(1)
Machining | $ 10 | per machine hour |
Engineering | $ 430 | per hour |
Receiving | $ 390 | per order |
Inspecting Products | $ 200 | per hour |
Explanations :-
(A) Overhead cost | (B) Activities | Overhead Rate (A÷B) | |
Machining | $9,000,000 | 900000 | $ 10 |
Engineering | $860,000 | 2000 | $ 430 |
Receiving | $468,000 | 1200 | $ 390 |
Inspecting Products | $480,000 | 2400 | $ 200 |
(2)
Unit cost | ||
Basic | $ 84.42 | per unit |
Advanced | $ 123.88 | per unit |
Overhead cost | ||
Basic | $ 12.42 | per unit |
Advanced | $ 19.88 | per unit |
Explanations :-
Basic | Advanced | |
Prime cost | $10,800,000 | $46,800,000 |
÷ Units produced | 150000 | 450000 |
Prime cost per unit | $72 | $104 |
Add: Overhead cost per unit | $12.42 | $19.88 |
Unit cost | $ 84.42 | $ 123.88 |
(A) Overhead Rate | (B) Basic Activity | Cost assigned to Basic (AXB) | (C) Advanced Activity | Cost assigned to Basic (AXC) | |
Machining | $10 | 150000 | $1,500,000 | 750000 | $7,500,000 |
Engineering | $430 | 200 | $86,000 | 1800 | $774,000 |
Receiving | $390 | 300 | $117,000 | 900 | $351,000 |
Inspecting Products | $200 | 800 | $160,000 | 1600 | $320,000 |
$1,863,000 | $8,945,000 | ||||
÷ Units produced | 150000 | 450000 | |||
Overhead cost per unit | $ 12.42 | $ 19.88 |
(3)
Cost assignment | |
Basic | $ 160,000 |
Advanced | $ 320,000 |
Basic = $480000 * 800/2400 = $160000
Advanced = $480000 * 1600/2400 = $320000
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 $46,800,000 Prime costs $10,800,000 Machine hours 150,000 750,000 $57,600,000 900,000 2,000 200 1,800 Engineering hours Receiving orders Inspection hours 300 900 1,200 800 1,600 2,400 Overhead costs: Machining Engineering $9,000,000 860,000 468,000 Receiving Inspecting products 480,000 Required: 2. Calculate the unit...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Advanced Total Basic 150,000 $12,900,000 450,000 $51,300,000 $64,200,000 150,000 750,000 900,000 Units produced Prime costs Machine hours Engineering hours Receiving orders Inspection hours 300 2,700 3,000 400 1,200 1,600 900 1,800 2,700 $7,200,000 Overhead costs: Machining Engineering Receiving Inspecting products 1,290,000 624,000 405,000 Required: per machine hour 1....
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 130,000 390,000 — Prime costs $9,880,000 $42,120,000 $52,000,000 Machine hours 130,000 650,000 780,000 Engineering hours 500 4,500 5,000 Receiving orders 500 1,500 2,000 Inspection hours 1,000 2,000 3,000 Overhead costs: Machining $8,580,000 Engineering 3,000,000 Receiving 440,000 Inspecting products 360,000 Required: 1. Calculate the...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 90,000 270,000 — Prime costs $6,480,000 $30,240,000 $36,720,000 Machine hours 90,000 450,000 540,000 Engineering hours 400 3,600 4,000 Receiving orders 500 1,500 2,000 Inspection hours ...
eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 Prime costs $12,600,000 $45,000,000 $57,600,000 900,000 Machine hours 150,000 750,000 500 4,500 5,000 Engineering hours Receiving orders Inspection hours 200 600 800 800 1,600 2,400 Overhead costs: Machining Engineering $9,000,000 2,100,000 320,000 Receiving Inspecting products 480,000 Required: 1. Calculate...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 Prime costs $11,760,000 $50,400,000 $62,160,000 Machine hours 140,000 700,000 840,000 Engineering hours 3,600 4,000 Receiving orders 300 1,200 Inspection hours 1,800 2,700 400 900 900 Overhead costs: Machining $9,240,000 2,240,000 Engineering Receiving 240,000 Inspecting products 297,000 Required: 1. Calculate the four...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 ------ Prime costs $9,800,000 $44,520,000 $54,320,000 Machine hours 140,000 700,000 840,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours ...
eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 300,000 100,000 $8,000,000 Prime costs $30,000,000 $38,000,000 Machine hours 100,000 500,000 600,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours 800 1,600 2,400 Overhead costs: Machining Engineering Receiving Inspecting products $6,000,000 2,000,000 560,000 360,000 Required: 1. Calculate...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving and inspection Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 Prime costs $10,500,000 $45,000,000 $55,500,000 Machine hours 150,000 750,000 900,000 Engineering hours 200 1,800 2,000 Receiving orders 300 900 Inspection hours 900 1,800 2,700 1.200 $9,900,000 Overhead costs: Machining Engineering Receiving Inspecting products 980,000 300,000 513,000 2. Calculate the unit costs...
eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 100,000 300,000 Prime costs $8,000,000 $30,000,000 $38,000,000 Machine hours 100,000 500,000 600,000 Engineering hours 400 3.600 4,000 Receiving orders 400 1,600 2.400 800 Inspection hours 1,200 1,600 Overhead costs: Machining Engineering Receiving Inspecting products Required: $6,000,000 2,000,000 560,000 360,000 х Removing...