1 Consider saturation headway knowledge and the data in the table below (Heavy vehicles are denoted by an H).


1 Consider saturation headway knowledge and the data in the table below (Heavy vehicles are denoted by an H). 

image.png

 A. What is the saturation headway from the data in the table?

 B. What is the corresponding saturation flow rate for the data in the table?

 C. What is the ideal saturation flow rate?

 D. What is the average start-up lost time per phase?

 E. If the approach has 34.5 seconds of effective green time from a 60 second cycle what is an estimate of the approach capacity?


2 Consider a two-phase intersection with a 75 second cycle length and the start-up and clearance lost times per phase listed below. a) How much time is actually available to move vehicles in a 1-hour period? and b) If the saturation headway is 2.2 seconds what is the maximum number of that vehicles can be accommodated per hour? c) repeat a & b assuming a 60 second cycle length d) discuss 

image.png

3 0
Add a comment Improve this question Transcribed image text
Answer #1

2)

A)

Step1: find effective time available for movement of vehicle per a cycle(gi)

step2: find no of cycles in one hour=(3600/cycle time)

step3: total available time in hour for vehicle movement = (gi *no of cycles)

ten oota ISA1Sc 31 S tea : 1.qsce ·le8 : 2 sec COTie avai la ble a velicle to ove in hour S- 91 )- (3142) 6 Sec or Cycte Cb) available e NO.da cycles In 1hour 売r l cgele 60-12-lt 19)-(31+9. So.qsee Time availabeorho 9160): 30Su Ke 1636.36 X 150-2

D)If we compare the both the results fo 75sec cycle length and 60sec cycle length, when cycle is 60sec have more time losses. Actual time available for movement of vehice is very less and due to this lane can accommodate less no of vehicles per one hour.

Thank you

Add a comment
Know the answer?
Add Answer to:
1 Consider saturation headway knowledge and the data in the table below (Heavy vehicles are denoted by an H).
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • An approach at a pretimed signalized intersection has a saturation flow rate of 2000 veh/h

    An approach at a pretimed signalized intersection has a saturation flow rate of 2000 veh/h and is allocated 15 seconds of effective green in a 60-second signal cycle. If the flow at the approach is 300 vel/h, provide an analysis of the intersection assuming D/D/1 queuing. a. The time to queue clearance after the start of the effective green b. The Proportion of cycle with a queue c. The proportion of vehicles stopped d. The Maximum number of vehicles in the queue e. The total...

  • 1. What is the flow rate if the average headway between 100 vehicles is 5 seconds?...

    1. What is the flow rate if the average headway between 100 vehicles is 5 seconds? 2. What is the difference between time-mean speed and space-mean speed? 3. How would you observe the speed, flow, and density of a roadway? Using Greenshields, what is the speed of traffic if the free flow speed is 70 miles per hour, the current density is 70 vehicles per mile, and the jam density is 70 vehicles per mile? 4. What is the speed...

  • 6- At the beginning of an effective red, vehicles are arriving at an approach at the...

    6- At the beginning of an effective red, vehicles are arriving at an approach at the rate of 600 veh/h and 18 vehicles are left in the queue from the previous cycle (at the end of the previous cycle’s effective green). However, due to the end of a major sporting event, the arrival rate is continuously increasing at a constant rate of 150 veh/h/min (after 1 minute the arrival rate will be 750 veh/h, after 2 minutes 900 veh/h, etc.)....

  • The saturation flow rate for an intersection approach is 3600 veh/h. At the beginning of a...

    The saturation flow rate for an intersection approach is 3600 veh/h. At the beginning of a cycle (effective red) no vehicles are queued. The signal is timed so that when the queue (from the continuously arriving vehicles) is 13 vehicles long, the effective green begins. If the queue dissipates 8 seconds before the end of the cycle and the cycle length is 60 seconds, what is the arrival rate, assuming D/D/1 queuing? Draw D/D/1 queuing diagram and label accordingly ??...

  • (15 points) Assume that all volumes shown have been converted to compatible through-car equivalent" values for...

    (15 points) Assume that all volumes shown have been converted to compatible through-car equivalent" values for the conditions shown. The phase plan in given in the following. Assume that critical volumes reverse in the other daily peak hour. The Saturation headway is 2 s/veh, start- up lost time is 1.5 s, clearance lost time is 2 s, Cycle length is 90s, only critical volumes shown and all volumes in tvu/h. Please determine: a. Find the appropriate number of lanes for...

  • SKAB / SKAA 3842 - 3- Q2. (a) Table Q2 below gives the flow and saturation...

    SKAB / SKAA 3842 - 3- Q2. (a) Table Q2 below gives the flow and saturation flow for all approaches (in pcu/hr) at unsignalised junction in Kluang district. The influence of heavy vehicles, turning movements and all other factors have already been considered. All approaches consist of one exclusive right turn lane (RT), one straight-through traffic (ST) and one straight- through shared with left turn (STLT). Table Q2: Traffic volume at unsignalised junction in Kluang district Approach NORTH SOUTH WEST...

  • An intersection has three phases, and the information for that intersection is provided in the ta...

    An intersection has three phases, and the information for that intersection is provided in the table below. Calculate: The sum of the flow ratios for the critical lane groups Minimum cycle length, optimal cycle length and effective green time for each phase using the minimum cycle length assuming the lost time is 4 seconds per phase and the critical intersection v/c of 0.90 is desired. The northbound approach delay and level of service. Phase 1 2 3 Allowed Movements NB...

  • 1:04 AM Homework 3 PDF-154 KB Verizon LTE A signainod intcnection approach bas a saturation flow...

    1:04 AM Homework 3 PDF-154 KB Verizon LTE A signainod intcnection approach bas a saturation flow eate of 1200 pogIn ifbe approach three lanes, and the signal has a 40grm time within a 70 sec cycle length what is the capecity of this approach? (I lint The equation t° calculate capacity for das pooblem B presented m Lact-7) Taffk volumes on a four-lane freeway (wo lanes in each direction) wene oounted manually from an overhcad location, rcsoing in the data...

  • Question 4 1 pts A physics student records the data in the table below during a...

    Question 4 1 pts A physics student records the data in the table below during a 1-D motion experiment with constant acceleration. Unfortunately he forgets to properly label the table before emailing it to his lab partners for analysis. As a result, they have to use their knowledge of kinematics to figure out how the table is organized and what the rows and columns represent. Use your knowledge of kinematics to select the correct answer below. Assume that all units...

  • Consider the three graphs below, which show the quantity of DNA in cells measured by fluorescence...

    Consider the three graphs below, which show the quantity of DNA in cells measured by fluorescence in flow cytometry. The x-axis represents the relative amount of DNA per cell, and the relative intensity of the florescence on the y-axis represents the number of cells with that amount of DNA in the cell. Look at the experiment shown on page 248 of your textbook. 1) A B C 2) 20-40,一60一助100 20-40 60一負100 40, 60 N 100 Amount of fluorescence per cell...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT