Question

2. In a proposed flood control project, there are two possible sites, A and B, for...

2. In a proposed flood control project, there are two possible sites, A and B, for a dam and storage reservoir. One or the other of these sites may be used but not both. Certain channel improvement is also considered; this will increase the capacity of the stream to carry flood discharge. Estimated first costs, lives, and annual operation and maintenance costs are as follows:

Site A

Site B

Channel Improvement

First cost

$6,000,000

$8,000,000

$1,000,000

Life

75 years

75 years

25 years

Annual O & M

$100,000

$140,000

$230,000

Annual capital recovery costs are to be computed using an interest rate of 5.5%. Assume zero salvage values at the end of the estimated lives.

The average annual amount of damages due to floods is estimated under various possible plans of development, as follows:

No flood control works at all

$1,200,000

Development at site A only

      380,000

Development at site B only

      260,000

Channel improvement only

      520,000

Site A plus channel improvement

      200,000

Site B plus channel improvement

      120,000

Compute the benefit to cost ratio for each of the five plans of development as compared to the alternative having no flood control (i.e. what is the derived benefit between an alternative and having no flood control). Assume that the annual costs of a dam and reservoir plus channel improvement alone. Compute any incremental benefit to incremental cost ratios for the combined projects as needed. Which plan of development, if any, would you recommend? Justify your answer using the engineering economics calculations you have performed.

3. A number of years have gone by with no flood control structures put in place for the flood control projects noted in problem 2. The estimated first costs, lives, and annual operation and maintenance costs are the same as stated in problem 2. The average annual damages without flood control are now double that shown in problem 2 and the interest rate for the projects is now 8%. Using these changes in data, calculate the benefit to cost ratios and incremental benefit to incremental cost ratios necessary to choose an alternative. Which plan to your recommend? Justify your answer using the engineering economics calculations you have performed.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Benefit to cost ratio=Present value of benefit/Present value of cost

Site A Site B
First cost $6,000,000 $8,000,000
Total Initial Cost $6,000,000 $8,000,000
Annual O & M $100,000 $140,000
Present Value Of Annual O & M((Annual O& M*((1.055)^75-1)/(1.055^75*.055)) $1,785,395 $2,499,553
Total Present Value $7,785,395 $10,499,553
Benefit at Site A(No flood control works at all-Development at site A only
$1,200,000-380,000)
$820,000
Present Value of Benefit at Site A $14,640,237
Benefit to Cost ratio 1.88
Benefit at Site B(No flood control works at all-Development at site B only
$1,200,000-260,000)
$940,000
Present Value of Benefit at Site B $16,782,710
Benefit to Cost ratio 1.60
Channel Improvement $1,000,000
Annual O & M $230,000
Present Value Of Annual O & M $3,085,205
Total Present Value of cost $4,085,205
Benefit of Channel Improvement Only(No flood control works at all-Channel Improvement Only
$1,200,000- 520,000)
$680,000
Present Value of Benefit of Channel Improvement Only $9,121,474
Benefit to Cost ratio 2.23
Total Present Value of cost At Site A+channel Improvement $11,870,599
Total Present Value of cost At Site B+channel Improvement $13,584,757
Benefit of Site A plus channel improvement(No flood control works at all-Site A plus channel improvement
$1,200,000- 200,000)
$1,000,000
Present Value of Benefit of Site A plus channel improvement $17,853,947
Benefit to Cost ratio 1.50
Benefit of Site B plus channel improvement(No flood control works at all-Site B plus channel improvement
$1,200,000- 120,000)
$1,080,000
Present Value of Benefit of Site B plus channel improvement $19,282,263
Benefit to Cost ratio 1.42

Development at site A plus channel management must be pursued since Benefit to cost ratio is both above 1 and evenly balanced.

Site A Site B
First cost $6,000,000 $8,000,000
Total Initial Cost $6,000,000 $8,000,000
Annual O & M $100,000 $140,000
Present Value Of Annual O & M((Annual O& M*((1.08)^75-1)/(1.08^75*.055)) $1,246,108 $1,744,552
Total Present Value $7,246,108 $9,744,552
Benefit at Site A(No flood control works at all-Development at site A only
$1,200,000-380,000)
$820,000
Present Value of Benefit at Site A $10,218,089
Benefit to Cost ratio 1.41
Benefit at Site B(No flood control works at all-Development at site B only
$1,200,000-260,000)
$940,000
Present Value of Benefit at Site B $11,713,419
Benefit to Cost ratio 1.20
Channel Improvement $1,000,000
Annual O & M $230,000
Present Value Of Annual O & M $2,455,199
Total Present Value of cost $3,455,199
Total Present Value of cost At Site A+channel Improvement $10,701,307
Total Present Value of cost At Site B+channel Improvement $12,199,750
Benefit of Channel Improvement Only(No flood control works at all-Development at site B only
$1,200,000- 520,000)
$680,000
Present Value of Benefit of Channel Improvement Only $7,258,848
Benefit to Cost ratio 2.10
Benefit of Site A plus channel improvement(No flood control works at all-Site A plus channel improvement
$1,200,000- 200,000)
$1,000,000
Present Value of Benefit of Site A plus channel improvement $12,461,084
Benefit to Cost ratio 1.16
Benefit of Site B plus channel improvement(No flood control works at all-Site B plus channel improvement
$1,200,000- 120,000)
$1,080,000
Present Value of Benefit of Site B plus channel improvement $13,457,971
Benefit to Cost ratio 1.10

Development at Site A only should be pursued since BCR is 1.41.

