Question

Joy Enterprises ?YE) uses a job costing system that requires the annual calculation of predetermined rates for its manufacturing overhead costs. Most jobs completed by DCE involve production activities in two departments, Machining and Assembly. Selected budgeted and actual data for 2016 are presented below as well as cost data for a particular job, #K-326, that was started and completed during 2016. Budgeted manufacturing overhead Actual manufacturing overhead Budgeted direct labor hours Budgeted machine hours Machining $400,000 $385,000 6,600 50,000 7,150 51,500 Assembly $300,000 5312,000 25,000 5,000 26,200 5,200 ACTUAL direct labor hours ACTUAL machine hours Job K-326 Direct materials cost $12,875 Direct labor cost: Machining (14 hrs @ $20 per hour) $280 Assembly (60 hours @$24 per hour) Machine hours used: $1,440 Machining Assembly Number of units in job K-326 1,150 hrs 35 hrs 220 units that JYE calculates departmental manufacturing overhead rates in each of its two Assume production departments. In Machining, the allocation base for manufacturing overhead in machine hours; in Assembly, the allocation base for manufacturing overhead is direct labor hours. Using the information above, answer questions 1-3 on the next page

media%2Ff61%2Ff6166d49-942d-4707-8d97-d5

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Calculation of Predetremined Manufacturing Overhead Rate

Predetremined Manufacturing Overhead Rate = Budgeted Manufacturing Overhead/Budgeted Cost driver relevant to the departement

Machining Assembly
Budgeted Manufaturing Overhead          400,000          300,000
Budgeted Labor Hours              6,600            25,000
Budgeted Machine Hours            50,000              5,000
Predetermined Manufacturing Overhead Rate                 8.00              12.00

2.

Total Cost of Job K-326
Direct Material      12,875.00
Direct Labor Hours
Machining (14hrs @ $20 per hr)            280.00
Assembly (60 hours @ 24 per hr)        1,440.00
Total Labor Cost        1,720.00
Overhead allocated
Machining ($8*1150 hrs)        9,200.00
Assembly ($12 * 35 hrs)            420.00
Total Overhead allocated        9,620.00
Total Cost of Job K-326      24,215.00
No of units produced                  220
Cost per unit            110.07

3.

Machining Assembly
Actual Manufaturing Overhead           385,000    312,000
Actual Labor Hours               7,150      26,200
Actual Machine Hours             51,500         5,200
Actual Manufacturing Overhead Rate                    7.5           11.9
Allocation to Job K-326 Machining Assembly
Actual Labor Hours 1150
Actual Machine Hours 35
Rate                    7.5           11.9
Total Cost         8,597.09      416.79
Overhead applied         9,200.00      420.00
Difference             602.91           3.21
Overapplied Overapplied
For JYE as a whole
Machining Assembly
Predetermined Manufacturing Overhead Rate                  8.00         12.00
Actual Labor Hours               7,150      26,200
Actual Machine Hours             51,500         5,200
Overhead applied           412,000    314,400
Actual Manufaturing Overhead           385,000    312,000
Difference             27,000         2,400
Overapplied Overapplied
Add a comment
Know the answer?
Add Answer to:
Joy Enterprises ?YE) uses a job costing system that requires the annual calculation of predetermined rates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Lowell Company uses a normal job-costing system at its Minneapolis plant. The plant has a...

    The Lowell Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assembly department. Its job-costing system has two direct-cost categories (direct materials and direct manufacturing labor, and two manufacturing overhead cost pools (the machining department overhead allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017 budget for the plant is as follows: (Click the icon to...

  • Walker Enterprises, Inc., uses a job-order costing system and sets a predetermined overhead rate at the...

    Walker Enterprises, Inc., uses a job-order costing system and sets a predetermined overhead rate at the beginning of each year based on estimated manufacturing overhead costs. Each job requires work in both the Assembly and Machining Departments. The predetermined overhead rate is based on direct labor cost in Assembly Department and on machine hours in Machining Department. At the beginning of the year, the company made the following estimates: Assembly Department $120,000 Machining Department $32,000 Direct labor cost Manufacturing overhead...

  • The Luke Company uses a normal job-costing systern at its Minneapolis plant. The plant has a...

    The Luke Company uses a normal job-costing systern at its Minneapolis plant. The plant has a machining department and an asserbly department. Its job-costing system has two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017 budget for the plant is as follows: (Click the icon to...

  • 4-31 Job costing, accounting for manufacturing overhead, budgeted rates. The Fasano Company uses a job-costing system...

    4-31 Job costing, accounting for manufacturing overhead, budgeted rates. The Fasano Company uses a job-costing system at its Dover, Delaware, plant. The plant has a machining department and a finishing department. Fasano uses normal costing with two direct-cost categories (direct materials and direct manu. facturing labor) and two manufacturing overhead cost pools (the machining department with machine. hours as the allocation base, and the finishing department with direct manufacturing labor costs as the allocation base). The 2011 budget for the...

  • 4-25 Job cesting, accounting for manufacturing overhead, budgeted rates. The Matthew Company uses a normal job-costing...

    4-25 Job cesting, accounting for manufacturing overhead, budgeted rates. The Matthew Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assem- bly department. Its job-costing system has two direct-cost categories (direct materials and direct manufac- turing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017...

  • Question 2 (Job costing, accounting for manufacturing overhead rates) 25 Marks) The Matthew Company uses a...

    Question 2 (Job costing, accounting for manufacturing overhead rates) 25 Marks) The Matthew Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assembly department. Its job- costing system has two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The...

  • Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department,...

    Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The following information relates to the year just ended: Machining Department Assembly Department Budgeted manufacturing overhead $ 4,000,000 $ 3,024,000 Actual...

  • The Lowell Company uses a normal job-costing system at its Minneapolis plant. The plant has a...

    The Lowell Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assembly department. Its job-costing system has two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017 budget for the plant is as follows: E (Click the icon...

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 54,500 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost 2 ? $1,533,500 Job Omega Direct materials Direct...

  • Landen Corporation uses a job-order costing system. At the beginning of the year, the company made...

    Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 140,000 70,000 $ 784,000 $ 2.00 $ 4.00 During the year, Job 550 was started and completed. The following information is available with respect to this job: Direct materials Direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT