Question

Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufactur

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER

Traditional Philosophy Lean Manufacturing Philosophy

Value-added time

3+9 =12

3+9 =12

Non-value-added time

12*(50-1)+10=598

12*(4-1) =36

Total lead time

598+12=610

12+36=48

Value-added ratio (as a percent)

12/610*100 = 1.96%

12/48*100=25%

_____________________________________________

If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.

*****************THANK YOU**************

Add a comment
Know the answer?
Add Answer to:
Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 80 parts. A part requires 3 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the...

    Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 60 parts. A part requires 3 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The...

  • Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the...

    Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 2 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The...

  • Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 40 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Calculate Lead Time Michigan Machining Company machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Michigan Machining Company machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 4 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes. Under the lean manufacturing philosophy, the part is produced in a cell that includes both the milling...

  • Chapter 12 - Homework eBook Calculator Print Item Calculate Lead Time Flint Fabricators Inc. machines metal...

    Chapter 12 - Homework eBook Calculator Print Item Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 60 parts. A part requires 3 minutes in milling and 6 minutes in finishing. The move time between the two operations for a complete batch is 7 minutes. Under the lean philosophy, the part is produced in...

  • Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Calculate Lead Time Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing Parts are produced in batch sizes of 65 parts. A part requires 5 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 9 minutes Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Calculate Lead Time Williams Optical Inc. is considering a new lean product cell. The present man...

    Calculate Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials...

  • Compute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing...

    Compute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials...

  • Lead Time Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed...

    Lead Time Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT