Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the...

Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 2 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes.

Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 6 parts and the move time is eliminated.

Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place.

Traditional Philosophy Lean Manufacturing Philosophy
Value-added time min min
Non-value-added time min min
Total lead time min min
Value-added ratio (as a percent) % %
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Traditional Philosophy Lean Manufacturing Philosophy
Value-added time(6+2) 8 min 8 min
Non-value-added time(8*(70-1)+7),(8*(6-1)) 559 min 40 min
Total lead time 567 min 48 min
Value-added ratio (as a percent)(8/567*100),(8/48*100)               1.41 %                 16.67 %
Non-Value Added time = Value Added time X (Batch size - 1) + Move time
Add a comment
Know the answer?
Add Answer to:
Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the...

    Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 60 parts. A part requires 3 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The...

  • Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 80 parts. A part requires 3 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 3 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 40 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Calculate Lead Time Michigan Machining Company machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Michigan Machining Company machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 4 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes. Under the lean manufacturing philosophy, the part is produced in a cell that includes both the milling...

  • Chapter 12 - Homework eBook Calculator Print Item Calculate Lead Time Flint Fabricators Inc. machines metal...

    Chapter 12 - Homework eBook Calculator Print Item Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 60 parts. A part requires 3 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in...

  • Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing Parts are produced in batch sizes of 65 parts. A part requires 5 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 9 minutes Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a...

    Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 61 units. The process time for each step is as follows: Process Step 1 6 minutes Process Step 2 8 minutes Process Step 3 5 minutes Process Step 4 4 minutes The time required to move each batch between steps is 15 minutes. In addition, the time to move raw materials to Process Step...

  • Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in f...

    Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step...

  • Compute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing...

    Compute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT