Question

Finance

In a proposed flood control project, there are two possible sites, A and B, for a dam and storage reservoir. One or the other of these sites may be used but not both. Certain channel improvement is also considered; this will increase the capacity of the stream to carry flood discharge. Estimated first costs, lives, and annual operation and maintenance costs are as follows:


Site A

Site B

Channel Improvement

First cost

$6,000,000

$8,000,000

$1,000,000

Life

75 years

75 years

25 years

Annual O & M

$100,000

$140,000

$230,000

Annual capital recovery costs are to be computed using an interest rate of 5.5%. Assume zero salvage values at the end of the estimated lives.

The average annual amount of damages due to floods is estimated under various possible plans of development, as follows:

No flood control works at all

$1,200,000

Development at site A only

      380,000

Development at site B only

      260,000

Channel improvement only

      520,000

Site A plus channel improvement

      200,000

Site B plus channel improvement

      120,000

Compute the benefit to cost ratio for each of the five plans of development as compared to the alternative having no flood control (i.e. what is the derived benefit between an alternative and having no flood control). Assume that the annual costs of a dam and reservoir plus channel improvement alone. Compute any incremental benefit to incremental cost ratios for the combined projects as needed. Which plan of development, if any, would you recommend? Justify your answer using the engineering economics calculations you have performed.

3. A number of years have gone by with no flood control structures put in place for the flood control projects noted in problem 2. The estimated first costs, lives, and annual operation and maintenance costs are the same as stated in problem 2. The average annual damages without flood control are now double that shown in problem 2 and the interest rate for the projects is now 8%. Using these changes in data, calculate the benefit to cost ratios and incremental benefit to incremental cost ratios necessary to choose an alternative. Which plan to your recommend? Justify your answer using the engineering economics calculations you have performed


0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 9 more requests to produce the answer.

1 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Finance
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • 2. In a proposed flood control project, there are two possible sites, A and B, for...

    2. In a proposed flood control project, there are two possible sites, A and B, for a dam and storage reservoir. One or the other of these sites may be used but not both. Certain channel improvement is also considered; this will increase the capacity of the stream to carry flood discharge. Estimated first costs, lives, and annual operation and maintenance costs are as follows: Site A Site B Channel Improvement First cost $6,000,000 $8,000,000 $1,000,000 Life 75 years 75...

  • Finance

     In a proposed flood control project, there are two possible sites for a dam and storage reservoir, designated as the Willow and Cottonwood sites. One or the other of these sites may be used but not both. A small hydroelectric power development may be added at the Willow site. Certain channel improvements are also considered. Seven alternate projects are set up for analysis and average annual damages due to floods under each plan estimate as follows: Plan Damages A) Willow...

  • Three sites (A, B & C) are being considered for flood control dams. The three construction...

    Three sites (A, B & C) are being considered for flood control dams. The three construction costs are $10 million, $12 million and $20 million; and the annual maintenance costs are expected to be $15,000, $20,000 and $23,000 respectively for sites A, B and C. In addition, a $75,000 refurbishing expenditure will be required every 10 years at each site. Every year without the dams, $2 million in flood damage occurs. It is projected that dam A, by itself, would...

  • An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss....

    An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss. It has been proposed that the river channel be improved by straightening and deepening it at a cost of$2,400,000​, to reduce the annual probability of flooding to 0.364  during a period of 18 years before it would have to be deepened again. This procedure would...

  • Written solution please 5- The Nile Basin countries are considering three flood control projects in Ethiopia....

    Written solution please 5- The Nile Basin countries are considering three flood control projects in Ethiopia. Project A is a dam. The dam will have recreation and irrigation benefits as well as the flood control benefits. Projects B and C consist of permanent dikes along the river. Facts about the three projects are shown in the following table. Each project has a life of 25 years. The MARR is 10%. Use (a) BCR & (b) IRR method to choose the...

  • economics. asap!!! Page 6 of 6 r small dam is being planned for a river tributary that is subject to frequent foodi...

    economics. asap!!! Page 6 of 6 r small dam is being planned for a river tributary that is subject to frequent fooding. From past experience, the probabilities that water flow will exceed the design capacity of the dam during a year, plus relevant cost information, are as follows Estimated Annual Probability of Greater Flow Duringa Dam Damages if Water Flows Capital Investment (S) Exceed Design Capacity Year Design g(Independent for different years) 100,000 150,000 0.050 150,000 200,000 140,000 0.030 160,000...

  • "The City of Cedar Rapids has received three bids to construct and operate a new automobile...

    "The City of Cedar Rapids has received three bids to construct and operate a new automobile parking facility in its Downtown District. The three designs have different costs and will have different fee structures. The costs and benefits of each design are given below in thousands of dollars. Design 1 - Cost of site = $215 - Cost of building = $1700 - Annual fee collection = $767 - Annual maintenance cost = $445 Design 2 - Cost of site...

  • 1. Which alternative of the three alternatives below should be selected if the MARR = 6%?...

    1. Which alternative of the three alternatives below should be selected if the MARR = 6%? Use the following to compare projects: PW analysis B/C ratio for each project Incremental B/C ratio assessment IRR for each project over its respective service life Incremental IRR using the same (a common) number of years for each project Are any of the projects acceptable? Are any not acceptable? Which project would you recommend and why? Alternatives:                             A                     B                      C First Cost                                  $800                 $300                ...

  • Which alternative of the three alternatives below should be selected if the MARR = 6%? Use...

    Which alternative of the three alternatives below should be selected if the MARR = 6%? Use the following to compare projects: a. PW analysis b. B/C ratio for each project c. Incremental B/C ratio assessment (define Defender and Challenger in each analysis) d. IRR for each project over its respective service life e. Incremental IRR using the same (a common) number of years for each project Are any of the projects acceptable? Are any not acceptable? Which project would you...

  • brief explanation Solve this problem using the incremental Benefit - Cost ration with, expected life of 10 years and rat...

    brief explanation Solve this problem using the incremental Benefit - Cost ration with, expected life of 10 years and rate of return of 10% Alternative A Initial cost $50,000 Annual maintenance cost $4,000 Estimated annual benefit $10,000 Alternative B Initial cost $30,000 Annual maintenance cost $3,000 Estimated annual benefit $9,000 a. Select A with B/C =1.14 b. Select B with B/C = 1.14 c. Reject A with B/C = 1.14 d. Select B with B/C = 0.14

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT