For the given intersection, lost time is equal to 3.5 sec per phase and Y+AR is equal to 3 sec. Width of each lane is 10 feet.
Estimate the signal timings for the intersection assuming a four phase operation.
Phase A: serves north - south left turns only
Phase B: serves north - south traffic (no left turns permitted)
Phase C: serves east - west left turns only
Phase D: serves east - west traffic (no left turns permitted) Assume the prevailing saturation flows as follows: s(TH+RT) = 1600; s(LT) = 1200
For the given intersection, lost time is equal to 3.5 sec per phase and Y+AR is equal to 3 sec. W...
4. For the traffic characteristics shown below, determine suitable phase lengths for the intersection using the Webster method. For each approach, assume one dedicated left-turn lane, one through lane, and one through-right lane North A South A h East A Left Tunm Through Movement Right Turn 135 415 138 162 559 167 West Approach 135 514 370 131 -PHF = 0.95 Left-turn factor 1.4 -Right-turn factor-1.0 -PCE for buses and trucks =1.6 -Truck percentage-3% for westbound traffic and zero otherwise...
SKAB / SKAA 3842 - 3- Q2. (a) Table Q2 below gives the flow and saturation flow for all approaches (in pcu/hr) at unsignalised junction in Kluang district. The influence of heavy vehicles, turning movements and all other factors have already been considered. All approaches consist of one exclusive right turn lane (RT), one straight-through traffic (ST) and one straight- through shared with left turn (STLT). Table Q2: Traffic volume at unsignalised junction in Kluang district Approach NORTH SOUTH WEST...