42) C
Value added time = Process A Time + Process B Time = 12+ 6 = 18 min
43) B
The non-value added time is 0.5 days which is a delay
44) A
The focus should be on reducing delay as it is the non-value added activity
45) D
The triangles are non-value added steps in the entire process
help, please! idk how to do them. OBLEM E-4 Questions he following represents a portion of...
Calculate Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials...
Compute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials...
Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 61 units. The process time for each step is as follows: Process Step 1 6 minutes Process Step 2 8 minutes Process Step 3 5 minutes Process Step 4 4 minutes The time required to move each batch between steps is 15 minutes. In addition, the time to move raw materials to Process Step...
Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step...
Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 64 units. The process time for each step is as follows: Process Step 1 7 minutes Process Step 2 5 minutes Process Step 3 4 minutes Process Step 4 9 minutes The time required to move each batch between steps is 14 minutes. In addition, the time to move raw materials to Process Step...
QUESTION 21 (10 points) ‐ Overall Equipment Effectiveness (OEE) QUESTION 21 (10 points) Overall Equipment Effectiveness (OEE) A copy machine is available 20 hours a day. On a typical day, the machine needs to process 360 jobs. Each job takes about 1.5 minutes on the machine, 0.5 minute of which is processing time and 1 minute is setup time (logging in, defining the job). About 30% of the jobs need to be reworked, in which the set-up time and the...
4. During the most recent month at Hybarger Corporation, queue time was 3.0 days, inspection time was 0.8 day, process time was 2.8 days, wait time was 11.8 days, and move time was 0.6 day. Required: (15%) a. Compute the throughput time. b. Compute the manufacturing cycle efficiency (MCE). c. What percentage of the production time is spent in non-value-added activities? d. Compute the delivery cycle time.
Acct 202... idk what the other boxes are, help me fill them with explanations to how you got the answers! Required Information [The following information applies to the questions displayed below) Sierra Company manufactures soccer balls in two sequential processes: Cutting and Stitching. All direct materials enter production at the beginning of the Cutting process. The following information is available regarding its May inventories: Raw materials inventory Work in process inventory-Cutting Work in process inventory-Stitching Finished goods inventory Beginning Inventory...
Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC boand assembly operation, a number。individuals are esponsible for assenting electronic components into pn te i ut boards. Each operator s es ons le r so den g e net erdg to a given set of instructions. Operators work on batches of s0 printed dircuit boards. Each board requires 4 minutes of board assembly time. After each...
2. Schlarbaum Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Wait time Inspection time Process time Move time Queue time Days 11.7 0.5 1.2 0.2 2.4 Required: a. Compute the throughput time. (Round your answer to 1 decimal places.) b. Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage.) c. What percentage of the...