Question

(15 points) Assume that all volumes shown have been converted to compatible through-car equivalent values for the conditions

0 0
Add a comment Improve this question Transcribed image text
Answer #1

So we have a two phase signal.

saturation headway = 2 sec/vehicle . Therfore saturation flow = 3600/2 = 1800 pcu/rhr/ln

Since saturation flow is 1800 at minimum for EB/WB we need two lanes, and we will start with one lane on NB/SB

I am assumign that in all my scenarios the # of lanes on EB=WB and # of lanes on NB =SB

Assume that PHF = 1 to start with.

Also we are given total lost time = start up lost time + clearance lost time = 3.5 seconds/phase.

So total lost time per cycle = 3.5 *2 = 7 seconds

Cycle Length = 90 seconds

Assume that the intersection operates

We know from formulas that Cminimum is given by

LEX Cmin LEX Χ. - Υ. Χ. - Σ. (3).

So assume that at worst intersection is at full capacity and Xc = 1, so Cmin = L/(1- sum of critical flow ratios) = 90

so 90 = 7(1-sum of critical flow ratios)

Therefore at worst case sum of critical flow ratios should be equal to 1-7/90 = 0.9222

So we can set up our phase, lane group and flow ratio table as follows

# of Saturation lanes Flow/lane Total Saturation Flow Given Peak Hour Flow Design Flow tvu = peak hour flow/PHF Flow Ratio =

So this WILL NOT WORK, since sum of critical flow ratios = 1.111

The sum of critical flow RATIOS must be less than 1, and at max it should be 0.9222

So try another combination by increasing the number of lanes on NB and SB to 2 lanes each

# of Saturation lanes Flow/lane Total Saturation Flow Given Peak Hour Flow PHF Design Flow tvu = peak hour flow/PHF Flow Rati

The above combination works

Sum of critical flow ratios = 0.833 which is less than .922

THEFORE 2 LANES ARE REQUIRED IN EACH DIRECTION IN EACH APPROACH.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------

B) Now we have a scenario with 4 lanes each direcion in E-W and 3 lanes each direction in N-S

In this case we have the following table

# of Saturation lanes Flow/lane Total Saturation Flow Given Peak Hour Flow PHE Design Flow tvu = peak hour flow/PHE Flow Rati

So sum of critical flow ratios = 0.463

So absolute minimum cycle length is Cmin = L/(1- sum of critical flow ratios) = 7(1-.463) = 13.03 seconds.

Maybe you can round it up to 15 seconds

------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

c) Now we have 4 lanes each in E-W and 4 lanes in N-S

Also we are given PHF = 0.90

# of Saturation lanes Flow/lane Total Saturation Flow Given Peak Hour Flow PHE Design Flow tvu = peak hour flow/PHF Flow Rati

We are given V/C ratio = 0.90 Therefore that means Xc = 0.90

Cycle Length according to HCM formula and based on Xc is given by

LEX Cmin LEX Χ. - Υ. Χ. - Σ. (3).

So we have minimum cycle length for getting v/c = 0.90

= 7 * 0.90/(0.90- .439) = 13.66 seconds

So round it up to 15 seconds

-------------------------------------------------------------------------------------------------------------------------------

d) For this we go back to our original problem, where cycle length = 90 seconds

Effective Green = Green time + yellow time - lost time = 20 + 5 - 7 = 18 seconds

so effective green for Phase 1 (i.e EB/WB approach) = critical flow ratio/sum of critical flow ratios * 18

= 0.292/.439 * 18 = 11.972 seconds

so we have saturation flow = 1800 pcu/hr/lane

Cycle Length = 90 seconds

Effective green per cycle = 11.972 seconds

so total effective green time which WB gets in one hour = 3600/90 * 11.972 = 478.88 seconds

So lane capacity = 1800 pcu/hr/lane 478.88/3600 = 239.44 vehicles/hour/lane

So capacity of WB approach assumeing green time is 20 second and cycle length is 90 seconds is 240 vehicles/hour

==================================================================

Please rate +vely to support us and encourage us to keep giving quality solutions. Thanks

Add a comment
Know the answer?
Add Answer to:
(15 points) Assume that all volumes shown have been converted to compatible through-car equivalent" values for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. For the traffic characteristics shown below, determine suitable phase lengths for the intersection using the...

    4. For the traffic characteristics shown below, determine suitable phase lengths for the intersection using the Webster method. For each approach, assume one dedicated left-turn lane, one through lane, and one through-right lane North A South A h East A Left Tunm Through Movement Right Turn 135 415 138 162 559 167 West Approach 135 514 370 131 -PHF = 0.95 Left-turn factor 1.4 -Right-turn factor-1.0 -PCE for buses and trucks =1.6 -Truck percentage-3% for westbound traffic and zero otherwise...