*Please not that First cost are initial costs which are paid upfront and hence cannot be discounted.

Add a comment
Know the answer?
Add Answer to:
2. In a proposed flood control project, there are two possible sites, A and B, for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Finance

    In a proposed flood control project, there are two possible sites, A and B, for a dam and storage reservoir. One or the other of these sites may be used but not both. Certain channel improvement is also considered; this will increase the capacity of the stream to carry flood discharge. Estimated first costs, lives, and annual operation and maintenance costs are as follows:Site ASite BChannel ImprovementFirst cost$6,000,000$8,000,000$1,000,000Life75 years75 years25 yearsAnnual O & M$100,000$140,000$230,000Annual capital recovery costs are to be...

  • Finance

     In a proposed flood control project, there are two possible sites for a dam and storage reservoir, designated as the Willow and Cottonwood sites. One or the other of these sites may be used but not both. A small hydroelectric power development may be added at the Willow site. Certain channel improvements are also considered. Seven alternate projects are set up for analysis and average annual damages due to floods under each plan estimate as follows: Plan Damages A) Willow...

  • Three sites (A, B & C) are being considered for flood control dams. The three construction...

    Three sites (A, B & C) are being considered for flood control dams. The three construction costs are $10 million, $12 million and $20 million; and the annual maintenance costs are expected to be $15,000, $20,000 and $23,000 respectively for sites A, B and C. In addition, a $75,000 refurbishing expenditure will be required every 10 years at each site. Every year without the dams, $2 million in flood damage occurs. It is projected that dam A, by itself, would...

  • An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss....

    An area on the Colorado River is subject to periodic flood damage that​ occurs, on the​ average, every two years​ (i.e., probability of flooding in any year is​ 0.5) and results in a $2,200,000 loss. It has been proposed that the river channel be improved by straightening and deepening it at a cost of$2,400,000​, to reduce the annual probability of flooding to 0.364  during a period of 18 years before it would have to be deepened again. This procedure would...

  • Written solution please 5- The Nile Basin countries are considering three flood control projects in Ethiopia....

    Written solution please 5- The Nile Basin countries are considering three flood control projects in Ethiopia. Project A is a dam. The dam will have recreation and irrigation benefits as well as the flood control benefits. Projects B and C consist of permanent dikes along the river. Facts about the three projects are shown in the following table. Each project has a life of 25 years. The MARR is 10%. Use (a) BCR & (b) IRR method to choose the...

  • 1. Given the costs and benefits of two water pumps, what is the rate of return on the difference ...

    1. Given the costs and benefits of two water pumps, what is the rate of return on the difference of these alternatives? Year -$3000 +800 +800 +800 +800 +800 -$3800 +1200 +1200 +1200 +1200 +1200 What is your choice of these 2 alternatives and why? 2. The manager of a local restaurant is trying to decide whether to buy a charcoal broiling unit or an electric grill for cooking hamburgers. A market study shows customers prefer charcoal broiling but the...

  • ROR ANALYSIS WITH ESTIMATED LIVES THAT VARY Background Make-to-Specs is a software system under development by...

    ROR ANALYSIS WITH ESTIMATED LIVES THAT VARY Background Make-to-Specs is a software system under development by ABC Corporation. It will be able to translate digital versions of three-dimensional computer models, containing a wide variety of part shapes with machined and highly finished (ultra smooth) surfaces. The product of the system is the numerically controlled (NC) machine code for the part’s manufacturing. Additionally, Make-to-Specs will build the code for superfine finishing of surfaces with continuous control of the finishing machines. Information...

  • The Armstrong Manufacturing Company is considering two projects, however only one project can be chosen. Prepare an incremental analysis using the data provided. Include internal rate of return (IRR)...

    The Armstrong Manufacturing Company is considering two projects, however only one project can be chosen. Prepare an incremental analysis using the data provided. Include internal rate of return (IRR) for each alternative. Prepare a report to be presented to vice-president of manufacturing with your recommendation. The company uses a depreciation. The company’s effective income tax rate is 35%. The Armstrong Manufacturing Company is considering two projects, however only one project can be chosen. Prepare an incremental analysis using the data...

  • Guri Dam Project Management Brings Reliable Power and Growth To Remote Venezuelan Region Commonly known as...

    Guri Dam Project Management Brings Reliable Power and Growth To Remote Venezuelan Region Commonly known as Guri Dam, the Central Hidroeléctrica Raúl Leoni (Raul Leoni Hydroelectric Center) is one of the largest operating hydroelectric projects in the world. It is located in the Bolívar State in Venezuela’s Guayana region, and was built over a 23-year period using a phased construction concept. This design minimized the project’s initial investment and matched power supply to the growth in demand on Venezuela’s electrical...

  • Case 27 To Use or Not to Use? Beaufort Sea Production Company (BSPC) operates a medium-sized...

    Case 27 To Use or Not to Use? Beaufort Sea Production Company (BSPC) operates a medium-sized oil field on Alaska’s north coast. The field is still producing at its maximum rate, 325,000 barrels of oil per day (BOPD). However, to sustain this rate the company started a waterflood of the reservoir two years ago. Now a capacity bottleneck in the water disposal process is threatening to curtail production. In waterflooding, salt water from the Beaufort Sea is treated to remove...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT