Question

SKAB / SKAA 3842 - 3- Q2. (a) Table Q2 below gives the flow and saturation flow for all approaches (in pcu/hr) at unsignalise

0 0
Add a comment Improve this question Transcribed image text
Answer #1

It will be a four phase signal as shown below

North approach means SB, West aproach means EB, so i have kept it in the same order as in the question

First phase is North approach i.e SB

Phase 1 SBL/T SBT Phase 2 SBR NBL/T NBT NBR Phase 3 EBLT EBT/R EBR WBL/T WBT WBR Phase 4

so lets calculate the flow ratio and critical flow ratios for different lane groups.

Critical Flow Saturation Flows/lane Total # of lanes Saturation Flow Given Peak Hour Flow Ratio Flow Ratio 215 0.126 0.112 Ph

So sum of critical flow ratios = 0.581

max critical ratio is 0.176 which is less than 0.85

According to ATJ 13/87 method

Intergreen time = Red + amber

= we can calculate it out

Lost time per phase = Driver Reaction Time + Amber Time

So we can calculate, intergreen and lost time for each phase as follows

ATJ 13/87 method Amber Time Start up Lost time Red Time Intergreen lost time (total/phase) 3.0 2.0 5.0 2.0 5.0 3.0 2.0 5.0 2

Optimum Cycle Time

C = (1.5L + 5)/(1-Y)

where L = total lost time per cycle

Y = sum of critical flow ratios

so C = ((1.5 *20) + 5)/(1-.581) = 35/.419 = 83.53 secs so round it up to 85 seconds

So Cycle Length = 85 seconds

---------------------------------------------------------------------------------------------------------------------------------------------

Effective Green time for entire cycle = Cycle length - total lost time = 85 - 20 = 65 seconds

so now we can calculate effective green for each phase

Effective green for phase1 = critical flow ratio for phase1/sum of all critical flow ratios * total effective green for entire cycle = .126/.581 * 65 = 14.1 seconds.

So we have for all phases as follows

ATJ 13/87 method Eff. Saturation Flows/lane Flow Ratio Critical Flow Ratio Amber Time Start up Lost time Red Time Intergreen

So we have the following phasing and timing plan

Phase 1 Phase 2 Phase 3 Phase 4 3.1 3 2 15 3 2 187 33 176 3 3| includes stave ub lost time

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Other possible phase combinations involve protected lefti-turns. For example you can have

Phase 1 Phase 2 EBL WBL EBT/R WBT/R NBL SBL NBT/R SBT/R Phase 3 Phase 4

However in this problem the through flows and left-turns are almost of the same magnitude, so perhaps allowing protected left-turns maynot have that much of an impact. Also for this you need to separate the left-turn flow from the through-flow, which is not possible from the given data, unless you get it directly from the survey counts.

So I would recommend to keep it at split phasing on all four approaches.

Add a comment
Know the answer?
Add Answer to:
SKAB / SKAA 3842 - 3- Q2. (a) Table Q2 below gives the flow and saturation...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For the given intersection, lost time is equal to 3.5 sec per phase and Y+AR is equal to 3 sec. W...

    For the given intersection, lost time is equal to 3.5 sec per phase and Y+AR is equal to 3 sec. Width of each lane is 10 feet. Estimate the signal timings for the intersection assuming a four phase operation. Phase A: serves north - south left turns only Phase B: serves north - south traffic (no left turns permitted) Phase C: serves east - west left turns only Phase D: serves east - west traffic (no left turns permitted) Assume...

  • 4. For the traffic characteristics shown below, determine suitable phase lengths for the intersection using the...

    4. For the traffic characteristics shown below, determine suitable phase lengths for the intersection using the Webster method. For each approach, assume one dedicated left-turn lane, one through lane, and one through-right lane North A South A h East A Left Tunm Through Movement Right Turn 135 415 138 162 559 167 West Approach 135 514 370 131 -PHF = 0.95 Left-turn factor 1.4 -Right-turn factor-1.0 -PCE for buses and trucks =1.6 -Truck percentage-3% for westbound traffic and zero otherwise...

  • A pretimed signal controls a four-way intersection with no turning permitted and zero lost time.

    A pretimed signal controls a four-way intersection with no turning permitted and zero lost time. The eastbound and westbound traffic volumes are 500 and 600 veh/h. respectively, and the two movements share the same effective green and effective red portions of the cycle. The northbound and southbound directions also share cycle times, with volumes of 650 and 300 veh/h. If the saturation flow of castbound and westbound approaches is 2100 veh/h, and the saturation flow of northbound and southbound approaches...

  • 3- Traffic Light Controller The diagram of figure 4 implified traffic light controll ents an intersection...

    3- Traffic Light Controller The diagram of figure 4 implified traffic light controll ents an intersection of a main road (North-South) and a side road (East-West). The er cycles the light (Red, Yellow, and Green) every one minutes for the side road and every three minutes. for the mairn Assuming t ming that a Llso, the controller ensures that the Red (N-S) and Red (EW) lasts for three l minute clock source is available, then NSREO NSYELLOW NSGREEN NSRED NSYELLOW...

  • What is the difference between actual green time and effective green time A They are the...

    What is the difference between actual green time and effective green time A They are the same, just different naming terminologies B Actual green time include lost times while effective green time esclude lost times C. Actual green time include pedestrian time while effective green does not D. One is calculated using Highway Capacity while the other in Wester Method Ideal (base) sauration flow rate is taken as So - 1.900 pphalThis value (1900) onte as dividing 3600 by Aspeed...

  • Database Intro Salesmen Sheet Order_info Sheet Business_Info sheet 1.Create your own table design based on the...

    Database Intro Salesmen Sheet Order_info Sheet Business_Info sheet 1.Create your own table design based on the Excel data, and include all relationships (joins). Apply referential integrity rules wherever appropriate. Import the data from Excel to Access to populate tables: 1. Use the Chen technique and illustrate the E-R diagram for the tables you created Note: It may be necessary to change the data composition due to normalization issues, if you change the composition detail how and why; (you may find...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT