Time Period (Year):                  0             1            2          3          4      

Cash flow:                             -800        -100       300       800      500

Answer: ________

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: 21.3%

A Year Ham to do 0 1 2 3 B Cash Flow $800) ($100) $300 $800 $500 9 IRR 21.3%Α. Year B. Cash Flow 2 3 4 0 1 2 -800 -100 300 800 500 9 IRR =IRR(B2:B6)

Add a comment
Know the answer?
Add Answer to:
Compute the IRR for Project X with the cash flows shown as follows if the appropriate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • IRR Compute the IRR statistic for Project E and note whether the firm should accept or...

    IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent.                         Project E             Time 0 1 2 3 4 5 Cash Flow -$1,000 $350 $480 $520 $300 $100

  • IRR Compute the IRR statistic for Project E and note whether the firm should accept or...

    IRR Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 8 percent.                         Project E             Time 0 1 2 3 4 5 Cash Flow -$1,000 $350 $480 $520 $300 $100

  • Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...

    Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: -$1,000 $350 $480 $520 $300 $100 Cash flow: IRR : :% Should the project be accepted or rejected? O accepted O rejected

  • Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not...

    Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 2 4 Cash flow: -$9,900 $3,7s0 $4,580 $1,920 $2,550 IRR Should the project be accepted or rejected? ассepted Orejected Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project...

  • Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do...

    Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 -$2,900 1 $910 2 $900 3 $800 4 $580 5 $380 Cash flow IRR % Should the project be accepted or rejected? O rejected O accepted

  • Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not...

    Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: Cash flow:-$10,100 $3,850 $4,680 $2,020 $2,650 IRR % Should the project be accepted or rejected? rejected O accepted Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E...

  • s. Understanding the NPV profile Aa Aa If an independent project with conventional, or normal, cash flows is being...

    s. Understanding the NPV profile Aa Aa If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) Year Project W Project x 800 0 - $1,500 -$1,000 $200 $350 600 Project X 2 $350 $500 $400 $600 400 4 $600 $750 Project W 200...

  • The IRR evaluation method assumes that cash flows from the project are reinvested at the same...

    The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $2,750,000. The project's expected cash flows are: Year Year 1...

  • Compute the IRR statistic for Project F. The appropriate cost of capital is 12 percent. (Do...

    Compute the IRR statistic for Project F. The appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: −$10,300 $3,950 $4,780 $2,120 $2,750 Should the project be accepted or rejected? rejected accepted

  • Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not...

    Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 1 Cash flow: -$10,400 $4,000 4 2 $4,830 3 $2,170 $2,800 IRR % Should the project be accepted or rejected? O rejected O accepted

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT