Answer
1)
Activity Rates
Machining Rate $ 10 per Machine Hours
Engineering Rate $ 430 per Engineering Hours
Receiving Rate $ 390 Receiving Orders
Inspecting Products Rate $ 200 Inspection Hours
Workings:
Total Overheads (a) | Total Activity (b) |
Rate per Activity (a / b) |
|
Machining | $ 9,000,000 | 900,000 Machine Hours | $ 10 per Machine Hours |
Engineering | $ 860,000 | 2,000 Engineering Hours | $ 430 per Engineering Hours |
Receiving | $ 468,000 | 1,200 Receiving Orders | $ 390 Receiving Orders |
Inspecting Products | $ 480,000 | 2,400 Inspection Hours | $ 200 Inspection Hours |
2)
Unit Cost
Basic = $ 84.42 per unit
Advance = $ 123.8781 per unit
Overhead Cost
Basic = $ 12.42 per unit
Advance = $ 19.8781 per unit
Workings:
Computation of Unit Cost Using Activity Rates
Basic | Advance | |
Prime Cost | $ 72 ($10,800,000 / 150,000) |
$ 104 ($46,800,000 / 450,000) |
Overhead Cost | ||
Machining | $ 10 (150,000 hr / 150,000 * $10) | $ 16.667 (750,000 hr / 450,000 * $10) |
Engineering | $ 0.5733 (200 hr / 150,000 * $ 430) | $ 1.72 (1,800 hr / 450,000 * $ 430) |
Receiving | $ 0.78 (300 hr / 150,000 * $ 390) | $ 0.78 (900 hr / 450,000 * $ 390) |
Inspecting Products | $ 1.0667 (800 hr / 150,000 * $ 200) | $ 0.7111 (1,600 hr / 450,000 * $ 200) |
Total Overhead Cost | $ 12.42 | $ 19.8781 |
Unit Cost (Prime Cost+Total Overhead Cost) | $ 84.42 | $ 123.8781 |
3)
Cost Assignment for the inspection Activity
Basic = Inspecting Products / Total Inspection Hours * Inspection Hour for Basic
Basic = $ 480,000 / 2400 Hrs * 800 Hrs = $ 160,000
Advance = Inspecting Products / Total Inspection Hours * Inspection Hour for Advance
Advance = $ 480,000 / 2,400 Hrs * 1,600 Hrs = $ 320,000
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 Prime costs 450,000 $46,800,000 750,000 $10,800,000 150,000 $57,600,000 Machine hours 900,000 2,000 200 1,800 Engineering hours Receiving orders 300 1,200 Inspection hours 800 1,600 2.400 Overhead costs: $9,000,000 860,000 Machining Engineering Receiving Inspecting products 468,000 480,000 Required: 1. Calculate the four activity...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Advanced Total Basic 150,000 $12,900,000 450,000 $51,300,000 $64,200,000 150,000 750,000 900,000 Units produced Prime costs Machine hours Engineering hours Receiving orders Inspection hours 300 2,700 3,000 400 1,200 1,600 900 1,800 2,700 $7,200,000 Overhead costs: Machining Engineering Receiving Inspecting products 1,290,000 624,000 405,000 Required: per machine hour 1....
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 130,000 390,000 — Prime costs $9,880,000 $42,120,000 $52,000,000 Machine hours 130,000 650,000 780,000 Engineering hours 500 4,500 5,000 Receiving orders 500 1,500 2,000 Inspection hours 1,000 2,000 3,000 Overhead costs: Machining $8,580,000 Engineering 3,000,000 Receiving 440,000 Inspecting products 360,000 Required: 1. Calculate the...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 90,000 270,000 — Prime costs $6,480,000 $30,240,000 $36,720,000 Machine hours 90,000 450,000 540,000 Engineering hours 400 3,600 4,000 Receiving orders 500 1,500 2,000 Inspection hours ...
eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 Prime costs $12,600,000 $45,000,000 $57,600,000 900,000 Machine hours 150,000 750,000 500 4,500 5,000 Engineering hours Receiving orders Inspection hours 200 600 800 800 1,600 2,400 Overhead costs: Machining Engineering $9,000,000 2,100,000 320,000 Receiving Inspecting products 480,000 Required: 1. Calculate...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 Prime costs $11,760,000 $50,400,000 $62,160,000 Machine hours 140,000 700,000 840,000 Engineering hours 3,600 4,000 Receiving orders 300 1,200 Inspection hours 1,800 2,700 400 900 900 Overhead costs: Machining $9,240,000 2,240,000 Engineering Receiving 240,000 Inspecting products 297,000 Required: 1. Calculate the four...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 140,000 420,000 ------ Prime costs $9,800,000 $44,520,000 $54,320,000 Machine hours 140,000 700,000 840,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours ...
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving and inspection Information on these activities and their drivers is given below. Basic Advanced Total Units produced 150,000 450,000 Prime costs $10,500,000 $45,000,000 $55,500,000 Machine hours 150,000 750,000 900,000 Engineering hours 200 1,800 2,000 Receiving orders 300 900 Inspection hours 900 1,800 2,700 1.200 $9,900,000 Overhead costs: Machining Engineering Receiving Inspecting products 980,000 300,000 513,000 2. Calculate the unit costs...
eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 300,000 100,000 $8,000,000 Prime costs $30,000,000 $38,000,000 Machine hours 100,000 500,000 600,000 Engineering hours 400 3,600 4,000 Receiving orders 400 1,200 1,600 Inspection hours 800 1,600 2,400 Overhead costs: Machining Engineering Receiving Inspecting products $6,000,000 2,000,000 560,000 360,000 Required: 1. Calculate...
eBook Calculator Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving and inspection. Information on these activities and their drivers is given below. Basic Advanced Total Units produced 100,000 300,000 Prime costs $8,000,000 $30,000,000 $38,000,000 Machine hours 100,000 500,000 600,000 Engineering hours 400 3.600 4,000 Receiving orders 400 1,600 2.400 800 Inspection hours 1,200 1,600 Overhead costs: Machining Engineering Receiving Inspecting products Required: $6,000,000 2,000,000 560,000 360,000 х Removing...