The company has two grades of inspectors, 1 and 2, who are to be assigned for a quality control inspection. It is required that at least 1,800 pieces be inspected per 8-hour day. Grade 1 inspectors can check pieces at the rate of 25 per hour, with an accuracy of 98%. Grade 2 inspectors check at the rate of 15 pieces per hour, with an accuracy of 95%. The wage rate of a Grade 1 inspector is $4.00 per hour, while that of a Grade 2 inspector is $3.00 per hour. Each time an error is made by an inspector, the cost to the company is $2.00. The company has available for the inspection job eight Grade 1 inspector, and ten Grade 2 inspectors. The company wants to determine the optimal assignment of inspectors, which will minimize the total cost of the inspection.
Formulation:
Let x1 and x2 be the number of grade-1 and grade-2 inspectors assigned per 8-hour shift.
Cost of labor = $4*8*x1 + $3*8*x1 = 32x1 + 24x2
Cost of quality = 25*8*(1-0.98)*$2*x1 + 15*8*(1-0.95)*$2*x2 = 8x1 +
12x2
So,
Minimize Z = total cost = (32+8)x1 + (24+12)x2 = 40x1 + 36x2
Subject to,
x1 <= 8
x2 <= 10
25*8*x1 + 15*8*x2 >= 1800 i.e. 20x1 + 12x2 >= 180
x1, x2 >= 0
Standard form to begin with the Big-M method
Minimize Z = 40x1 + 36x2 + 0s1 + 0s2 + 0s3 + M.A1
s.t.
x1 + s1 = 8
x2 + s2 = 10
20x1 + 12x2 - s3 + A1 <= 180
x1, x2, s1, s2, s3, A1 >= 0
Iteration-1 | Cj | 40 | 36 | 0 | 0 | 0 | M | ||
B | CB | XB | x1 | x2 | S1 | S2 | S3 | A1 | MinRatio XB/x1 |
S1 | 0 | 8 | (1) | 0 | 1 | 0 | 0 | 0 | 8/1=8→ |
S2 | 0 | 10 | 0 | 1 | 0 | 1 | 0 | 0 | --- |
A1 | M | 180 | 20 | 12 | 0 | 0 | -1 | 1 | 180/20=9 |
Z=180M | Zj | 20M | 12M | 0 | 0 | -M | M | ||
Zj-Cj | 20M-40↑ | 12M-36 | 0 | 0 | -M | 0 |
Positive maximum Zj-Cj is
20M-40 and its column index is 1. So, the entering
variable is x1.
The minimum ratio is 8 and its row index is 1. So, the leaving
basic variable is S1.
So, the pivot element is 1.
Entering =x1, Departing =S1, Key Element =1
Row operations:
Iteration-2 | Cj | 40 | 36 | 0 | 0 | 0 | M | ||
B | CB | XB | x1 | x2 | S1 | S2 | S3 | A1 | MinRatio XBx2 |
x1 | 40 | 8 | 1 | 0 | 1 | 0 | 0 | 0 | --- |
S2 | 0 | 10 | 0 | 1 | 0 | 1 | 0 | 0 | 10/1=10 |
A1 | M | 20 | 0 | (12) | -20 | 0 | -1 | 1 | 20/12=1.667→ |
Z=20M+320 | Zj | 40 | 12M | -20M+40 | 0 | -M | M | ||
Zj-Cj | 0 | 12M-36↑ | -20M+40 | 0 | -M | 0 |
Positive maximum Zj-Cj is
12M-36 and its column index is 2. So, the entering
variable is x2.
The minimum ratio is 1.667 and its row index is 3. So, the leaving
basic variable is A1.
So, the pivot element is 12.
Entering =x2, Departing =A1, Key Element =12
Row operations:
Iteration-3 | Cj | 40 | 36 | 0 | 0 | 0 | |
B | CB | XB | x1 | x2 | S1 | S2 | S3 |
x1 | 40 | 8 | 1 | 0 | 1 | 0 | 0 |
S2 | 0 | 8.3333 | 0 | 0 | 1.667 | 1 | 0.0833 |
x2 | 36 | 1.6667 | 0 | 1 | -1.667 | 0 | -0.0833 |
Z=380 | Zj | 40 | 36 | -20 | 0 | -3 | |
Zj-Cj | 0 | 0 | -20 | 0 | -3 |
Since all Zj-Cj ≤ 0, the
optimal solution is reached and the solution is as follows:
x1 = 8
x2 = 1.67
Min Z = 380
The company has two grades of inspectors, 1 and 2, who are to be assigned for...
United Aluminum Company of Cincinnati produces three grades (high, medium, and low) of aluminum at two mills. Each mill has a different production capacity (in tons per day) for each grade, as follows: Mill Aluminum Grade 1 2 High 6 2 Medium 2 2 Low 4 10 The company has contracted with a manufacturing firm to supply at least 12 tons of high-grade aluminum, 9 tons of medium-grade aluminum, and 5 tons of low-grade aluminum. It costs United $6,000 per...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 Prime costs $11,760,000 $50,400,000 $62,160,000 Machine hours 140,000 700,000 840,000 Engineering hours 3,600 4,000 Receiving orders 300 1,200 Inspection hours 1,800 2,700 400 900 900 Overhead costs: Machining $9,240,000 2,240,000 Engineering Receiving 240,000 Inspecting products 297,000 Required: 1. Calculate the four...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 ------ Prime costs $9,800,000 $44,520,000 $54,320,000 Machine hours 140,000 700,000 840,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours ...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 90,000 270,000 — Prime costs $6,480,000 $30,240,000 $36,720,000 Machine hours 90,000 450,000 540,000 Engineering hours 400 3,600 4,000 Receiving orders 500 1,500 2,000 Inspection hours ...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 $46,800,000 Prime costs $10,800,000 Machine hours 150,000 750,000 $57,600,000 900,000 2,000 200 1,800 Engineering hours Receiving orders Inspection hours 300 900 1,200 800 1,600 2,400 Overhead costs: Machining Engineering $9,000,000 860,000 468,000 Receiving Inspecting products 480,000 Required: 2. Calculate the unit...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 Prime costs 450,000 $46,800,000 750,000 $10,800,000 150,000 $57,600,000 Machine hours 900,000 2,000 200 1,800 Engineering hours Receiving orders 300 1,200 Inspection hours 800 1,600 2.400 Overhead costs: $9,000,000 860,000 Machining Engineering Receiving Inspecting products 468,000 480,000 Required: 1. Calculate the four activity...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Advanced Total Basic 150,000 $12,900,000 450,000 $51,300,000 $64,200,000 150,000 750,000 900,000 Units produced Prime costs Machine hours Engineering hours Receiving orders Inspection hours 300 2,700 3,000 400 1,200 1,600 900 1,800 2,700 $7,200,000 Overhead costs: Machining Engineering Receiving Inspecting products 1,290,000 624,000 405,000 Required: per machine hour 1....
Problem 2: A company wishes to assign multiple machines to an operator to minimize costs The following times have been collected: Loading machine standard time 034 min Unloading machine standard time Walk time between machines Operator rate Machine rate Power feed time (machining time) 0.26 min 0.09 min $15.00/h S22.00/h 1.56 min - 1. 2. 3. 4. 5. Determine the optimal number of machines per operator to minimize unit cost. Create a worker-machine chart. (Suggestion: use Excel or insert a...
Rosehut Olive Oil Company makes two grades of olive oil: standard and extra virgin. Rosehut has identified two activity cost pools, the related costs per pool, the cost driver for each pool, and the expected usage for each pool. Activity Total Activity Cost Cost Driver Standard Extra Virgin Washing, Pressing & Filtering (WPF) $ 1,778,400 Washing, Pressing, and Filtering hours 47,400 hours 108,600 hours Bottling $ 931,500 Number of bottles 324,000 bottles 81,000 bottles Additional information about each grade of...
1) Helio Company has two products: A and B. The annual production and sales of Product A is 1,850 units and of Product B is 1,250 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. Product A requires 0.3 direct labor-hours per unit and Product B requires 0.6 direct labor-hours per unit. The total estimated overhead for next period is $100,485. What is the company’s predetermined overhead rate? 2) Activities Activity...