Question

Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a...

Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 61 units. The process time for each step is as follows:

Process Step 1 6 minutes
Process Step 2 8 minutes
Process Step 3 5 minutes
Process Step 4 4 minutes

The time required to move each batch between steps is 15 minutes. In addition, the time to move raw materials to Process Step 1 is also 15 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 15 minutes.

The new lean layout will allow the company to reduce the batch sizes from 61 units to 4 units. The time required to move each batch between steps and the inventory locations will be reduced to 3 minutes. The processing time in each step will stay the same.

Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the present and proposed production approaches. If required, round percentages to one decimal place.

Present Approach Proposed Approach
Value-added time min min
Non-value-added time min min
Total lead time min min
Value-added ratio (as a percent) % %
0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER:

As per the given Question

Present Approach

Value added time = Process time Step 1 + Process time Step 2 + Process time Step 3 + Process time Step 4

= 6 + 9 + 4 + 8 = 27 minutes

Non-value added time = Total within batch wait time + Move time

= [Total time required for four steps *(Batch size -1)] + Move time

= [27 * (70-1)] + 60 mins

= 1,923 minutes

Total lead time = Value added time + Non-value added time

= 27 + 1,923 = 1,950 minutes

Value added ratio = Value added time / Total lead time

= 27 / 1,950 = 1.4%

Proposed Approach

Value added time = Process time Step 1 + Process time Step 2 + Process time Step 3 + Process time Step 4

= 6 + 9 + 4 + 8 = 27 minutes

Non-value added time = Total within batch wait time + Move time

= [Total time required for four steps *(Batch size -1)] + Move time

= [27 * (4-1)] + 10 mins

= 91 mins

Total lead time = Value added time + Non-value added time

= 27 + 91 = 118 mins

Value added ratio = Value added time / Total lead time

= 27 / 118 = 22.9%

Thank you for given Question......kindly rate.......it helps me a lot

Add a comment
Know the answer?
Add Answer to:
Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in f...

    Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step...

  • Compute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing...

    Compute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials...

  • Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a...

    Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 64 units. The process time for each step is as follows: Process Step 1 7 minutes Process Step 2 5 minutes Process Step 3 4 minutes Process Step 4 9 minutes The time required to move each batch between steps is 14 minutes. In addition, the time to move raw materials to Process Step...

  • Calculate Lead Time Williams Optical Inc. is considering a new lean product cell. The present man...

    Calculate Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials...

  • Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the...

    Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 60 parts. A part requires 3 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The...

  • Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the...

    Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 2 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The...

  • Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 80 parts. A part requires 3 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 3 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 40 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Calculate Lead Time Michigan Machining Company machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Michigan Machining Company machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 4 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes. Under the lean manufacturing philosophy, the part is produced in a cell that includes both the milling...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT