E 5 B F 7 B, C G 3 D, E, F
5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days. Activity Duration IPA ES EF LS LF TF FF A 6 - B 2 - C 9 - D 4 A, B E 7 B F 5 D G 10 D, E H 8 C, F, G I 3 C, G J 2...
Draw the following network and calculate all dates (all activities are contiguous): Activity Duration IPA Type Rel Lag ES EF LS LF TF FF A 4 - B 3 - C 8 A D 7 A,B E 6 D SS 3 F 3 D FF G 5 F SS 2 2 F FF please do not copy from others, they are wrong
2. For the following project draw a node network and a bar chart. Then perform resource leveling trying to reduce the daily resources needed to no more than 8 laborers per day. If you cannot get it down to 8, manually shift resources so that the project starts low and gradually increases towards the middle and gradually decreases toward the end of the project Duration (days) laborers Activity IPA А 6 2 В 2 C 8 3 5 А, В...
From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.
I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors Time in Weeks A ---- 2 B A 5 C A 4 D B 3 E C, D 6 F D 3 G F 3 H E, G 4 Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and...
Schedule the following activities using CPM: Table 2 ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 8 B A 4 C A 4 D C 8 E B, D 2 F D 6 G E, F 2 Question 25 (1 point) What is the critical path? (Show your diagram and calculations) Question 25 options: A-C-D-E-G A-B-E-G A-B-D-E-G A-C-D-F-G A-B-D-F-G How many weeks will it take to complete the project? What is B slack time?
7. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Activity IPA Duration ES EF LS LF TF FF A - 3 0 3 3 6 3 5 B - 5 0 5 5 10 5 2 C A 6 3 9 9 14 5 4 D A, B 9 5 14 14 23 9 9 E A, B 4 5 9 9 12 7 4 F B 6...