  • 4.A two-phase signal system is to be designed for an isolated intersection with a peak hour tacto...

    Transportation Can correct the answer 4.A two-phase signal system is to be designed for an isolated intersection with a peak hour tactor 81 0.99. TIL lane volumes are: Phase A-550 veh/hr, Phase B 600 veh/hr, The total lost time L is 14 sec. Determine an appropriate cycle length for the intersection that will satisfy the following conditions: minimum cycle length-45 sec, maximum cycle length = 120 sec, maximum critical ve ratio (Xc)-0.85 and The saturation flow per lane for each...

  • 3- Consider the third example solved in the lecture videos. Two additional 12-ft through lanes are...

    3- Consider the third example solved in the lecture videos. Two additional 12-ft through lanes are added to Vine Street (the street in the intersection of the first example solved in the lecture videos), one lane in each direction. If the peak-hour traffic volumes are unchanged but the Vine Street left-turn saturation flow rates increase by 120 veh/h because of the added through lanes, what would the revised effective green time, yellow time, and all-red time be for each phase?...

  • 4- Consider Problem 3. Calculate the new minimum pedestrian green time, assuming the effective crosswalk width...

    4- Consider Problem 3. Calculate the new minimum pedestrian green time, assuming the effective crosswalk width is 6 ft and the maximum number of crossing pedestrians in any phase is 20. This is the problem 3 Two additional 12-ft through lanes are added to Vine Street, one lane in each direction. If the peak-hour traffic volumes are unchanged but the Vine Street left-turn saturation flow rates increase by 120 veh/h because of the added through lanes, what would the revised...

  • A pretimed signal controls a four-way intersection with no turning permitted and zero lost time.

    A pretimed signal controls a four-way intersection with no turning permitted and zero lost time. The eastbound and westbound traffic volumes are 500 and 600 veh/h. respectively, and the two movements share the same effective green and effective red portions of the cycle. The northbound and southbound directions also share cycle times, with volumes of 650 and 300 veh/h. If the saturation flow of castbound and westbound approaches is 2100 veh/h, and the saturation flow of northbound and southbound approaches...

  • 1:04 AM Homework 3 PDF-154 KB Verizon LTE A signainod intcnection approach bas a saturation flow...

    1:04 AM Homework 3 PDF-154 KB Verizon LTE A signainod intcnection approach bas a saturation flow eate of 1200 pogIn ifbe approach three lanes, and the signal has a 40grm time within a 70 sec cycle length what is the capecity of this approach? (I lint The equation t° calculate capacity for das pooblem B presented m Lact-7) Taffk volumes on a four-lane freeway (wo lanes in each direction) wene oounted manually from an overhcad location, rcsoing in the data...

  • An intersection has a four-phase signal with the movements allowed in each phase

     An intersection has a four-phase signal with the movements allowed in each phase and the corresponding analysis and saturation flow rates shown in the table below. Please complete the following: a. Calculate the sum of flow ratios for the critical lane groups.  b. Calculate the minimum cycle length and effective green time for each phase (balancing v/c ratio for each lane group). Assume the lost time is 4 sec/phase and a critical intersection vc ratio of 0.95 is desired. c. Calculate the optimal...

  • 2. Determine the minimum cycle length for the intersection with the volumes shown on the table...

    2. Determine the minimum cycle length for the intersection with the volumes shown on the table below. The intersection is designed to have the following three phases: Phase A for left-turn movements from the EB and WB approaches; Phase B for the through and right movements from the EB and WB approaches; Phase C serving all movements for the NB and SB approaches. EB approach WB approach N B approach SB approach LT RLT RL TRL TR 110 500 200...

  • Description D to solve Questions 12-14 An intersection has a four-timing-stage signal with the movements allowed...

    Description D to solve Questions 12-14 An intersection has a four-timing-stage signal with the movements allowed in each timing stage and corresponding analysis and saturation flow rates shown in Table below. Timing stage 1 2 3 4 Allowed movements EB L, WBL EB T/R, WB T/R SB L, SB T/R NB L, NB T/R Analysis Flow rate 245, 230 veh/h 975,1030 veh/h 255,235 veh/h 225,215 veh/h Saturation flow rate 1750, 1725 veh/h 3350,3400 veh/h 1725,1750 veh/h 1700, 1750 veh/h Question...

  • The intersection has a four-timing-state signal with the movements allowed in each timing stage a...

    the intersection has a four-timing-state signal with the movements allowed in each timing stage and corresponding analysis and saturation flow rates shown in the table. a) calculate the minimum cycle length and effective green time for each timing stage (balancing v/c for the critical lane groups). assume the lsot time is 4 seconds per timing stage and a criticsl intersection v/c of 0.9 is desired. b) calculate the intersection control delay and level of service, assumjng pre-times isolated intersection. 4...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT